Resumptions in connection with Street Widening and Improvement Schemes, &c.,-Continued.
Scheme & Vote debited.
Hong Kong,-Continued.
P.W.E. 40, Compensation & Resumptions,-Continued.
Conduit Road, Widening.
Properties dealt with.
Amount paid.
Area in sq. ft. Rate per sq. ft. $ $ Remarks. Bonham Strand, Widening. Portion required for road widening at:- G.L. 37, Sec. A. Portion required for road widening at:--- 50.00 0.925 0.05 This amount of compensation was a round figure as agreed upon by Government and the owner. 5, Bonham Strand (M.L. 1a, Sec. A, ss. 1) 984.00 82 12.00 Morrison Hill Road & Wan-chai Road, Improvement. 191, Wanchai Road (I.L. 1584) 5,382 10.00 This compensation includes value of buildings. 157,170 193, Wanchai Road (I.L. 1419) 6,825 8.00 Resumption required in connection with the extension of the Peak Motor Road from Chamberlain Road to Victoria Gap. R.B.L. 77 Sec. A. 90.30 127 0.70 43 Resumptions.Resumptions in connection with Street Widening and Improvement Schemes, &c.,-Continued.
Scheme & Vote debited.
Hong Kong,-Continued.
P.W.E. 40, Compensation & Resumptions,-Continued.
Conduit Road, Widening.
Properties dealt with.
Amount paid.
Area in
Rate per
$
sq. ft.
sq. ft. $
Remarks.
Bonham Strand, Widening.
Portion required for road
widening at:-
G.L. 37, Sec. A.
Portion required for road
widening at:---
50.00
925
.05
This amount of compensation was a round figure as agreed upon by Government and the owner.
5, Bonham Strand (M.L.
1a, Sec. A, ss. 1)
984.00
82
12.00
Morrison Hill Road & Wan- chai Road, Improvement.
191, Wanchai Road (I.L. |\
1584)
5,382
10.00
This compensation includes value of buildings.
157,170
193, Wanchai Road (I.L.
1419)
6,825
8.00
Resumption required in con- R.B.L. 77 Sec. A.
nection with the extension of
the Peak Motor Road from Chamberlain Road to Victoria Gap.
90.30
127
.70
43