P.W.E. New Territories.

year.

Q 108

The work was satisfactorily completed by the end of the year.

Estimates, Expenditure,

$10,000.00 $7,078.84

251. Tai Po Road Improvements-Bridge at 13 miles.-In view of improvements to the existing bridge the work of constructing the new bridge was not proceeded with.

Estimates, Expenditure,

$30,000.00 Nil.

252. Levelling strip of land formerly occupied by the Railway, Sha Tau Kok.-When the section of the roadway occupied by the branch line of the Kowloon-Canton Railway to Sha Tau Kok was vacated, the terminal area at Sha Tau Kok was levelled to provide parking places for motor buses and other vehicles.

The work was let to Mr. Pang Loong, on 13th May, 1929 as Part B of Contract No. 17 of 1929 for a sum of $1,132.00.

The work was satisfactorily completed by the end of the year.

Estimates, Expenditure,

$5,000.00 $1,195.18

253. Forming and surfacing street in front of D.D.C. Lot 827 C. and D. and 828 C.--This work was completed.

Estimates, Expenditure,

$2,000.00 $1,432.88

254. Fencing of Magnetic Huts, Au Tau.-The area on which the Magnetograph House and Magnetic Hut at Au Tau were built, reference of which is made in paragraph 193 of the Report for 1927, was enclosed in a wooden fence in the construction of which no iron work was permitted.

A Contract for this work was let to Mr. Keng Tack Cheong on 17th May, 1929 for a sum of $1,046.60.

The work was satisfactorily completed by the end of the year.

Estimates, Expenditure,

$1,600.00 $988.95

Edit History

2026-05-09 03:38:47 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. New Territories. year. Q 108 The work was satisfactorily completed by the end of the year. Estimates, Expenditure, $10,000.00 $7,078.84 251. Tai Po Road Improvements-Bridge at 13 miles.-In view of improvements to the existing bridge the work of constructing the new bridge was not proceeded with. Estimates, Expenditure, $30,000.00 Nil. 252. Levelling strip of land formerly occupied by the Railway, Sha Tau Kok.-When the section of the roadway occupied by the branch line of the Kowloon-Canton Railway to Sha Tau Kok was vacated, the terminal area at Sha Tau Kok was levelled to provide parking places for motor buses and other vehicles. The work was let to Mr. Pang Loong, on 13th May, 1929 as Part B of Contract No. 17 of 1929 for a sum of $1,132.00. The work was satisfactorily completed by the end of the year. Estimates, Expenditure, $5,000.00 $1,195.18 253. Forming and surfacing street in front of D.D.C. Lot 827 C. and D. and 828 C.--This work was completed. Estimates, Expenditure, $2,000.00 $1,432.88 254. Fencing of Magnetic Huts, Au Tau.-The area on which the Magnetograph House and Magnetic Hut at Au Tau were built, reference of which is made in paragraph 193 of the Report for 1927, was enclosed in a wooden fence in the construction of which no iron work was permitted. A Contract for this work was let to Mr. Keng Tack Cheong on 17th May, 1929 for a sum of $1,046.60. The work was satisfactorily completed by the end of the year. Estimates, Expenditure, $1,600.00 $988.95
Baseline (Original)
P.W.E. New Territories. year. Q 108 The work was satisfactorily, completed by the end of the Estimates, Expenditure, $10,000.00 $ 7,078.84 251. Tai Po Road Improvements-Bridge at 13 miles.-In view of improvements to the existing bridge the work of con- structing the new bridge was not proceeded with. Estimates, Expenditure, $30,000.00 Nil. 252. Levelling strip of land formerly occupied by the Rail- way, Sha Tau Kok.-When the section of the roadway occupied by the branch line of the Kowloon-Canton Railway to Sha Tau Kok was vacated, the terminal area at Sha Tau Kok was levelled to provide parking places for motor buses and other vehicles. The work was let to Mr. Pang Loong, on 13th May, 1929 as Part B of Contract No. 17 of 1929 for a sum of $1,132.00. The work was satisfactorily completed by the end of the year. Estimates, Expenditure, $5,000.00 $1,195.18 253. Forming and surfacing street in front of D.D.C. Lot 827 C. and D. and 828 C.--This work was completed. Estimates, Expenditure, $2,000.00 $1,432.88 254. Fencing of Magnetic Huts, Au Tau.-The area on which the Magnetograph House and Magnetic Hut at Au Tau were built, reference of which is made in paragraph 193 of the Report for 1927, was enclosed in a wooden fence in the construc- tion of which no iron work was permitted. A Contract for this work was let to Mr. Keng Tack Cheong on 17th May, 1929 for a sum of $1,046.60. year. The work was satisfactorily completed by the end of the Estimates, Expenditure, $1,600.00 $ 988.95
2026-05-09 03:38:47 · Baseline
View content

P.W.E. New Territories.

year.

Q 108

The work was satisfactorily, completed by the end of the

Estimates, Expenditure,

$10,000.00

$ 7,078.84

251. Tai Po Road Improvements-Bridge at 13 miles.-In view of improvements to the existing bridge the work of con- structing the new bridge was not proceeded with.

Estimates,

Expenditure,

$30,000.00

Nil.

252. Levelling strip of land formerly occupied by the Rail- way, Sha Tau Kok.-When the section of the roadway occupied by the branch line of the Kowloon-Canton Railway to Sha Tau Kok was vacated, the terminal area at Sha Tau Kok was levelled to provide parking places for motor buses and other vehicles.

The work was let to Mr. Pang Loong, on 13th May, 1929 as Part B of Contract No. 17 of 1929 for a sum of $1,132.00.

The work was satisfactorily completed by the end of the

year.

Estimates,

Expenditure,

$5,000.00

$1,195.18

253. Forming and surfacing street in front of D.D.C. Lot 827 C. and D. and 828 C.--This work was completed.

Estimates,

Expenditure,

$2,000.00 $1,432.88

254. Fencing of Magnetic Huts, Au Tau.-The area on which the Magnetograph House and Magnetic Hut at Au Tau were built, reference of which is made in paragraph 193 of the Report for 1927, was enclosed in a wooden fence in the construc- tion of which no iron work was permitted.

A Contract for this work was let to Mr. Keng Tack Cheong on 17th May, 1929 for a sum of $1,046.60.

year.

The work was satisfactorily completed by the end of the

Estimates,

Expenditure,

$1,600.00

$ 988.95