P.W.E. Kowloon,

180. Kowloon Bay West Reclamation, 1st Section.-This work was reterred to in paragraphs 177 of the Report for 1923 and 181 of that for last year.

By the end of the year 32,577 c. yds. of rubble has been dumped. The work is now in abeyance pending a decision on the ultimate line of the sea-wall.

$ 50,000.00 Total Estimates, ...$

30,000.00

A

1925 Estimates, 1925 Sup. Vote,

...$

$ 80,000.00

Expenditure to

31.12.25,

$127,862.90

1925 Expenditure, $ 79,984.40

181. Chinese Cemeteries.-Laying out of new areas.—The work carried out under this heading has been alluded to in paragraph 37 of this report.

1925 Estimates,

1925 Expenditure,

.$ 8,000.00

$ 4,799.81

182. King's Park,-Laying out grounds for recreation pur- poses. This work, referred to in paragraph 185 of last year's Report, was completed at the end of the year.

1925 Estimates, ...$ 70,000.00 Total Estimates, ...$170,000.00 1925 Sup. Vote,

34,000.00

14,000.00

$118,000.00 Expenditure to

31.12.25,

1925 Expenditure, $117,925.49

$191,676.69

183. Kai Tack Reclamation.-There was no work done and consequently no expenditure under this heading.

1925 Estimates,

1925 Expenditure,

$ 10,000.00

Nil.

184. Providing Plant and opening out Quarry at Taikoktsui, This was referred to in paragraph 180 of last year's Report.

All plant ordered through the Crown Agents arrived during the year.

1925 Estimates,

1925 Expenditure,

$ 67,000.00 $ 63,851.09

185. Blackhead's Point Pier. This was referred to in para- graph 235 of last year's Report and was completed by the end of that year. The retention money was paid to the Contractor on completion of the maintenance period.

1925 Estimates, 1925 Expenditure,

$ 5,000.00 $ 5,000.00