P.W.E. Kowloon.

120

necessary improvements made in front of new buildings erected during the year :—

Laichikok (Boundary Street to Shanghai Street), Kowloon City Road, Canton Road, Jordan Road, Reclamation Street, Woosung Street, Pitt Street, Nathan Road, Winslow Street, Coronation Road, Battery Street, Chi Wo Street, Wuhu Street, Shantung Street, Temple Street, Parkes Street, Granville Road, Salisbury Road, Dundas Street, Shanghai Street, Hung Hom-Kowloon City Road, Ivy Street, Portland Street, Public Square Street, Carnarvon Road.

Shanghai, Woosung and Reclamation Streets were also raised to the approved levels.

1924 Estimates, $50,000.00
1924 Sup. Vote, $4,950.00
1924 Sup. Vote, $61,000.00
$154,950.00

1924 Expenditure, $137,692.31

180. Providing plant and opening out Quarry at Taikoktsui.— The only expenditure incurred during the year in this connection was for two 2-ton Dennis Lorries.

1924 Estimates, $75,000.00
1924 Expenditure, $14,591.00

181. Kowloon Bay West Reclamation, 1st Section.— Area between New Reclamation line and Kowloon City Road and between San Shan and the proposed 100-foot road contouring the Matau-chung Nullah.—This work was referred to in paragraph 177 of last year's Report.

Edit History

2026-05-07 08:07:54 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Kowloon. 120 necessary improvements made in front of new buildings erected during the year :— Laichikok (Boundary Street to Shanghai Street), Kowloon City Road, Canton Road, Jordan Road, Reclamation Street, Woosung Street, Pitt Street, Nathan Road, Winslow Street, Coronation Road, Battery Street, Chi Wo Street, Wuhu Street, Shantung Street, Temple Street, Parkes Street, Granville Road, Salisbury Road, Dundas Street, Shanghai Street, Hung Hom-Kowloon City Road, Ivy Street, Portland Street, Public Square Street, Carnarvon Road. Shanghai, Woosung and Reclamation Streets were also raised to the approved levels. 1924 Estimates, $50,000.001924 Sup. Vote, $4,950.001924 Sup. Vote, $61,000.00$154,950.00 1924 Expenditure, $137,692.31 180. Providing plant and opening out Quarry at Taikoktsui.— The only expenditure incurred during the year in this connection was for two 2-ton Dennis Lorries. 1924 Estimates, $75,000.001924 Expenditure, $14,591.00 181. Kowloon Bay West Reclamation, 1st Section.— Area between New Reclamation line and Kowloon City Road and between San Shan and the proposed 100-foot road contouring the Matau-chung Nullah.—This work was referred to in paragraph 177 of last year's Report.
Baseline (Original)
P.W.E. Kowloon. 120 necessary improvements made in front of new buildings erected during the year :— Laichikok (Boundary Street to Shanghai. Street), Kowloon City Road. Canton Road, Jordan Road, Reclamation Street, Woosung Street, Pitt Street, Nathan Road, Winslow Street, Coronation Road, Battery Street, Chi Wo Street, Wuhu Street, Shantung Street, Temple Street, Parkes Street, Granville Road, Salisbury Road, Dundas Street, Shanghai Street, Hung Hom-Kowloon City Road, Ivy Street, Portland Street, Public Square Street, Carnarvon Road. Shanghai, Woosung and Reclamation Streets were also rais- ed to the approved levels. 1924 Estimates, $50,000.00 1924 Sup. Vote, $4,950.00 1924 Sup. Vote, $61,000.00 $154,950.00 1924 Expenditure, 137,692.31 180. Providing plant and opening out Quarry at Taikoktsui.— The only expenditure incurred during the year in this connection was for two 2-ton Dennis Lorries. 1924 Estimates, 1924 Expenditure, $75,000.00 $14,591.00 181. Kowloon Bay West Reclamation, 1st Section,-- Area be- tween New Reclamation line and Kowloon Citu Road and between San Shan and the proposed 100-foot road conturing” the Matau- chung Nullah.—This work was referred to in paragraph 177 of last year's Report. 8
2026-05-07 08:07:54 · Baseline
View content

P.W.E. Kowloon.

120

necessary improvements made in front of new buildings erected

during the year :—

Laichikok (Boundary

Street to Shanghai.

Street),

Kowloon City Road.

Canton Road,

Jordan Road,

Reclamation Street,

Woosung Street,

Pitt Street,

Nathan Road,

Winslow Street,

Coronation Road,

Battery Street,

Chi Wo Street,

Wuhu Street,

Shantung Street,

Temple Street,

Parkes Street,

Granville Road, Salisbury Road,

Dundas Street, Shanghai Street, Hung Hom-Kowloon

City Road,

Ivy Street,

Portland Street,

Public Square Street,

Carnarvon Road.

Shanghai, Woosung and Reclamation Streets were also rais-

ed to the approved levels.

1924 Estimates,

$50,000.00

1924 Sup. Vote,

$4,950.00

1924 Sup. Vote,

$61,000.00

$154,950.00

1924 Expenditure,

137,692.31

180. Providing plant and opening out Quarry at Taikoktsui.— The only expenditure incurred during the year in this connection was for two 2-ton Dennis Lorries.

1924 Estimates,

1924 Expenditure,

$75,000.00 $14,591.00

181. Kowloon Bay West Reclamation, 1st Section,-- Area be- tween New Reclamation line and Kowloon Citu Road and between San Shan and the proposed 100-foot road conturing” the Matau- chung Nullah.—This work was referred to in paragraph 177 of last year's Report.