AnnualReport-1925 — Page 690

Administrative Reports 行政報告書 All AI Reviewed

P.W.E. New Territories.

- Q 124

Considerable damage was done during the year by typhoon rains swelling the stream North of the Kaulungtong Area and in consequence the temporary diversion under construction overflowed.

By the end of the year the damage has been made good and the diversion nearly completed to its full width.

1925 Estimates, ...$45,000.00 Total Estimates, ...$60,000.00 1925 Sup. Vote, 1,000.00

$46,000.00

Expenditure to 31.12.25, $19,948.48

1925 Expenditure, $9,948.48

(c.) Shamshuipo, extension of the existing Nanchang Street Nullah to Taipo Road.—This work, referred to in paragraph 208 (c) of last year's Report, was completed during the year.

1925 Estimates, $10,000.00 Total Estimates.

1925 Expenditure, $7,691.27 Expenditure to 31.12.25, $48,999.22

(d.) General Works. To combat mosquito breeding, a considerable amount of trenching was carried out in Kowloon North of Boundary Street between the Railway and Kaulungtong.

1925 Estimates, $5,000.00 1925 Expenditure, $1,664.00

213. Miscellaneous Drainage Works: —

(a.) Main sewer from Fuk-Tsun-Heung in a North-Easterly direction to Tai Po Road.-It was found possible to proceed with a portion only of this work during the year.

1925 Estimates, ...$25,000.00 1925 Expenditure, $3,283.36

Total Estimates, ...$25,000.00 Expenditure to 31.12.25, $3,283.36

(b.) Stormwater drains from Nanchang Street Nullah in the direction of Kaulungtong Village.-Such lengths of stormwater drains as were considered necessary were completed.

1925 Estimates, $10,000.00 Total Estimates, $15,000.00 1925 Expenditure, $6,609.63 Expenditure to 31.12.25, $7,903.09

(c.) Kaulungtong Development Scheme.-Sewers.—Sewers were laid in the streets and scavenging lanes at the rear of the houses nearing completion.

1925 Estimates, ...$50,000.00 Total Estimates, $100,000.00 1925 Expenditure, $26,867.78 Expenditure to 31.12.25, $38,922.85

Page 690

Page 691

Edit History

2026-05-07 10:56:13 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. New Territories. - Q 124 Considerable damage was done during the year by typhoon rains swelling the stream North of the Kaulungtong Area and in consequence the temporary diversion under construction overflowed. By the end of the year the damage has been made good and the diversion nearly completed to its full width. 1925 Estimates, ...$45,000.00 Total Estimates, ...$60,000.00 1925 Sup. Vote, 1,000.00 $46,000.00 Expenditure to 31.12.25, $19,948.48 1925 Expenditure, $9,948.48 (c.) Shamshuipo, extension of the existing Nanchang Street Nullah to Taipo Road.—This work, referred to in paragraph 208 (c) of last year's Report, was completed during the year. 1925 Estimates, $10,000.00 Total Estimates. 1925 Expenditure, $7,691.27 Expenditure to 31.12.25, $48,999.22 (d.) General Works. To combat mosquito breeding, a considerable amount of trenching was carried out in Kowloon North of Boundary Street between the Railway and Kaulungtong. 1925 Estimates, $5,000.00 1925 Expenditure, $1,664.00 213. Miscellaneous Drainage Works: (a.) Main sewer from Fuk-Tsun-Heung in a North-Easterly direction to Tai Po Road.-It was found possible to proceed with a portion only of this work during the year. 1925 Estimates, ...$25,000.00 1925 Expenditure, $3,283.36 Total Estimates, ...$25,000.00 Expenditure to 31.12.25, $3,283.36 (b.) Stormwater drains from Nanchang Street Nullah in the direction of Kaulungtong Village.-Such lengths of stormwater drains as were considered necessary were completed. 1925 Estimates, $10,000.00 Total Estimates, $15,000.00 1925 Expenditure, $6,609.63 Expenditure to 31.12.25, $7,903.09 (c.) Kaulungtong Development Scheme.-Sewers.—Sewers were laid in the streets and scavenging lanes at the rear of the houses nearing completion. 1925 Estimates, ...$50,000.00 Total Estimates, $100,000.00 1925 Expenditure, $26,867.78 Expenditure to 31.12.25, $38,922.85 Page 690 Page 691
Baseline (Original)
P.W.E. New Territories. - Q 124 Considerable damage was done during the year by typhoon rains swelling the stream North of the Kaulungtong Area and in consequence the temporary diversion under construction over- flowed. By the end of the year the damage has been made good and the diversion nearly completed to its full width. 1925 Estimates, ...$ 45,000.00 Total Estimates, ...$ 60,000.00 1925 Sup. Vote, 1,000.00 $ 46,000.00 Expenditure to 31.12.25, $ 19,948.48 1925 Expenditure, $ 9,948.48 (c.) Shamshuipo, extension of the existing Nanchang Street Nullah to Taipo Road.—This work, referred to in paragraph 208 (c) of last year's Report, was completed during the year. 1925 Estimates, $10,000.00 Total Estimates. 1925 Expenditure, $7.691.27 Expenditure to · 31.12.25, $48,999.22 (d.) General Works. To combat mosquito breeding, a con- siderable amount of trenching was carried out in Kowloon North of Boundary Street between the Railway and Kaulungtong. 1925 Estimates, 1925 Expenditure, $ 5,000.00 1,664.00 213. Miscellaneous Drainage Works: (a.) Main sewer from Fuk-Tsun-Heung in a North-Easterly direction to Tai Po Road.-It was found possible to proceed with a portion only of this work during the year. 1925 Estimates, ...$ 25.000.00 1925 Expenditure, $ 3,283.36 Total Estimates, ...$ 25,000.00 Expenditure to 31.12.25. $ 3,283.36 (b.) Stormwater drains from Nanchang Street Nullah in the direction of Kaulungtong Village.-Such lengths of stormwater drains as were considered necessary were completed. 1925 Estimates, $ 10,000.00 Total Estimates, 1925 Expenditure, $ 6,609.63 Expenditure to 31.12.25, $ 15,000.00 $ 7.903.09 (c.) Kaulungtong Development Scheme.-Sewers.—Sewers were laid in the streets and scavenging lanes at the rear of the houses nearing completion. 1925 Estimates, ...$ 50,000.00 Total Estimates, 1925 Expenditure, $ 26,867.78 Expenditure to 31.12.25, .$100,000.00 $ 38,922.85 Page 690Page 691
2026-05-07 10:56:13 · Baseline
View content

