AnnualReport-1929 — Page 602

Administrative Reports 行政報告書 All AI Reviewed

Q 115

Works carried out and chargeable to Loan Funds.

(c) Filtering Plant and Erection. This plant was brought into operation on June 10th, being run for 8 hours per day in order to supply Piper's Hill Service Reservoir with approx. 1.0 million gallons per day. The results of Bacteriological and chemical tests have been satisfactory. A Paterson type Fluxograph to record the quantity of water passing through the plant was installed in February.

Total Estimates, $199,694.35

Expenditure up to 31.12.29, $200,048.14

(d) Service Reservoir, Shek Lai Pui. Steady progress was made with the excavation of the Eastern half of the reservoir resulting in a commencement of the concrete invert by the middle of June. Early in August concrete work in the main walls and piers was commenced and continued steadily to the end of the year.

Towards the end of November the timbering & placing of reinforcement for the roof was commenced.

During the year the following concrete work was completed:

Invert 195 bays 15′0″ x 12′0″

Piers 165 No.

Main Walls 553 lineal feet.

Division Wall 116 ""

As the excavations were proceeding it was found economical to enlarge the size of the service reservoir to give a capacity of 11.5 million gallons.

Total Estimates, $400,000.00

Expenditure up to 31.12.29, $127,155.27

(e) Pipe Line. The laying of the 24″ steel main in Nathan Road was continued and by the end of May it had been laid to Prince Edward Road. The section above Cheung Sha Wan was completed in May by the laying of 560 lineal feet of 24″ main to the site of Shek Lai Pui Service Reservoir. From this point a temporary 12″ C. I. main 360 lineal feet in length was laid to the Shing Mun Rapid Gravity Filters.

A 24″ x 11″ Self Closing valve with recording apparatus was installed at a point approx. 560 lineal feet below the Shek Lai Pui Service Reservoir and a valve house built.

The pipe line was brought into operation on June 10th, to feed the Piper's Hill Service Reservoir from the Shing Mun Rapid Gravity Filters.

