The new plant has been constructed inside one of the three old Siow sand beds, and the other two beds have been roofed over and made into additional service reservoirs to feed the Kennedy Road District. Additional head has thereby been obtained for No. 4 Hydraulic Motor, which shows a large increase in output.

The leakage from Wongneichong Reservoir has been picked up below the dam and conveyed by means of a 2" dia. W.I. pipe to a small service reservoir on the hill behind Deep Water Bay. This supply is being utilized for supplying R.B.L. 245 and distribution pipes have been laid in the roads.

Considerable investigation work was carried out in connection with a proposed scheme for the development of the Aberdeen Valley.

Kowloon.-The following lengths of cast iron distribution mains were laid: 450 lin. feet of 3″ dia. 870 lin. ft. of 4" dia., 8,110 lin. ft. of 6" dia., 1,750 lin. ft. of 8″ dia, and 750 lin. ft. of 18″ dia.

New Kowloon.-An additional length of 4,000 lin. ft. of 6" C.I. pipes was laid in the Kowloon Tong Development area.

New Territories.-Shing Mun Valley Scheme. A length of about eighty feet of the North Tunnel was straightened, and considerable lengths of pathways, copings and channelling were completed.

Pipe laying commenced in August and a total length of 3,230 lin. feet of 24" dia. steel main had been laid by the end of the year. The two reinforced concrete bridges over the Sheklaipui Stream were completed.

Construction of the Fast Gravity Filter Beds and Chemical House was commenced during the year and fair progress was made.

RECLAMATIONS.

Hong Kong.-Praya East, about 90 acres, of which about 75 acres were reclaimed at end of year.

North Point.-Private Scheme, 231 acres, scheme almost completed.

Kowloon.-Taikoktsui, about 54 acres, of which about 52 were reclaimed by end of the year.

New Kowloon.-Shamshuipo Reclamation comprising an area of about 66 acres completed except for sea wall. No further work was carried out during the year.