P.W.E. New Territories.

- Q 124

Considerable damage was done during the year by typhoon rains swelling the stream North of the Kaulungtong Area and in consequence the temporary diversion under construction over- flowed.

By the end of the year the damage has been made good and the diversion nearly completed to its full width.

1925 Estimates, ...$ 45,000.00 Total Estimates, ...$ 60,000.00 1925 Sup. Vote, 1,000.00

$ 46,000.00

Expenditure to

31.12.25,

$ 19,948.48

1925 Expenditure, $ 9,948.48

(c.) Shamshuipo, extension of the existing Nanchang Street Nullah to Taipo Road.—This work, referred to in paragraph 208 (c) of last year's Report, was completed during the year.

1925 Estimates,

$10,000.00 Total Estimates.

1925 Expenditure, $7.691.27 Expenditure to

·

31.12.25,

$48,999.22

(d.) General Works. To combat mosquito breeding, a con- siderable amount of trenching was carried out in Kowloon North of Boundary Street between the Railway and Kaulungtong.

1925 Estimates, 1925 Expenditure,

$ 5,000.00

1,664.00

213. Miscellaneous Drainage Works: —

(a.) Main sewer from Fuk-Tsun-Heung in a North-Easterly direction to Tai Po Road.-It was found possible to proceed with

a portion only of this work during the year.

1925 Estimates, ...$ 25.000.00 1925 Expenditure, $ 3,283.36

Total Estimates, ...$ 25,000.00 Expenditure to

31.12.25.

$ 3,283.36

(b.) Stormwater drains from Nanchang Street Nullah in the direction of Kaulungtong Village.-Such lengths of stormwater drains as were considered necessary were completed.

1925 Estimates, $ 10,000.00 Total Estimates, 1925 Expenditure, $ 6,609.63 Expenditure to

31.12.25,

$ 15,000.00

$ 7.903.09

(c.) Kaulungtong Development Scheme.-Sewers.—Sewers were laid in the streets and scavenging lanes at the rear of the houses nearing completion.

1925 Estimates, ...$ 50,000.00 Total Estimates, 1925 Expenditure, $ 26,867.78 Expenditure to

31.12.25,

.$100,000.00

$ 38,922.85

Page 690Page 691

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.