Edit History

2026-05-09 03:39:52 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 115 Works carried out and chargeable to Loan Funds. (c) Filtering Plant and Erection. This plant was brought into operation on June 10th, being run for 8 hours per day in order to supply Piper's Hill Service Reservoir with approx. 1.0 million gallons per day. The results of Bacteriological and chemical tests have been satisfactory. A Paterson type Fluxograph to record the quantity of water passing through the plant was installed in February. Total Estimates, $199,694.35 Expenditure up to 31.12.29, $200,048.14 (d) Service Reservoir, Shek Lai Pui. Steady progress was made with the excavation of the Eastern half of the reservoir resulting in a commencement of the concrete invert by the middle of June. Early in August concrete work in the main walls and piers was commenced and continued steadily to the end of the year. Towards the end of November the timbering & placing of reinforcement for the roof was commenced. During the year the following concrete work was completed: Invert 195 bays 15′0″ x 12′0″ Piers 165 No. Main Walls 553 lineal feet. Division Wall 116 "" As the excavations were proceeding it was found economical to enlarge the size of the service reservoir to give a capacity of 11.5 million gallons. Total Estimates, $400,000.00 Expenditure up to 31.12.29, $127,155.27 (e) Pipe Line. The laying of the 24″ steel main in Nathan Road was continued and by the end of May it had been laid to Prince Edward Road. The section above Cheung Sha Wan was completed in May by the laying of 560 lineal feet of 24″ main to the site of Shek Lai Pui Service Reservoir. From this point a temporary 12″ C. I. main 360 lineal feet in length was laid to the Shing Mun Rapid Gravity Filters. A 24″ x 11″ Self Closing valve with recording apparatus was installed at a point approx. 560 lineal feet below the Shek Lai Pui Service Reservoir and a valve house built. The pipe line was brought into operation on June 10th, to feed the Piper's Hill Service Reservoir from the Shing Mun Rapid Gravity Filters.
Baseline (Original)
Q 115 Works carried out and chargeable to Loan Funds. (c) Filtering Plant and Erection. This plant was brought into operation on June 10th., being run for 8 hours per day in order to supply Piper's Hill Service Reservoir with approx. 1.0 million gallons per day. The results of Bacteriological and chemical tests tests have been satisfactory. A Paterson type Fluxograph to record the quantity of water passing through the plant was installed in February. Total Estimates, Expenditure up to 31.12.29, $199,694.35 $200,048.14 (d) Service Reservoir, Shek Lai Pui.-Steady progress was made with the execavation of the Eastern half of the reservoir resulting in a commencement of the concrete invert by the middle of June. Early in August concrete work in the main walls and piers was commenced and continued steadily to the end of the year. Towards the end of November the timbering & placing of reinforcement for the roof was commenced. During the year the following concrete work was com- pleted: Invert Piers Main Walls Division Wall 195 bays 15′0′′ x 12′0′′ 165 No. 553 lineal feet. 116 "" "" As the excavations were proceeding it was found economical to enlarge the size of the service reservoir to give a capacity of 11.5 million gallons. Total Estimates, Expenditure up to 31.12.29, $400,000.00 $127,155.27 (e) Pipe Line. The laying of the 24" steel main in Nathan Road was continued and by the end of May it had been laid to Prince Edward Road. The section above Cheung Sha Wan was completed in May by the laying of 560 lineal feet of 24′′ main to the site of Shek Lai Pui Service Reservoir. From this point a temporary 12′′ C. I. main 360 lineal feet in length was laid to the Shing Mun Rapid Gravity Filters. A 24" x 11" Self Closing valve with recording apparatus was installed at a point approx. 560 lineal feet below the Shek Lai Pui Service Reservoir and a valve house built. The pipe line was brought into operation on June 10th., to feed the Piper's Hill Service Reservoir from the Shing Mun Rapid Gravity Filters.
2026-05-09 03:39:52 · Baseline
View content

Q 115

Works carried out and chargeable to Loan Funds.

(c) Filtering Plant and Erection. This plant was brought into operation on June 10th., being run for 8 hours per day in order to supply Piper's Hill Service Reservoir with approx. 1.0 million gallons per day. The results of Bacteriological and chemical tests

tests have been satisfactory. A Paterson type Fluxograph to record the quantity of water passing through the plant was installed in February.

Total Estimates,

Expenditure up to 31.12.29,

$199,694.35

$200,048.14

(d) Service Reservoir, Shek Lai Pui.-Steady progress was

made with the execavation of the Eastern half of the reservoir resulting in a commencement of the concrete invert by the middle of June. Early in August concrete work in the main walls and piers was commenced and continued steadily to the end of the year.

Towards the end of November the timbering & placing of reinforcement for the roof was commenced.

During the year the following concrete work was com- pleted:

Invert

Piers

Main Walls

Division Wall

195 bays 15′0′′ x 12′0′′

165 No.

553 lineal feet.

116 ""

""

As the excavations were proceeding it was found economical to enlarge the size of the service reservoir to give a capacity of 11.5 million gallons.

Total Estimates,

Expenditure up to 31.12.29,

$400,000.00 $127,155.27

(e) Pipe Line. The laying of the 24" steel main in Nathan Road was continued and by the end of May it had been laid to Prince Edward Road. The section above Cheung Sha Wan was completed in May by the laying of 560 lineal feet of 24′′ main to the site of Shek Lai Pui Service Reservoir. From this point a temporary 12′′ C. I. main 360 lineal feet in length was laid to the Shing Mun Rapid Gravity Filters.

A 24" x 11" Self Closing valve with recording apparatus was installed at a point approx. 560 lineal feet below the Shek Lai

Pui Service Reservoir and a valve house built.

The pipe line was brought into operation on June 10th., to feed the Piper's Hill Service Reservoir from the Shing Mun Rapid Gravity Filters.

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.