P.W.E. Hong Kong.
Q 52
The work was completed by the end of the year.
1928 Estimates, $15,800.00
1928 Sup. Vote, $1,000.00
Total Estimates, $130,000.09
Expenditure up to 31.12.28, $21,897.34
1928 Expenditure, $14,279.18
115. Stubbs Road, Improvements to junction with Morrison Gap Road. The work, which was referred to in paragraph 110 (d) of last year's Report, was completed early in the year:
Estimates, $10,000.00
Expenditure, $359.40
116. Approach Road to New Tung Wah Hospital Site at Soo Kun Poo. A road 16 feet wide and about 830 feet long was constructed from the Eastern part of the road encircling Caroline Hill site to give an access to the new Tung Wah Hospital Site.
A contract was let to Mr. Li Yau for a sum of $3,232.80 on 16th May and the work was completed by end of August.
Estimates, $5,500.00
Expenditure, $2,661.40
Drainage:
Training Nullahs:
117. Reconstruction of Wong Nei Chong Nullah, Section No. 3, from Bowrington Canal to Chinese Stand. This work, which was referred to in paragraph 111 (c) of last year's Report, was completed towards the end of November.
Total Estimates, $150,000.00
1928 Estimates, $75,000.00
1928 Sup. Vote, $20,653.00
1928 Expenditure, $95,652.80
Expenditure up to 31.12.28, $137,658.33
118. Construction of nullah through site of new Tung Wah Hospital at Sookunpoo.—This work, for which a Contract was let in May, was commenced towards the end of that month and completed in September.
Estimates, $7,000.00
Expenditure, $2,230.03
119. Reconstruction of Wong Nei Chong Nullah, Section No. 4, in front of Jockey Club Stand.-A Contract was let, and work was commenced in the middle of March. The foundations, walling and flooring were nearly completed. Very good progress was made with the reinforced concrete decking.
1928 Estimates, $130,000.00
1928 Expenditure, $84,922.83
Total Estimates, $200,000.00
Expenditure up to 31.12.28, $84,922.83
P.W.E. Hong Kong.
Q 52
The work was completed by the end of the year.
1928 Estimates,
1928 Sup. Vote,
...
•
$ 1,000.00 Total Estimates, $130,000.09
14,800.00
$15,800.00 Expenditure up
1928 Expenditure, . $14,279.18
to 31.12.28, $ 21,897.34
115. Stubbs Road, Improvements to junction with Morrison Gap Road. The work, which was referred to in paragraph 110 (d) of last year's Report, was completed early in the year:-
Estimates, Expenditure,
$10,000.00 $ 359.40
116. Approach Road to New Tung Wah Hospital Site at Soo Kun Poo. A road 16 feet wide and about 830 feet long was con- structed from the Eastern part of the road encircling Caroline Hill site to give an access to the new Tung Wah Hospital Site.
A contract was let to Mr. Li Yau for a sum of $3,232.80 on 16th May and the work was completed by end of August.
Estimates, Expenditure,
$5,500.00 $2,661.40
Drainage :-
Training Nullahs:
117. Reconstruction of Wong Nei Chong Nullah, Section No. 3, from Bowrington Canal to Chinese Stand. This work, which was referred to in paragraph 111 (c) of last year's Report, was completed towards the end of November.
$75,000.00 Total Estimates,
20,653.00
··
$150,000.00
1928 Estimates,
1928 Sup. Vote,
1928 Expenditure, . $95,652.80
$95,653.00 Expenditure up
to 31.12.28,
$137,658.33
118. Construction of nullah through site of new Tung Wah Hospital at Sookunpoo.—This work, for which a Contract was let in May, was commenced towards the end of that month and completed in September.
Estimates, Expenditure,
$7,000.00 $2,230.03
119. Reconstruction of Wong Nei Chong Nullah, Section No. 4, in front of Jockey Club Stand.-A Contract was let, and work was commenced in the middle of March. The foundations, wall- ing and flooring were nearly completed. Very good progress was made with the reinforced concrete decking.
1928 Estimates, $130,000.00
•
1928 Expenditure, $ 84,922.83
Total Estimates, Expenditure up to 31.12.28,
$200,000.00
$ 84,922.83