Edit History

2026-05-07 14:17:27 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
20 The new plant has been constructed inside one of the three old Siow sand beds, and the other two beds have been roofed over and made into additional service reservoirs to feed the Kennedy Road District. Additional head has thereby been obtained for No. 4 Hydraulic Motor, which shows a large increase in output. The leakage from Wongneichong Reservoir has been picked up below the dam and conveyed by means of a 2" dia. W.I. pipe to a small service reservoir on the hill behind Deep Water Bay. This supply is being utilized for supplying R.B.L. 245 and distribution pipes have been laid in the roads. Considerable investigation work was carried out in connection with a proposed scheme for the development of the Aberdeen Valley. Kowloon.-The following lengths of cast iron distribution mains were laid: 450 lin. feet of 3″ dia. 870 lin. ft. of 4" dia., 8,110 lin. ft. of 6" dia., 1,750 lin. ft. of 8″ dia, and 750 lin. ft. of 18″ dia. New Kowloon.-An additional length of 4,000 lin. ft. of 6" C.I. pipes was laid in the Kowloon Tong Development area. New Territories.-Shing Mun Valley Scheme. A length of about eighty feet of the North Tunnel was straightened, and considerable lengths of pathways, copings and channelling were completed. Pipe laying commenced in August and a total length of 3,230 lin. feet of 24" dia. steel main had been laid by the end of the year. The two reinforced concrete bridges over the Sheklaipui Stream were completed. Construction of the Fast Gravity Filter Beds and Chemical House was commenced during the year and fair progress was made. RECLAMATIONS. Hong Kong.-Praya East, about 90 acres, of which about 75 acres were reclaimed at end of year. North Point.-Private Scheme, 231 acres, scheme almost completed. Kowloon.-Taikoktsui, about 54 acres, of which about 52 were reclaimed by end of the year. New Kowloon.-Shamshuipo Reclamation comprising an area of about 66 acres completed except for sea wall. No further work was carried out during the year.
Baseline (Original)
20 The new plant has been constructed inside one of the three old Siow sand beds, and the other two beds have been roofed over and made into additional service reservoirs to feed the Kennedy Road District. Additional head has thereby been obtained for No. 4 Hydraulic Motor, which shows a large increase in output. The leakage from Wongneichong Reservoir has been picked up below the dam and conveyed by means of a 2" dia. W.I. pipe to a small service reservoir on the hill behind Deep Water Bay. This supply is being utilized for supplying R.B.L. 245 and distribution pipes have been laid in the roads. Considerable investigation work was carried out in connection with a proposed scheme for the development of the Aberdeen Valley. Kowloon.-The following lengths of cast iron distribution mains were laid: 450 lin. feet of 3′′ dia. 870 lin. ft. of 4" dia., 8,110 lin. ft. of 6" dia., 1,750 lin. ft. of 8′′ dia, and 750 lin. ft. of 18′′ dia. New Kowloon.-An additional length of 4,000 lin. ft. of 6" C.I. pipes was laid in the Kowloon Tong Development area. New Territories.-Shing Mun Valley Scheme. A length of about eighty feet of the North Tunnel was straightened, and considerable iengths of pathways, copings and channelling were completed. Pipe laying commenced in August and a total length of 3,230 lin. feet of 24" dia. steel main had been laid by the end of the year. The two reinforced concrete bridges over the Sheklaipui Stream were completed. Construction of the Fast Gravity Filter Beds and Chemical House was commenced during the year and fair progress was made. RECLAMATIONS. Hong Kong.-Praya East, about 90 acres, of which about 75 acres were reclaimed at end of year. North Point.-Private Scheme, 231 acres, scheme almost completed. Kowloon.-Taikoktsui, about 54 acres, of which about 52 were reclaimed by end of the year. New Kowloon.--Shamshuipo Reclamation comprising an area of about 66 acres completed except for sea wall. No further work was carried out during the year. -
2026-05-07 14:17:27 · Baseline
View content

20

The new plant has been constructed inside one of the three old Siow sand beds, and the other two beds have been roofed over and made into additional service reservoirs to feed the Kennedy Road District. Additional head has thereby been obtained for No. 4 Hydraulic Motor, which shows a large increase in output.

The leakage from Wongneichong Reservoir has been picked up below the dam and conveyed by means of a 2" dia. W.I. pipe to a small service reservoir on the hill behind Deep Water Bay. This supply is being utilized for supplying R.B.L. 245 and distribution pipes have been laid in the roads.

Considerable investigation work was carried out in connection with a proposed scheme for the development of the Aberdeen Valley.

Kowloon.-The following lengths of cast iron distribution mains were laid: 450 lin. feet of 3′′ dia. 870 lin. ft. of 4" dia., 8,110 lin. ft. of 6" dia., 1,750 lin. ft. of 8′′ dia, and 750 lin. ft. of 18′′ dia.

New Kowloon.-An additional length of 4,000 lin. ft. of 6" C.I. pipes was laid in the Kowloon Tong Development area.

New Territories.-Shing Mun Valley Scheme. A length of about eighty feet of the North Tunnel was straightened, and considerable iengths of pathways, copings and channelling were completed.

Pipe laying commenced in August and a total length of 3,230 lin. feet of 24" dia. steel main had been laid by the end of the year. The two reinforced concrete bridges over the Sheklaipui Stream were completed.

Construction of the Fast Gravity Filter Beds and Chemical House was commenced during the year and fair progress was made.

RECLAMATIONS.

Hong Kong.-Praya East, about 90 acres, of which about 75 acres were reclaimed at end of year.

North Point.-Private Scheme, 231 acres, scheme almost completed.

Kowloon.-Taikoktsui, about 54 acres, of which about 52 were reclaimed by end of the year.

New Kowloon.--Shamshuipo Reclamation comprising an area of about 66 acres completed except for sea wall. No further work was carried out during the year. -