AnnualReport-1930 — Page 645

Administrative Reports 行政報告書 All AI Reviewed

Q 91

P.W.E. Kowloon.

A Contract for this work was let to Messrs. Foo Loong & Co. for a sum of $2,000 on 12th March, 1930, and the work was completed by the end of July, 1930.

Estimates Expenditure $4,000.00 $1,735.00

171. Laying a cable between Hung Hom Bridge and Yaumati Government School.—A 75 pair telephone cable was laid between the points mentioned.

Estimates Expenditure $8,000.00 $7,295.72

172. Additional 100 line Telephone Exchange Switchboard.—The telephone switchboard was ordered from England but had not arrived in the Colony by the end of the year.

It will be installed at Kowloon Telephone Exchange.

Estimates Expenditure $5,000.00 $3,605.31

173. Renewing electrical wiring at Ma Tau Kok Slaughter House, Kowloon Post Office and Tsim Sha Tsui Pier.—The wiring in these places was renewed. Total points fifty three.

Estimates Expenditure $700.00 $621.03

174. Renewing Kowloon-Canton Railway Station, Goods Yards, Officers Quarters, Hung Hom A. & B. Blocks and old Quarters formerly property of China Light & Power Co.—The electrical wiring was renewed; total points—five hundred and ninety eight.

Estimates Expenditure $8,650.00 $7,560.13

175. Chinese Cemeteries. Laying out new areas.—Work carried out under this head has already been alluded to in paragraph 34 of this Report.

Estimates Expenditure $10,000.00 $9,972.76

Page 645

Page 646

Edit History

2026-05-09 06:05:19 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 91 P.W.E. Kowloon. A Contract for this work was let to Messrs. Foo Loong & Co. for a sum of $2,000 on 12th March, 1930, and the work was completed by the end of July, 1930. Estimates Expenditure $4,000.00 $1,735.00 171. Laying a cable between Hung Hom Bridge and Yaumati Government School.—A 75 pair telephone cable was laid between the points mentioned. Estimates Expenditure $8,000.00 $7,295.72 172. Additional 100 line Telephone Exchange Switchboard.—The telephone switchboard was ordered from England but had not arrived in the Colony by the end of the year. It will be installed at Kowloon Telephone Exchange. Estimates Expenditure $5,000.00 $3,605.31 173. Renewing electrical wiring at Ma Tau Kok Slaughter House, Kowloon Post Office and Tsim Sha Tsui Pier.—The wiring in these places was renewed. Total points fifty three. Estimates Expenditure $700.00 $621.03 174. Renewing Kowloon-Canton Railway Station, Goods Yards, Officers Quarters, Hung Hom A. & B. Blocks and old Quarters formerly property of China Light & Power Co.—The electrical wiring was renewed; total points—five hundred and ninety eight. Estimates Expenditure $8,650.00 $7,560.13 175. Chinese Cemeteries. Laying out new areas.—Work carried out under this head has already been alluded to in paragraph 34 of this Report. Estimates Expenditure $10,000.00 $9,972.76 Page 645 Page 646
Baseline (Original)
Q 91 P.W.E. Kowloon. A Contract for this work was let to Messrs. Foo Loong & Co. for a sum of $2,000 on 12th March, 1930, and the work was completed by the end of July, 1930. Estimates Expenditure $4,000.00 $1,735.00 171. Laying a cable between Hung Hom Bridge and Yaumati Government School.—A 75 pair telephone cable was laid between the points mentioned. Estimates Expenditure $8,000.00 $7,295.72 172. Additional 100 line Telephone Exchange Switch- board.—The telephone switchboard was ordered from England but had not arrived in the Colony by the end of the year. It will be installed at Kowloon Telephone Exchange. Estimates Expenditure $5,000.00 $3,605.31 173. Renewing electrical wiring at Ma Tau Kok Slaughter House, Kowloon Post Office and Tsim Sha Tsui Pier.—The wiring in these places was renewed. Total points fifty three. Estimates Expenditure $700.00 $621.03 174. Renewing Kowloon-Canton Railway Station, Goods Yards, Officers Quarters, Hung Hom A. & B. Blocks and old Quarters formerly property of China Light & Power Co.—The electrical wiring was renewed; total points-five hundred and ninety eight. Estimates Expenditure $8,650.00 $7,560.13 175. Chinese Cemeteries. Laying out new areas.--Work carried out under this head has already been alluded to in paragraph 34 of this Report. Estimates Expenditure $10,000.00 $ 9,972.76 Page 645Page 646
2026-05-09 06:05:19 · Baseline
View content

Q 91

P.W.E. Kowloon.

A Contract for this work was let to Messrs. Foo Loong & Co. for a sum of $2,000 on 12th March, 1930, and the work was completed by the end of July, 1930.

Estimates

Expenditure

$4,000.00

$1,735.00

171. Laying a cable between Hung Hom Bridge and Yaumati Government School.—A 75 pair telephone cable was laid between the points mentioned.

Estimates

Expenditure

$8,000.00

$7,295.72

172. Additional 100 line Telephone Exchange Switch- board.—The telephone switchboard was ordered from England but had not arrived in the Colony by the end of the year.

It will be installed at Kowloon Telephone Exchange.

Estimates Expenditure

$5,000.00 $3,605.31

173. Renewing electrical wiring at Ma Tau Kok Slaughter House, Kowloon Post Office and Tsim Sha Tsui Pier.—The wiring in these places was renewed. Total points fifty three.

Estimates Expenditure

$700.00 $621.03

174. Renewing Kowloon-Canton Railway Station, Goods Yards, Officers Quarters, Hung Hom A. & B. Blocks and old Quarters formerly property of China Light & Power Co.—The electrical wiring was renewed; total points-five hundred and ninety eight.

Estimates Expenditure

$8,650.00 $7,560.13

175. Chinese Cemeteries. Laying out new areas.--Work carried out under this head has already been alluded to in paragraph 34 of this Report.

Estimates

Expenditure

$10,000.00

$ 9,972.76

Page 645Page 646

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.