Q 91
P.W.E. Kowloon.
A Contract for this work was let to Messrs. Foo Loong & Co. for a sum of $2,000 on 12th March, 1930, and the work was completed by the end of July, 1930.
Estimates Expenditure $4,000.00 $1,735.00171. Laying a cable between Hung Hom Bridge and Yaumati Government School.—A 75 pair telephone cable was laid between the points mentioned.
Estimates Expenditure $8,000.00 $7,295.72172. Additional 100 line Telephone Exchange Switchboard.—The telephone switchboard was ordered from England but had not arrived in the Colony by the end of the year.
It will be installed at Kowloon Telephone Exchange.
Estimates Expenditure $5,000.00 $3,605.31173. Renewing electrical wiring at Ma Tau Kok Slaughter House, Kowloon Post Office and Tsim Sha Tsui Pier.—The wiring in these places was renewed. Total points fifty three.
Estimates Expenditure $700.00 $621.03174. Renewing Kowloon-Canton Railway Station, Goods Yards, Officers Quarters, Hung Hom A. & B. Blocks and old Quarters formerly property of China Light & Power Co.—The electrical wiring was renewed; total points—five hundred and ninety eight.
Estimates Expenditure $8,650.00 $7,560.13175. Chinese Cemeteries. Laying out new areas.—Work carried out under this head has already been alluded to in paragraph 34 of this Report.
Estimates Expenditure $10,000.00 $9,972.76Page 645
Page 646
Q 91
P.W.E. Kowloon.
A Contract for this work was let to Messrs. Foo Loong & Co. for a sum of $2,000 on 12th March, 1930, and the work was completed by the end of July, 1930.
Estimates
Expenditure
$4,000.00
$1,735.00
171. Laying a cable between Hung Hom Bridge and Yaumati Government School.—A 75 pair telephone cable was laid between the points mentioned.
Estimates
Expenditure
$8,000.00
$7,295.72
172. Additional 100 line Telephone Exchange Switch- board.—The telephone switchboard was ordered from England but had not arrived in the Colony by the end of the year.
It will be installed at Kowloon Telephone Exchange.
Estimates Expenditure
$5,000.00 $3,605.31
173. Renewing electrical wiring at Ma Tau Kok Slaughter House, Kowloon Post Office and Tsim Sha Tsui Pier.—The wiring in these places was renewed. Total points fifty three.
Estimates Expenditure
$700.00 $621.03
174. Renewing Kowloon-Canton Railway Station, Goods Yards, Officers Quarters, Hung Hom A. & B. Blocks and old Quarters formerly property of China Light & Power Co.—The electrical wiring was renewed; total points-five hundred and ninety eight.
Estimates Expenditure
$8,650.00 $7,560.13
175. Chinese Cemeteries. Laying out new areas.--Work carried out under this head has already been alluded to in paragraph 34 of this Report.
Estimates
Expenditure
$10,000.00
$ 9,972.76
Page 645Page 646