AnnualReport-1929 — Page 22

Administrative Reports 行政報告書 All AI Reviewed

20

A Contract was let for the Byewash Reservoir situated immediately below the existing Kowloon Dam and fair progress was made during the year.

Orders for a 12" diameter Steel Main were placed in England in June for a pipe line across the Harbour and pipes commenced to arrive in September. Actual laying commenced on 17th December.

2nd Section.--Surveys and investigations were continued.

RECLAMATIONS.

Hong Kong.-Praya East, about 90 acres, was completed. A further reclamation of about 2 acres at Shaukiwan was commenced.

New Kowloon.-Construction was continued on the sea wall to protect the Shamshuipo Reclamation. A length of about 1,400 lineal feet was completed.

The dumping of refuse at Cheung Sha Wan resulted in the reclamation of a total area of approximately 3 acres.

The work of bringing the Kai Tak Reclamation to finished levels was continued.

New Territories.-The Standard Oil Co. continued with the formation of a site at Lai Chi Kok. Progress with this work has been delayed owing to the failure of the sea wall.

PIERS.

Kowloon.-At Mong Kok Tsui, construction was commenced on a reinforced concrete ferry pier, 150 feet in length by 50 feet in width.

New Kowloon.-At Shamshuipo, the construction of a ferry pier, 150 feet in length by 50 feet in width, was commenced.

SLIPWAYS.

New Kowloon.-The construction of the slipway at the Kai Tak Reclamation was completed. The slipway is 380 feet in length at a grade of 1 in 20 and provides a depth of 6 feet at L.W.O.S.T.

Edit History

2026-05-09 01:07:29 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
20 A Contract was let for the Byewash Reservoir situated immediately below the existing Kowloon Dam and fair progress was made during the year. Orders for a 12" diameter Steel Main were placed in England in June for a pipe line across the Harbour and pipes commenced to arrive in September. Actual laying commenced on 17th December. 2nd Section.--Surveys and investigations were continued. RECLAMATIONS. Hong Kong.-Praya East, about 90 acres, was completed. A further reclamation of about 2 acres at Shaukiwan was commenced. New Kowloon.-Construction was continued on the sea wall to protect the Shamshuipo Reclamation. A length of about 1,400 lineal feet was completed. The dumping of refuse at Cheung Sha Wan resulted in the reclamation of a total area of approximately 3 acres. The work of bringing the Kai Tak Reclamation to finished levels was continued. New Territories.-The Standard Oil Co. continued with the formation of a site at Lai Chi Kok. Progress with this work has been delayed owing to the failure of the sea wall. PIERS. Kowloon.-At Mong Kok Tsui, construction was commenced on a reinforced concrete ferry pier, 150 feet in length by 50 feet in width. New Kowloon.-At Shamshuipo, the construction of a ferry pier, 150 feet in length by 50 feet in width, was commenced. SLIPWAYS. New Kowloon.-The construction of the slipway at the Kai Tak Reclamation was completed. The slipway is 380 feet in length at a grade of 1 in 20 and provides a depth of 6 feet at L.W.O.S.T.
Baseline (Original)
20 A Contract was let for the Byewash Reservoir situated im- mediately below the existing Kowloon Dam and fair progress was male during the year. Orders for a 12" diameter Steel Main were placed in England in June for a pipe line across the Harbour and pipes commenced to arrive in September. Actual laying commenced on 17th December. 2nd Section.--Surveys and investigations were continued. RECLAMATIONS. Hong Kong.-Praya East, about 90 acres, was completed. + A further reclamation of about 2 acres Shaukiwan was commenced at New Kowloon.-Construction was continued on the sea wall to protect the Shamshuipo Reclamation. A length of about 1,400 lineal feet was completed. The dumping of refuse at Cheung Sha Wan resulted in the reclamation of a total area of approximately 3 acres. The work of bringing the Kai Tak Reclamation to finished levels was continued. New Territories.-The Standard Oil Co. continued with with the formation of a site at Lai Chi Kok. Progress with this work has been delayed owing to the failure of the sea wall. PIERS. Kowloon.-At Mong Kok Tsui, construction was commenced on a reinforced concrete ferry pier, 150 feet in length by 50 feet in width. of a ferry New Kowloon. At Shamshuipo, the construction pier, 150 feet in length by 50 feet in width, was commenced. SLIPWAYS. New Kowloon.-The construction of the slipway at the Kai Tak Reclamation was completed. The slipway is 380 feet in length at a grade of 1 in 20 and provides a depth of 6 feet at L.W.O.S.Ť.
2026-05-09 01:07:29 · Baseline
View content

20

A Contract was let for the Byewash Reservoir situated im- mediately below the existing Kowloon Dam and fair progress was male during the year.

Orders for a 12" diameter Steel Main were placed in England in June for a pipe line across the Harbour and pipes commenced to arrive in September. Actual laying commenced on 17th December.

2nd Section.--Surveys and investigations were continued.

RECLAMATIONS.

Hong Kong.-Praya East, about 90 acres, was completed.

+

A further reclamation of about 2 acres Shaukiwan

was commenced at

New Kowloon.-Construction was continued on the sea wall to protect the Shamshuipo Reclamation. A length of about 1,400 lineal feet was completed.

The dumping of refuse at Cheung Sha Wan resulted in the reclamation of a total area of approximately 3 acres.

The work of bringing the Kai Tak Reclamation to finished levels was continued.

New Territories.-The Standard Oil Co. continued with

with the formation of a site at Lai Chi Kok. Progress with this work has been delayed owing to the failure of the sea wall.

PIERS.

Kowloon.-At Mong Kok Tsui, construction was commenced on a reinforced concrete ferry pier, 150 feet in length by 50 feet in width.

of a ferry

New Kowloon. At Shamshuipo, the construction pier, 150 feet in length by 50 feet in width, was commenced.

SLIPWAYS.

New Kowloon.-The construction of the slipway at the Kai Tak Reclamation was completed. The slipway is 380 feet in length at a grade of 1 in 20 and provides a depth of 6 feet at L.W.O.S.Ť.

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.