P.W.E. Hong Kong.

Q 48

106. Alterations to Offices in Old Buildings at the Central Police Station to accommodate the Accounts Office.—This work consisted of the reconstruction and improvement of the various ground floor rooms in the old building to accommodate the Accounts Office in a convenient manner and to group its various branches together so as to ensure greater efficiency.

The work was commenced in April and completed in October.

1927 Estimates, $5,000.00

1927 Expenditure, $3,784.03

107. Installation of Water-flushed Closets and Urinals at the Ellis Kadoorie School for Indians.—This work consisted of installing two water-flushed closets in the main building for the European and Chinese Masters, which involved the subdivision by means of partitions of a room previously used by coolies.

The work was commenced in March and completed towards the end of May.

1927 Estimates, $1,000.00

1927 Expenditure, $610.32

108. Garage for Motor Vans and Cars at the Central Police Station. This work consisted of the erection of a Garage to house the Prison Motor Vans and the Police Motor Cars, and of a shelter at the rear of the old Police Station to protect the Police Motor-cycles.

To provide a site for the Garage, the old and dilapidated wing of the quarters of the Deputy Superintendent of Police containing disused servants' quarters was demolished, and the Garage built thereon, such servants' quarters as were required being incorporated in the scheme.

The open yard at the rear of the old barrack block was covered over to form a shelter for the Police Motor-cycles.

The work was commenced in February and completed in September.

1927 Estimates, $10,000.00

1927 Expenditure, $6,393.78

109. General Works:

(a) Roads:-The following is a brief description of the principal works carried out under this heading:

Edit History

2026-05-07 20:56:20 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Hong Kong. Q 48 106. Alterations to Offices in Old Buildings at the Central Police Station to accommodate the Accounts Office.—This work consisted of the reconstruction and improvement of the various ground floor rooms in the old building to accommodate the Accounts Office in a convenient manner and to group its various branches together so as to ensure greater efficiency. The work was commenced in April and completed in October. 1927 Estimates, $5,000.00 1927 Expenditure, $3,784.03 107. Installation of Water-flushed Closets and Urinals at the Ellis Kadoorie School for Indians.—This work consisted of installing two water-flushed closets in the main building for the European and Chinese Masters, which involved the subdivision by means of partitions of a room previously used by coolies. The work was commenced in March and completed towards the end of May. 1927 Estimates, $1,000.00 1927 Expenditure, $610.32 108. Garage for Motor Vans and Cars at the Central Police Station. This work consisted of the erection of a Garage to house the Prison Motor Vans and the Police Motor Cars, and of a shelter at the rear of the old Police Station to protect the Police Motor-cycles. To provide a site for the Garage, the old and dilapidated wing of the quarters of the Deputy Superintendent of Police containing disused servants' quarters was demolished, and the Garage built thereon, such servants' quarters as were required being incorporated in the scheme. The open yard at the rear of the old barrack block was covered over to form a shelter for the Police Motor-cycles. The work was commenced in February and completed in September. 1927 Estimates, $10,000.00 1927 Expenditure, $6,393.78 109. General Works: (a) Roads:-The following is a brief description of the principal works carried out under this heading:
Baseline (Original)
P.W.E. Hong Kong. Q 48 106. Alterations to Offices in Old Buildings at the Central Police Station to accommodate the Accounts Office.—This work consisted of the reconstruction and improvement of the various ground floor rooms in the old building to accommodate the Accounts Office in a convenient manner and to group its various branches together so as to ensure greater efficiency. The work was commenced in April and completed in October. 1927 Estimates, 1927 Expenditure, $5,000.00 $3,784.03 107. Installation of Water-flushed Closets and Urinals at the Ellis Kadoorie School for Indians.—This work consisted of installing two water-flushed closets in the main building for the European and Chinese Masters which involved the subdivision by means of partitions of a room previously used by coolies The work was commenced in March and completed towards the end of May. 1927 Estimates, 1927 Expenditure, $1,000.00 $ 610.32 108. Garage for Motor Vans and Cars at the Central Police Station. This work consisted of the erection of a Garage to house the Prison Motor Vans and the Police Motor Cars and of a shelter at the rear of the old Police Station to protect the Police Motor-cycles. P To provide a site for the Garage, the old and dilapidated wing of the quarters of the Deputy Superintendent of Police containing disused servants' quarters was demolished and the Garage built thereon, such servants quarters as were required being incorporated in the scheme. The open yard at the rear of the old barrack block was covered over to form a shelter for the Police Motor-cycles. The work was commenced in February and completed in September. 1927 Estimates, 1927 Expenditure, 109. General Works: $10,000.00 $ 6,393.78 (a.) Roads:-The following is a brief description of the principal works carried out under this heading:-
2026-05-07 20:56:20 · Baseline
View content

P.W.E. Hong Kong.

Q 48

106. Alterations to Offices in Old Buildings at the Central Police Station to accommodate the Accounts Office.—This work consisted of the reconstruction and improvement of the various ground floor rooms in the old building to accommodate the Accounts Office in a convenient manner and to group its various branches together so as to ensure greater efficiency.

The work was commenced in April and completed in October.

1927 Estimates,

1927 Expenditure,

$5,000.00

$3,784.03

107. Installation of Water-flushed Closets and Urinals at the Ellis Kadoorie School for Indians.—This work consisted of installing two water-flushed closets in the main building for the European and Chinese Masters which involved the subdivision by means of partitions of a room previously used by coolies

The work was commenced in March and completed towards the end of May.

1927 Estimates,

1927 Expenditure,

$1,000.00

$ 610.32

108. Garage for Motor Vans and Cars at the Central Police Station. This work consisted of the erection of a Garage to house the Prison Motor Vans and the Police Motor Cars and of a shelter at the rear of the old Police Station to protect the Police Motor-cycles.

P

To provide a site for the Garage, the old and dilapidated wing of the quarters of the Deputy Superintendent of Police containing disused servants' quarters was demolished and the Garage built thereon, such servants quarters as were required being incorporated in the scheme.

The open yard at the rear of the old barrack block was covered over to form a shelter for the Police Motor-cycles.

The work was commenced in February and completed in September.

1927 Estimates,

1927 Expenditure,

109. General Works:

$10,000.00

$ 6,393.78

(a.) Roads:-The following is a brief description of the principal works carried out under this heading:-