P.W.R. Hong Kong.
Q 34
48. Maintenance of Water Works, Shau Ki Wan:-A constant supply of water by fountains was maintained throughout the year, which was rendered possible by the temporary connection to the City Mains, the total quantity of water drawn therefrom amounting to 8.00 million gallons.
The total consumption of filtered water for the year was 71.58 million gallons which includes 2.83 million gallons supplied to the boat population giving an average of 195,000 gallons per day. An unfiltered supply of 3.07 million gallons was given to the Barracks at Sai Wan, which with the total of the filtered supply stated above amounted to 74.65 million gallons or 204,000 gallons per day. The details of the consumption are given in Annexe F.
There were 65 meters in use at the close of the year.
Estimates, Expenditure,
$1,200.00 $935.60
49. Maintenance of Water Works Aberdeen.—A satisfactory supply of water was maintained throughout the year, the total consumption being 31.44 million gallons inclusive of 4.37 million gallons supplied through the water-boat station, as compared with a total consumption of 31.16 million gallons and a water-boat supply of 3.45 million gallons during 1927.
The average consumption throughout the year was 86,000 gallons per day, the details of which are given in Annexe G.
There were 19 meters in use at the close of the year.
Estimates, Expenditure,
$1,200.00 $747.62
50. Maintenance of Water Works, Repulse Bay. The total quantity of water supplied during the year amounted to 7.85 million gallons or an average consumption of 21,000 gallons per day against a total supply of 6.42 million gallons and an average consumption of 17,000 gallons per day during 1927.
There were 23 meters in use at the close of the year.
Estimates, Expenditure,
$1,000.00 $747.20
51. Water Account (Meters, etc.). The number of meters examined and repaired during the year was 1,715. A systematic overhaul of all meters is being carried out.
The total expenditure for the year was
Estimates, Sup. Vote, Expenditure,
$24,000.00 $5,000.00 $28,639.75
P.W.R. Hong Kong.
Q 34
48. Maintenance of Water Works, Shau Ki Wan:-A con- stant supply of water by fountains was maintained throughout the year, which was rendered possible by the temporary connec tion to the City Mains, the total quantity of water drawn there- from amounting to 8.00 million gallons.
The total consumption of filtered water for the year was 71.58 million gallons which includes 2.83 million gallons supplied to the boat population giving an average of 195,000 gallons per day. An unfiltered supply of 3.07 million gallons was given to the Barracks at Sai Wan, which with the total of the filtered supply stated above amounted to 74.65 million gallons or 204,000 gallons per day. The details of the consumption are given in Annexe F.
There were 65 meters in use at the close of the year.
Estimates, Expenditure,
$1,200.00 $ 935.60
49. Maintenance of Water Works Aberdeen.—A satisfactory supply of water was maintained throughout the year, the total consumption being 31.44 million gallons inclusive of 4.37 million gallons supplied through the water-boat station, as compared with a total consumption of 31.16 million gallons and a water- boat supply of 3.45 million gallons during 1927.
The average consumption throughout the year was 86,000 gallons per day, the details of which are given in Annexe G.
There were 19 meters in use at the close of the year.
Estimates, Expenditure,
$1,200.00 $ 747.62
50. Maintenance of Water Works, Repulse Bay. The total quantity of water supplied during the year amounted to 7.85 million gallons or an average consumption of 21,000 gallons per day against a total supply of 6.42 million gallons and an average consumption of 17,000 gallons per day during 1927.
There were 23 meters in use at the close of the year.
Estimates, Expenditure,
$1,000.00 $ 747.20
51. Water Account (Melers, etc.). The number of meters examined and repaired during the year was 1,715. A systematic overhaul of all meters is being carried out.
The total expenditure for the year was
Estimates, Sup. Vote, Expenditure,
་
$24,000.00 $ 5,000.00
$28,639.75