179. Market at Tong Mi.-The work consists of the erection of a market of 36 stalls, but owing to shortage of staff it could not be undertaken during 1933.

Expenditure

Nil.

GENERAL WORKS.

180. Roads.-The undermentioned roads were macadamized, kerbed, channelled and laid to approved levels, the footpaths being paved with granolithic paving or slabs and the necessary improvements made in front of new buildings erected during the year: Sai Kung Road, Shek Ku Lung Road, Sa Po Road, Tak Ku Ling Road, South Wall Road, Prince Edward Road, Fuk Wa Street, Maple Street, Po Kong Road, Cheung Sha Wan Road, Poplar Street, Apliu Street, Fuk Wing Street, Wong Chuk Street, Shek Kip Mi Street, Un Chau Street, Pei Ho Street, Shamshuipo Market, Kwei-lin Street, Kiu Kiang Street, Castle Peak Road, Tai Po Road, Nan Chang Street, Tung Chau Street, Hai-tan Street, Boundary Street, Lung Kong Road.

Expenditure

$74,636.85

181. Drainage:-(a) Training Nullahs.--The invert of the nullah in Sam Tak Road was completed. A nullah with decking was constructed at Castle Peak Road, Wong Uk, and the eastern nullah wall with parapet walling at Lai Chi Kok Nullah was completed.

Expenditure

$38,646.76

(b) Miscellaneous Drainage Works.-New sewers and storm water drains varying in diameter from 66″ to 6", were constructed to a length of 14,761 feet, principally in Shamshuipo, Cheung Sha Wan, Shek Kip Mei, and Kowloon City. The number of drain connections made was 230. Many new gullies were constructed and connected to the existing storm water drainage system.

Expenditure

$112,728.06

182. Miscellaneous.-The following were the principal works executed under this heading :-Formation of pigstye site, west of Kowloon City, Levelling open space at rear of N.K.I.L. 1414, Filling in pool on Crown Land lying between Yu Chau Street and Tai Po Road, Levelling area between Shek Ku Lung Road and Sa Po Road at the rear of Kowloon City Market. Four beacons were constructed on the foothills to the East of Kowloon Bay to replace the existing measured mile.

Expenditure

$2,368.06

183. Water Works. A block of coolie quarters was erected at the Tai Po Road Bungalow, consisting of a brick building with a reinforced concrete roof, providing accommodation for eight

Edit History

2026-05-09 14:42:02 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 45 179. Market at Tong Mi.-The work consists of the erection of a market of 36 stalls, but owing to shortage of staff it could not be undertaken during 1933. Expenditure Nil. GENERAL WORKS. 180. Roads.-The undermentioned roads were macadamized, kerbed, channelled and laid to approved levels, the footpaths being paved with granolithic paving or slabs and the necessary improvements made in front of new buildings erected during the year: Sai Kung Road, Shek Ku Lung Road, Sa Po Road, Tak Ku Ling Road, South Wall Road, Prince Edward Road, Fuk Wa Street, Maple Street, Po Kong Road, Cheung Sha Wan Road, Poplar Street, Apliu Street, Fuk Wing Street, Wong Chuk Street, Shek Kip Mi Street, Un Chau Street, Pei Ho Street, Shamshuipo Market, Kwei-lin Street, Kiu Kiang Street, Castle Peak Road, Tai Po Road, Nan Chang Street, Tung Chau Street, Hai-tan Street, Boundary Street, Lung Kong Road. Expenditure $74,636.85 181. Drainage:-(a) Training Nullahs.--The invert of the nullah in Sam Tak Road was completed. A nullah with decking was constructed at Castle Peak Road, Wong Uk, and the eastern nullah wall with parapet walling at Lai Chi Kok Nullah was completed. Expenditure $38,646.76 (b) Miscellaneous Drainage Works.-New sewers and storm water drains varying in diameter from 66″ to 6", were constructed to a length of 14,761 feet, principally in Shamshuipo, Cheung Sha Wan, Shek Kip Mei, and Kowloon City. The number of drain connections made was 230. Many new gullies were constructed and connected to the existing storm water drainage system. Expenditure $112,728.06 182. Miscellaneous.-The following were the principal works executed under this heading :-Formation of pigstye site, west of Kowloon City, Levelling open space at rear of N.K.I.L. 1414, Filling in pool on Crown Land lying between Yu Chau Street and Tai Po Road, Levelling area between Shek Ku Lung Road and Sa Po Road at the rear of Kowloon City Market. Four beacons were constructed on the foothills to the East of Kowloon Bay to replace the existing measured mile. Expenditure $2,368.06 183. Water Works. A block of coolie quarters was erected at the Tai Po Road Bungalow, consisting of a brick building with a reinforced concrete roof, providing accommodation for eight
Baseline (Original)
Q 45 179. Market at Tong Mi.-The work consists of the erection of a market of 36 stalls, but owing to shortage of staff it could not be undertaken during 1933. Expenditure Nil. GENERAL WORKS. 180. Roads.-The undermentioned roads were macadamized, kerbed, channelled and laid to approved levels, the footpaths being paved with granolithic paving or slabs and the necessary improvements made in front of new buildings erected during the year: Sai Kung Road, Shek Ku Lung Road, Sa Po Road, Tak Ku Ling Road, South Wall Road, Prince Edward Road, Fuk Wa Street, Maple Street, Po Kong Road, Cheung Sha Wan Road, Poplar Street, Apliu Street, Fuk Wing Street, Wong Chuk Street, Shek Kip Mi Street, Un Chau Street, Pei Ho Street, Shamshuipo Market, Kwei-lin Street, Kiu Kiang Street, Custle Peak Road, Tai Po Road, Nan Chang Street, Tung Chau Street, Hai-tan Street, Boundary Street, Lung Kong Road. Expenditure $74,636.85 181. Drainage:-(a) Training Nullahs.--The invert of the nullah in Sam Tak Road was completed. A nullah with decking was constructed at Castle Peak Road, Wong Uk, and the eastern nullah wall with parapet walling at Lai Chi Kok Nullah was com- pleted. Expenditure $38,646.76 (b) Miscellaneous Drainage Works.-New sewers and storm water drains varying in diameter from 66′′ to 6", were constructed to a length of 14,761 feet, principally in Shamshuipo, Cheung Sha Wan, Shek Kip Mei, and Kowloon City. The number of drain connections made was 230. Many new gullies were con structed and connected to the existing storm water drainage system. Expenditure $112,728.06 182. Miscellaneous.-The following were the principal works executed under this heading :-Formation of pigstye site, west of Kowloon City, Levelling open space at rear of N.K.I.L. 1414, Filling in pool on Crown Land lying between Yu Chau Street and Taipo Road, Levelling area between Shek Ku Lung Road and Sa Po Road at the rear of Kowloon City Market. Four beacons were constructed on the foothills to the East of Kowloon Bay to replace the existing measured mile. Expenditure $2,368.06 183. Water Works. A block of coolie quarters was erected at the Taipo Road Bungalow, consisting of a brick building with a reinforced concrete roof, providing accommodation for eight
2026-05-09 14:42:02 · Baseline
View content

