Works carried out and charged to Loan Funds.

A pathway three feet wide with coping of lime and cement concrete was laid along the whole length of the South Conduit, a distance of 2,100 feet, while considerable trimming and turfing of slopes, and formation of channels were carried out at the tunnel portals.

1927 Estimates, $25,000.00 Total Estimates, $1,100,000.00

Expenditure to 31.12.27, $1,073,644.13

1927 Expenditure, $23,823.97

(d.) Pipe Line.-This work was referred to in paragraph 164 (c.) of last year's Report.

The excavation of the pipe trace and stringing of the 24″ steel pipes were commenced in May on the section between Piper's Hill Reservoir and Shek Lei Pui, and pipe laying on this section was begun in August. By the end of the year 3,230 lineal feet of pipe line had been laid.

The construction of the bridges over the Lai Chi Kok and Shek Lei Pui streams was commenced in September and completed by the end of the year.

1927 Estimates, $130,000.00

Total Estimates, $700,000.00

Expenditure to 31.12.27, $325,654.17

1927 Expenditure, $13,314.28

202. Dredging within the Harbour Limits and Formation of Reclamation at Kowloon City.-Investigations were instituted during the early part of the year with a view to carrying out a scheme of dredging at Kowloon Point, Belcher Ridge and Rambler Shoal, Penguin Shoals, and the Western Fairway.

A Contract was let to the Netherlands Harbour Works Co. on the 14th May for the dredging of Kowloon Point, Belcher Ridge, Rambler Shoal, and Penguin Shoals. The contract provides for the dredged material to be utilized in forming the reclamation South-East of Kowloon City, the construction of about 1,300 feet of sea walling, and other necessary contingent works. The contract is to be completed in fifteen months.

Dredging.-The Contractors commenced operations on the 4th of July and completed the dredging of Penguin Shoals to an average depth of -37.5′ O.D. on the 11th of August. The total quantity of material dredged from this area was 66,259 cubic yards, and it was found to consist of 69% sand, 16% mud, and 15% shell.

The dredging of Belcher Ridge and Rambler Shoal Area was completed to a depth of 36.5' O.D. on the 12th of October. The total quantity of material dredged from this area 198,822 cubic yards, and it was proved to consist of approximately 57% sand, 14% mud, and 29% shell.

Edit History

2026-05-07 21:11:01 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
95 Works carried out and charged to Loan Funds. A pathway three feet wide with coping of lime and cement concrete was laid along the whole length of the South Conduit, a distance of 2,100 feet, while considerable trimming and turfing of slopes, and formation of channels were carried out at the tunnel portals. 1927 Estimates, $25,000.00 Total Estimates, $1,100,000.00 Expenditure to 31.12.27, $1,073,644.13 1927 Expenditure, $23,823.97 (d.) Pipe Line.-This work was referred to in paragraph 164 (c.) of last year's Report. The excavation of the pipe trace and stringing of the 24″ steel pipes were commenced in May on the section between Piper's Hill Reservoir and Shek Lei Pui, and pipe laying on this section was begun in August. By the end of the year 3,230 lineal feet of pipe line had been laid. The construction of the bridges over the Lai Chi Kok and Shek Lei Pui streams was commenced in September and completed by the end of the year. 1927 Estimates, $130,000.00 Total Estimates, $700,000.00 Expenditure to 31.12.27, $325,654.17 1927 Expenditure, $13,314.28 202. Dredging within the Harbour Limits and Formation of Reclamation at Kowloon City.-Investigations were instituted during the early part of the year with a view to carrying out a scheme of dredging at Kowloon Point, Belcher Ridge and Rambler Shoal, Penguin Shoals, and the Western Fairway. A Contract was let to the Netherlands Harbour Works Co. on the 14th May for the dredging of Kowloon Point, Belcher Ridge, Rambler Shoal, and Penguin Shoals. The contract provides for the dredged material to be utilized in forming the reclamation South-East of Kowloon City, the construction of about 1,300 feet of sea walling, and other necessary contingent works. The contract is to be completed in fifteen months. Dredging.-The Contractors commenced operations on the 4th of July and completed the dredging of Penguin Shoals to an average depth of -37.5′ O.D. on the 11th of August. The total quantity of material dredged from this area was 66,259 cubic yards, and it was found to consist of 69% sand, 16% mud, and 15% shell. The dredging of Belcher Ridge and Rambler Shoal Area was completed to a depth of 36.5' O.D. on the 12th of October. The total quantity of material dredged from this area 198,822 cubic yards, and it was proved to consist of approximately 57% sand, 14% mud, and 29% shell.
Baseline (Original)
95 Works carried out and charged to Loan Funds. A pathway three feet wide with coping of lime and cement concrete was laid along the whole length of the South Conduit, a distance of 2,100 feet, while considerable trimming and turfing of slopes, and formation of channels were carried out at the tunnel portals. 1927 Estimates, $25,000.00 Total Estimates, $1,100,000.00 Expenditure to 1927 Expenditure,. $23,823.97 31.12.27, $1,073,644.13 (d.) Pipe Line.-This work was referred to in paragraph 164 (c.) of last year's Report. The excavation of the pipe trace and stringing of the 24′′ steel pipes were commenced in May on the section between Piper's Hill Reservoir and Shek Lei Pui, and pine laying on this section was begun in August. By the end of the year 3,230 lineal feet of pipe line had been laid. The construction of the bridges over the Lai Chi Kok and Shek Lei Pui streams was commenced in September and com- pieted by the end of the year. 1927 Estimates, $130,000.00 Total Estimates, . $700,000.00 Expenditure to 31.12.27, $325,654.17 1927 Expenditure, $ 13,314.28 202. Dredging within the Harbour Limits and Formation of Reclamation at Kowloon Citu.-Investigations were instituted during the early part of the year with a view to carrving out a scheme of dredging at Kowloon Point, Belcher Ridge and Rambler Shoal, Penguin Shoals, and the Western Fairway. A Contract was let to the Netherlands Harbour Works Co. on the 14th Mav for the dredging of Kowloon Point. Belcher Ridge, Rambler Shoal, and Penguin Shoals. The contract pro- vides for the dredged material to be utilized in forming the reclamation South-East of Kowloon City, the construction of about 1,300 feet of sea walling, and other necessary contingent works. The contract is to be completed in fifteen months. Dredging.-The Contractors commenced operations on the 4th of July and completed the dredging of Penguin Shoals to an average denth of-37.5′ 0.D. on the 11th of August. The total quantity of material dredged from this area was 66,259 cubic yards, and it was found to consist of 69% sand, 16% mud, and 15% shell. The dredging of Belcher Ridge and Rambler Shoal Area was completed to a depth of 36.5' O.D. on the 12th of October. The total quantity of material dredged from this area 198,822 cubic yards, and it was proved to consist of approximate- ly 57% sand, 14% mud, and 29% shell. *
2026-05-07 21:11:01 · Baseline
View content

