AnnualReport-1926 — Page 577

Administrative Reports 行政報告書 All AI Reviewed

Q 35

B. O. O. Work.

Six bungalows completed on R.B.L. 200, Repulse Bay.

Reconstruction of Upper Peak Tram Station House and Engine House.

Three bungalows completed at Shek O.

The following is a list of principal works in other parts of the City and outlying districts which were in course of erection :-

Site development for 28 houses on R.B.L. 245, Deep Water Bay. A large number of the sites and five large reinforced concrete bridges are completed.

Formation of sites for 28 houses and erection of retaining walls on I.L. 2354, Stubbs Road.

Ninety-eight Chinese houses on M.L. 365 and I.L.'s 29 and 457, at East Point Hill.

A large modern Theatre on I.L. 1452, Percival Street, was nearing completion.

Reinforced concrete godowns, steel framed refinery and mort house, and concrete and steel jetty on Q.B. M.L. 1, nearing completion.

Filter house on Q.B. M.L. 2, nearing completion.

Levelling of sites for several blocks of flats on I.L. 2366, Shaukiwan Road, was continued.

Formation of sites on I.L.'s 2367-2376, Shaukiwan Road, was continued.

The following is a list of principal works in the Kowloon district which were completed during the year:-

Theatre on N.K.I.L. 239, Kowloon City.

Rope Works on K.I.L. 1094, Ma Tau Kok.

New offices and quarters for the China Light and Power Company, on K.M.L. 93, Tai Wan.

New sub-station for the China Light and Power Company on K.J.L. 1947, Kau Pui Shek.

Twenty Chinese houses on N.K.T.L. 420, Shamshuipo.

Over 100 houses on the Kowloon Tong Estate were certified during the year.

Edit History

2026-05-07 13:33:33 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 35 B. O. O. Work. Six bungalows completed on R.B.L. 200, Repulse Bay. Reconstruction of Upper Peak Tram Station House and Engine House. Three bungalows completed at Shek O. The following is a list of principal works in other parts of the City and outlying districts which were in course of erection :- Site development for 28 houses on R.B.L. 245, Deep Water Bay. A large number of the sites and five large reinforced concrete bridges are completed. Formation of sites for 28 houses and erection of retaining walls on I.L. 2354, Stubbs Road. Ninety-eight Chinese houses on M.L. 365 and I.L.'s 29 and 457, at East Point Hill. A large modern Theatre on I.L. 1452, Percival Street, was nearing completion. Reinforced concrete godowns, steel framed refinery and mort house, and concrete and steel jetty on Q.B. M.L. 1, nearing completion. Filter house on Q.B. M.L. 2, nearing completion. Levelling of sites for several blocks of flats on I.L. 2366, Shaukiwan Road, was continued. Formation of sites on I.L.'s 2367-2376, Shaukiwan Road, was continued. The following is a list of principal works in the Kowloon district which were completed during the year:- Theatre on N.K.I.L. 239, Kowloon City. Rope Works on K.I.L. 1094, Ma Tau Kok. New offices and quarters for the China Light and Power Company, on K.M.L. 93, Tai Wan. New sub-station for the China Light and Power Company on K.J.L. 1947, Kau Pui Shek. Twenty Chinese houses on N.K.T.L. 420, Shamshuipo. Over 100 houses on the Kowloon Tong Estate were certified during the year.
Baseline (Original)
Q 35 B. O. 0. Work. Six bungalows completed on R.B.L. 200, Repulse Bay. Reconstruction of Upper Peak Tram Station House and Engine House. Three bungalows completed at Shek O. The following is a list of principal works in other parts of the City and outlying districts which were in course of erection :- Site development for 28 houses on R.B.L. 245, Deep Water Bay. A large number of the sites and five large reinforced concrete bridges are completed. Formation of sites for 28 houses and erection of retain- ing walls on I.L. 2354, Stubbs Road. Ninety-eight Chinese houses on M.L. 365 and I.L.'s 29 and 457, at East Point Hill. A large modern Theatre on I.L. 1452, Percival Street, was nearing completion. Reinforced concrete godowns, steel framed refinery and morit house, and concrete and steel jetty on Q.B. M.L. 1, nearing completion. Filter house on Q.B. M.L. 2, nearing completion. Levelling of sites for several blocks of flats on I.L. 2366, Shaukiwan Road, was continued. Formation of sites on I.I.'s 2367-2376, Shaukiwan Road, was continued. The following is a list of principal works in the Kowloon district which were completed during the year:- Theatre on N.K.I.L. 239, Kowloon City. Rope Works on K.I.L. 1094, Ma Tau Kok. New offices and quarters for the China Light and Power Company, on K.M.L. 93, Tai Wan. New sub-station for the China Light and Power Com- pany on K.J.L. 1947, Kau Pui Shek. Twenty Chinese houses on N.K.T.L. 420, Shamshuipo. Over 100 houses on the Kowloon Tong Estate were certified during the year.
2026-05-07 13:33:33 · Baseline
View content

Q 35

B. O. 0. Work.

Six bungalows completed on R.B.L. 200, Repulse Bay.

Reconstruction of Upper Peak Tram Station House and

Engine House.

Three bungalows completed at Shek O.

The following is a list of principal works in other parts of the City and outlying districts which were in course of erection :-

Site development for 28 houses on R.B.L. 245, Deep Water Bay. A large number of the sites and five large reinforced concrete bridges are completed.

Formation of sites for 28 houses and erection of retain-

ing walls on I.L. 2354, Stubbs Road.

Ninety-eight Chinese houses on M.L. 365 and I.L.'s 29

and 457, at East Point Hill.

A large modern Theatre on I.L. 1452, Percival Street,

was nearing completion.

Reinforced concrete godowns, steel framed refinery and morit house, and concrete and steel jetty on Q.B. M.L. 1, nearing completion.

Filter house on Q.B. M.L. 2, nearing completion.

Levelling of sites for several blocks of flats on I.L.

2366, Shaukiwan Road, was continued.

Formation of sites on I.I.'s 2367-2376, Shaukiwan

Road, was continued.

The following is a list of principal works in the Kowloon district which were completed during the year:-

Theatre on N.K.I.L. 239, Kowloon City.

Rope Works on K.I.L. 1094, Ma Tau Kok.

New offices and quarters for the China Light and Power

Company, on K.M.L. 93, Tai Wan.

New sub-station for the China Light and Power Com-

pany on K.J.L. 1947, Kau Pui Shek.

Twenty Chinese houses on N.K.T.L. 420, Shamshuipo.

Over 100 houses on the Kowloon Tong Estate were

certified during the year.