P.W.E. New Kowloon.

Q 78

Size Description Length (in feet) Locality Position Remarks 6" Sewer 44 Kowloon City S" 6" 82 11 295 Cheung Sha Wan In scavenging lane at rear of N.K.I.L's. 542 & 513. In street West of N.K.I.L. 510 to opposite tee Jane N.K.I.L. 510, at In tee lane and scavenging lane behind N.K.I.L. 510 Through new market block West of N.K.I.L. 510. In scavenging lane at rear of N.K.I.L. 559. 166 In street South of and in scavenging lane behind N.K.I.L. 402. 6" 250 9" & 6" 528

The number of drain connections made was 88.

Many new gullies were constructed and connected to the stormwater drainage system.

1927 Estimates. $50,000.00

1927 Expenditure (contributions by various lessees), $23,034.87

1927 Expenditure (from Government Funds), $35,131.15

$23,166.02

(c.) Miscellaneous. At the Christian Chinese Cemetery boundary walls were erected round the new extension, the Sexton's Quarters and Entrance Gates were completed, and a commencement made with the formation of terraces.

Edit History

2026-05-07 21:06:02 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. New Kowloon. Q 78 Size Description Length (in feet) Locality Position Remarks 6" Sewer 44 Kowloon City S" 6" 82 11 295 Cheung Sha Wan In scavenging lane at rear of N.K.I.L's. 542 & 513. In street West of N.K.I.L. 510 to opposite tee Jane N.K.I.L. 510, at In tee lane and scavenging lane behind N.K.I.L. 510 Through new market block West of N.K.I.L. 510. In scavenging lane at rear of N.K.I.L. 559. 166 In street South of and in scavenging lane behind N.K.I.L. 402. 6" 250 9" & 6" 528 The number of drain connections made was 88. Many new gullies were constructed and connected to the stormwater drainage system. 1927 Estimates. $50,000.00 1927 Expenditure (contributions by various lessees), $23,034.87 1927 Expenditure (from Government Funds), $35,131.15 $23,166.02 (c.) Miscellaneous. At the Christian Chinese Cemetery boundary walls were erected round the new extension, the Sexton's Quarters and Entrance Gates were completed, and a commencement made with the formation of terraces.
Baseline (Original)
P.W.E. New Kowloon. Q 78 Size. Description. Length (in feet). Locality. Position. Remarks. 6" Sewer 44 Kowloon City S" 6" 82 11 "'; "} 295 Cheung Sha Wan In scavenging lane at Completed rear of N.K.I.L's. 542 & 513. In street West of N.K.I.L. 510 to op- posite tee Jane N.K.I.L. 510, at In tee lane and scav- enging lane bebind N.K.I.L. 510 Through new market block West of N.K.I.L. 510. In scavenging lane at rear of N.K.I.L. 559. In street South of and in scavenging lane behind N.K.I.L. 402. " "J "" JJ 6. "" 166 # 6" 250 9" & 6" 528 "} >> The number of drain connections made was 88. Many new gullies were constructed and connected to the stormwater drainage system. 1927 Estimates. $50,000.00 1927 Expenditure (contributions 1927 Expenditure (from Govern- ment Funds), by various lessees), $23,034.87 $35 131.15 $23,166.02 (c.) Miscellaneous. At the Christian Chinese Cemetery boundary walls were erected round the new extension, the Sexton's Quarters and Entrance Gates were completed, and a commencement made with the formation of terraces.
2026-05-07 21:06:02 · Baseline
View content

P.W.E. New Kowloon.

Q 78

Size. Description.

Length (in feet).

Locality.

Position.

Remarks.

6"

Sewer

44

Kowloon City

S"

6"

82

11

"';

"}

295

Cheung Sha Wan

In scavenging lane at Completed

rear of N.K.I.L's. 542

& 513.

In street West of N.K.I.L. 510 to op- posite tee Jane N.K.I.L. 510,

at

In tee lane and scav- enging lane bebind N.K.I.L. 510

Through new market block West of N.K.I.L. 510.

In scavenging lane at rear of N.K.I.L. 559.

In street South of and in scavenging lane behind N.K.I.L. 402.

"

"J

""

JJ

6.

""

166

#

6"

250

9" & 6"

528

"}

>>

The number of drain connections made was 88.

Many new gullies were constructed and connected to the stormwater drainage system.

1927 Estimates.

$50,000.00

1927 Expenditure (contributions

1927 Expenditure (from Govern-

ment Funds),

by various lessees),

$23,034.87

$35 131.15

$23,166.02

(c.) Miscellaneous. At the Christian Chinese Cemetery boundary walls were erected round the new extension, the Sexton's Quarters and Entrance Gates were completed, and a commencement made with the formation of terraces.