95

Works carried out and charged to Loan Funds.

A pathway three feet wide with coping of lime and cement concrete was laid along the whole length of the South Conduit, a distance of 2,100 feet, while considerable trimming and turfing of slopes, and formation of channels were carried out at the tunnel portals.

1927 Estimates,

$25,000.00 Total Estimates, $1,100,000.00

Expenditure to

1927 Expenditure,. $23,823.97 31.12.27,

$1,073,644.13

(d.) Pipe Line.-This work was referred to in paragraph 164 (c.) of last year's Report.

The excavation of the pipe trace and stringing of the 24′′ steel pipes were commenced in May on the section between Piper's Hill Reservoir and Shek Lei Pui, and pine laying on this section was begun in August. By the end of the year 3,230 lineal feet of pipe line had been laid.

The construction of the bridges over the Lai Chi Kok and Shek Lei Pui streams was commenced in September and com- pieted by the end of the year.

1927 Estimates, $130,000.00

Total Estimates, . $700,000.00

Expenditure to

31.12.27,

$325,654.17

1927 Expenditure, $ 13,314.28

202. Dredging within the Harbour Limits and Formation of Reclamation at Kowloon Citu.-Investigations were instituted during the early part of the year with a view to carrving out a scheme of dredging at Kowloon Point, Belcher Ridge and Rambler Shoal, Penguin Shoals, and the Western Fairway.

A Contract was let to the Netherlands Harbour Works Co. on the 14th Mav for the dredging of Kowloon Point. Belcher Ridge, Rambler Shoal, and Penguin Shoals. The contract pro- vides for the dredged material to be utilized in forming the reclamation South-East of Kowloon City, the construction of about 1,300 feet of sea walling, and other necessary contingent works. The contract is to be completed in fifteen months.

Dredging.-The Contractors commenced operations on the 4th of July and completed the dredging of Penguin Shoals to an average denth of-37.5′ 0.D. on the 11th of August. The total quantity of material dredged from this area was 66,259 cubic yards, and it was found to consist of 69% sand, 16% mud, and 15% shell.

The dredging of Belcher Ridge and Rambler Shoal Area was completed to a depth of 36.5' O.D. on the 12th of October. The total quantity of material dredged from this area 198,822 cubic yards, and it was proved to consist of approximate- ly 57% sand, 14% mud, and 29% shell.

*