P.W.E. Hong Kong.

(d.) Shaukiwan Road, Improvements in Shaukiwan Village. -This work was referred to in paragraph 123 (e.) of last year's Report.

The contract for this work was let and the work started towards the end of the year. Satisfactory progress was made.

1926 Estimates, $30,000.00
1926 Expenditure, $9,024.06

(e.) Robinson Road to Conduit Road. This work, referred to in paragraph 123 (g.) of last year's Report, was completed.

1926 Estimates, $50,000.00
1926 Expenditure, $30,519.08

Construction. This

(f.) Tai Hang Development,—Road work was referred to in paragraphs 120 (n.) of the Report for 1923, 124 (m.) of that for 1924 and 123 (j.) of last year's Report.

A short length of walling was completed on the lower section, but upon the receipt of an application from the Contractor for an adjustment of the prices of the contract the opportunity was taken to close the contract.

1926 Estimates, $74,000.00
Total Estimates, $122,000.00
Expenditure to 31.12.26, $138,220.13
1926 Expenditure, $7,490.89

Construction.-

(g). Wongneichong Development,-Road This work was referred to in paragraph 123 (l) of last year's Report.

A contract was let to Messrs. Yee Lee & Co. for the sum of $23,234 on 29th September, 1926.

Progress was retarded, delay being caused by the slow removal of matsheds occupied by late tenants of village houses at Wongneichong.

1926 Estimates, $50,000.00
Expenditure to 31.12.26, $280.00
1926 Expenditure, $280.00

(h.) Queen's Road East.-Widening to 60 feet. This work was referred to in paragraph 123 (m.) of last year's Report.

The laying of cement concrete and asphalt surfacing was carried out where land for road widening had been resumed during the year.

1926 Estimates, $20,000.00
1926 Expenditure, $13,018.59
Expenditure to 31.12.26, $377,890.51

Edit History

2026-05-07 13:39:01 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 75 P.W.E. Hong Kong. (d.) Shaukiwan Road, Improvements in Shaukiwan Village. -This work was referred to in paragraph 123 (e.) of last year's Report. The contract for this work was let and the work started towards the end of the year. Satisfactory progress was made. 1926 Estimates, $30,000.001926 Expenditure, $9,024.06 (e.) Robinson Road to Conduit Road. This work, referred to in paragraph 123 (g.) of last year's Report, was completed. 1926 Estimates, $50,000.001926 Expenditure, $30,519.08 Construction. This (f.) Tai Hang Development,—Road work was referred to in paragraphs 120 (n.) of the Report for 1923, 124 (m.) of that for 1924 and 123 (j.) of last year's Report. A short length of walling was completed on the lower section, but upon the receipt of an application from the Contractor for an adjustment of the prices of the contract the opportunity was taken to close the contract. 1926 Estimates, $74,000.00Total Estimates, $122,000.00Expenditure to 31.12.26, $138,220.131926 Expenditure, $7,490.89 Construction.- (g). Wongneichong Development,-Road This work was referred to in paragraph 123 (l) of last year's Report. A contract was let to Messrs. Yee Lee & Co. for the sum of $23,234 on 29th September, 1926. Progress was retarded, delay being caused by the slow removal of matsheds occupied by late tenants of village houses at Wongneichong. 1926 Estimates, $50,000.00Expenditure to 31.12.26, $280.001926 Expenditure, $280.00 (h.) Queen's Road East.-Widening to 60 feet. This work was referred to in paragraph 123 (m.) of last year's Report. The laying of cement concrete and asphalt surfacing was carried out where land for road widening had been resumed during the year. 1926 Estimates, $20,000.001926 Expenditure, $13,018.59Expenditure to 31.12.26, $377,890.51
Baseline (Original)
Q 75 P.W.E. Hong Kong. (d.) Shaukiwan Road, Improvements in Shaukiwan Village. -This work was referred to in paragraph 123 (e.) of last year's Report. The contract for this work was let and the work started towards the end of the year. Satisfactory progress was made. 1926 Estimates, 1926 Expenditure, $30,000.00 $ 9,024.06 (e.) Robinson Road to Conduit Road. This work, referred to in paragraph 123 (g.) of last year's Report, was completed. 1926 Estimates, 1926 Expenditure, $50,000.00 $30,519.08 Construction. This (f.) Tai Hang Development,—Road work was referred to in paragraphs 120 (n.) of the Report for 1923, 124 (m.) of that for 1924 and 123 (j.) of last year's Report. A short length of walling was completed on the lower section, but upon the receipt of an application from the Con- tractor for an adjustment of the prices of the contract the opportunity was taken to close the contract. $74,000.00 Total Estimates, Expenditure to 1926 Estimates, 1926 Expenditure, . $ 7,490.89 31.12.26, $122,000.00 $138,220.13 Construction.- (g). Wongneichong Development,-Road This work was referred to in paragraph 123 (1) of last year's Report. A contract was let to Messrs. Yee Lee & Co. for the sum of $23,234 on 29th September, 1926. Progress was retarded, delay being caused by the slow removal of matsheds occupied by late tenants of village houses at Wongneichong. 1926 Estimates, 1926 Expenditure, 4 $50,000.00 Expenditure to $ 280.00 31.12.26, $280.00 (h.) Queen's Road East.-Widening to 60 feet. This work was referred to in paragraph 123 (m.) of last year's Report. The laying of cement concrete and asphalt surfacing was carried out where land for road widening had been resumed during the year. 1926 Estimates, $20,000.00 1926 Expenditure, . $13,018.59 Expenditure to 31.12.26, $377,890.51
2026-05-07 13:39:01 · Baseline
View content

Q 75

P.W.E. Hong Kong.

(d.) Shaukiwan Road, Improvements in Shaukiwan Village. -This work was referred to in paragraph 123 (e.) of last year's Report.

The contract for this work was let and the work started towards the end of the year. Satisfactory progress was made.

1926 Estimates,

1926 Expenditure,

$30,000.00 $ 9,024.06

(e.) Robinson Road to Conduit Road. This work, referred to in paragraph 123 (g.) of last year's Report, was completed.

1926 Estimates, 1926 Expenditure,

$50,000.00 $30,519.08

Construction. This

(f.) Tai Hang Development,—Road work was referred to in paragraphs 120 (n.) of the Report for 1923, 124 (m.) of that for 1924 and 123 (j.) of last year's Report.

A short length of walling was completed on the lower section, but upon the receipt of an application from the Con- tractor for an adjustment of the prices of the contract the opportunity was taken to close the contract.

$74,000.00 Total Estimates,

Expenditure to

1926 Estimates,

1926 Expenditure, . $ 7,490.89 31.12.26,

$122,000.00

$138,220.13

Construction.-

(g). Wongneichong Development,-Road This work was referred to in paragraph 123 (1) of last year's Report.

A contract was let to Messrs. Yee Lee & Co. for the sum of $23,234 on 29th September, 1926.

Progress was retarded, delay being caused by the slow removal of matsheds occupied by late tenants of village houses at Wongneichong.

1926 Estimates, 1926 Expenditure,

4

$50,000.00 Expenditure to $ 280.00 31.12.26,

$280.00

(h.) Queen's Road East.-Widening to 60 feet. This work was referred to in paragraph 123 (m.) of last year's Report.

The laying of cement concrete and asphalt surfacing was carried out where land for road widening had been resumed during the year.

1926 Estimates,

$20,000.00

1926 Expenditure, . $13,018.59

Expenditure to 31.12.26,

$377,890.51