P.W.R. New Territories.
54
P. W. R. NEW TERRITORIES.
95. Maintenance of Buildings.-Repairs and renovations necessary to maintain Government Buildings in a good state of repair were carried out under the usual recurring programme.
Estimates, $20,000.00 Expenditure, $17,913.0696. Improvements to Buildings.-The following are the more important items carried out under this head:
Tai Po Land Office-Removal of partition wall to increase the area of the Court Room. Tai Po Rest House-Tiling bathrooms. Tai Ku Ling Police Station-Ceiling to underside of rafters.
Estimates, Expenditure,97. Maintenance of Roads and Bridges.
Improvements to Roads and Bridges.
$5,000.00 $2,871.37Approximately 75 miles of roads.—The road surfaces were generally maintained in a satisfactory manner.
The strengthening and improvement of the road surfaces was commenced, an additional layer of 4" macadam being laid over the present surface and tar painted from a point near Castle Peak to the Molasses Factory.
The following are particulars of the areas laid during the year:
1. Tarring and sanding Square yards. 104,574 2. 2½" granolithic paving slabs laid on footways 785 Estimates, $70,000.00 $2,000.00 $72,000.00 Expenditure, $66,426.82 $1,898.14 $68,324.9698. Maintenance of Telephones.-The lines and instruments were maintained in good order. Two additional instruments were installed.
Estimates, $4,000.00 Expenditure, $3,847.55P.W.R. New Territories.
54
P. W. R. NEW TERRITORIES.
95. Maintenance of Buildings.-Repairs and renovations necessary to maintain Government Buildings in a good state of repair were carried out under the usual recurring programme.
Estimates, Expenditure,
$20,000.00 $17,913.06
96. Improvements to Buildings.-The following are the more important items carried out under this head:
Tai Po Land Office-Removal of partition wall to in- crease the area of the Court Room. Tai Po Rest House-Tiling bathrooms. Tai Ku Ling Police Station-Ceiling to underside of rafters.
Estimates,
Expenditure,
97. Maintenance of Roads and Bridges.
Improvements to Roads and Bridges.
$5,000.00
$2,871.37
Approximately
75 miles of rouds.—The road surfaces were generally maintained in a satisfactory manner.
The strengthening and improvement of the road surfaces was commenced, an additional layer of 4" macadam being laid over the present surface and tar painted from a point near Castie Peak to the Molasses Factory.
The following are particulars of the areas laid during the year:
1. Tarring and sanding
2. 21" granolithic paving slabs laid
on footways
Estimates,
Expenditure,
Square yards. 104,574
785
$70,000.00
2,000.00
$72,000.00
$66,426.82
1,898.14
$68,324.96
98. Maintenance of Telephones.-The lines and instruments were maintained in good order. Two additional instruments were installed.
Estimates, Expenditure,
$4,000.00 $3,847.55