Q 45

179. Market at Tong Mi.-The work consists of the erection of a market of 36 stalls, but owing to shortage of staff it could not be undertaken during 1933.

Expenditure

Nil.

GENERAL WORKS.

180. Roads.-The undermentioned roads were macadamized, kerbed, channelled and laid to approved levels, the footpaths being paved with granolithic paving or slabs and the necessary improvements made in front of new buildings erected during the year: Sai Kung Road, Shek Ku Lung Road, Sa Po Road, Tak Ku Ling Road, South Wall Road, Prince Edward Road, Fuk Wa Street, Maple Street, Po Kong Road, Cheung Sha Wan Road, Poplar Street, Apliu Street, Fuk Wing Street, Wong Chuk Street, Shek Kip Mi Street, Un Chau Street, Pei Ho Street, Shamshuipo Market, Kwei-lin Street, Kiu Kiang Street, Custle Peak Road, Tai Po Road, Nan Chang Street, Tung Chau Street, Hai-tan Street, Boundary Street, Lung Kong Road.

Expenditure

$74,636.85

181. Drainage:-(a) Training Nullahs.--The invert of the nullah in Sam Tak Road was completed. A nullah with decking was constructed at Castle Peak Road, Wong Uk, and the eastern nullah wall with parapet walling at Lai Chi Kok Nullah was com- pleted.

Expenditure

$38,646.76

(b) Miscellaneous Drainage Works.-New sewers and storm water drains varying in diameter from 66′′ to 6", were constructed to a length of 14,761 feet, principally in Shamshuipo, Cheung Sha Wan, Shek Kip Mei, and Kowloon City. The number of drain connections made was 230. Many new gullies were con structed and connected to the existing storm water drainage system.

Expenditure

$112,728.06

182. Miscellaneous.-The following were the principal works executed under this heading :-Formation of pigstye site, west of Kowloon City, Levelling open space at rear of N.K.I.L. 1414, Filling in pool on Crown Land lying between Yu Chau Street and Taipo Road, Levelling area between Shek Ku Lung Road and Sa Po Road at the rear of Kowloon City Market. Four beacons were constructed on the foothills to the East of Kowloon Bay to replace the existing measured mile.

Expenditure

$2,368.06

183. Water Works. A block of coolie quarters was erected at the Taipo Road Bungalow, consisting of a brick building with a reinforced concrete roof, providing accommodation for eight