P.W.E. Hongkong.

141. Lowering Water Mains in City to give better Cover. --The work done under this Vote was only of a minor importance.

1924 Estimates, $8,000.00 Total Estimates,

1924 Expenditure, $1,459.35 Total Expenditure, $1,692.14

142. Mount Cameron Development,--Temporary arrangements for water supply (not including distribution service) —This work was referred to in paragraph 152 of last year's Report.

During the year a line of 3" W. I. pipe, 4,200 feet in length, was laid from the Peak system along the new path from Wanchai Gap leading to R. B. L. 237, but so far little development has taken place.

1924 Estimates, $4,000.00 Total Estimates, 1924 Expenditure, $2,694.75 Total Expenditure, $4,563.90

143. Bankers, Taitam Tuk Pumping Station.—This work was referred to in paragraph 153 of last year's Report.

No work has been carried out in connection with coal bunkers, as work on the Extensions to the Pumping Station was in progress.

No expenditure was incurred during the year.

1924 Estimates, $15,000.00 1924 Expenditure, Nil

144. New Rising Main to 750 foot Tank (9″).—This work was referred to in paragraph 155 of last year's Report.

The laying of the new 8" wrought iron pipes with screwed on flanges was commenced, completed, and in use in July. About 2,300 lin. feet of 8" W.I. piping was laid.

1924 Estimates, $10,000.00 Total Estimates, $30,000.00 1924 Sup. Vote, $6,000 $16,000.00 1924 Expenditure, $4,722.08 Total Expenditure, $16,015.21

145. Conduit and Hatton Roads Development Scheme:

(a). Diverting Peak Pumping Main.

(b). Diverting Distribution Main.

This work was referred to in paragraph 156 of last year's Report.

Edit History

2026-05-07 08:06:29 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 107 P.W.E. Hongkong. 141. Lowering Water Mains in City to give better Cover. --The work done under this Vote was only of a minor importance. 1924 Estimates, $8,000.00 Total Estimates, 1924 Expenditure, $1,459.35 Total Expenditure, $1,692.14 142. Mount Cameron Development,--Temporary arrangements for water supply (not including distribution service) —This work was referred to in paragraph 152 of last year's Report. During the year a line of 3" W. I. pipe, 4,200 feet in length, was laid from the Peak system along the new path from Wanchai Gap leading to R. B. L. 237, but so far little development has taken place. 1924 Estimates, $4,000.00 Total Estimates, 1924 Expenditure, $2,694.75 Total Expenditure, $4,563.90 143. Bankers, Taitam Tuk Pumping Station.—This work was referred to in paragraph 153 of last year's Report. No work has been carried out in connection with coal bunkers, as work on the Extensions to the Pumping Station was in progress. No expenditure was incurred during the year. 1924 Estimates, $15,000.00 1924 Expenditure, Nil 144. New Rising Main to 750 foot Tank (9″).—This work was referred to in paragraph 155 of last year's Report. The laying of the new 8" wrought iron pipes with screwed on flanges was commenced, completed, and in use in July. About 2,300 lin. feet of 8" W.I. piping was laid. 1924 Estimates, $10,000.00 Total Estimates, $30,000.00 1924 Sup. Vote, $6,000 $16,000.00 1924 Expenditure, $4,722.08 Total Expenditure, $16,015.21 145. Conduit and Hatton Roads Development Scheme: (a). Diverting Peak Pumping Main. (b). Diverting Distribution Main. This work was referred to in paragraph 156 of last year's Report.
Baseline (Original)
Q 107 P.W.E. Hongkong.. 141. Lowering Water Mains in City to give better Cover. --The work done under this Vote was only of a minor importance. 1924 Estimates,..... $8,000.00 Total Estimates, | 1924 Expenditure,... $ 1,459.35 | Total Expenditure,....$ 1,692.14 142. Mount Cameron Development,--Temporary arrangements for water supply (not including distribution service) —This work was referred to in paragraph 15z of last year's Report. During the year a line of 3" W. I. pipe, 4,200 feet in length, was laid from the Peak system along the new path from Wanchai Gap leading to R. B. L. 237, but so far little development has taken place. 1924 Estimates, $ 4,000.00 | Total Estimates, 1924 Expenditure,...$ 2.694.75 | Total Expenditure,.. $ 4,563.90- 143. Bankers, Taitam Tuk Pumping Station.—This work was referred to in paragraph 153 of last year's Report. No work has been carried out in connection with coal bunkers. as work on the Extensions to the Pumping Station was in progress.. No expenditure was incurred during the year. 1924 Estimates, 1924 Expenditure, $15,000.00 Nil 144. New Rising Main to 750 foot Tank (9′′).—This work was referred to in paragraph 155 of last year's Report. The laying of the new 8" wrought iron pipes with screwed on flanges was comnienced, completed, and in use in July. About 2,300 lin. feet of 8" W.I. piping was laid. 1924 Estimates.......$10,000.00 | Total Estimates,......$30,000.00 1924 Sup. Vote, ... 6,000 $16,000.00 1924 Expenditure,...$ 4,722.08 Total Expenditure,..$16,015.21 145. Conduit and Hatton Roads Development Scheme:- (a). Diverting Peak Pumping Main. (b). Diverting Distribution Main. This work was referred to in paragraph 156 of last year's. Report.
2026-05-07 08:06:29 · Baseline
View content

Q 107

P.W.E. Hongkong..

141. Lowering Water Mains in City to give better Cover. --The work done under this Vote was only of a minor importance.

1924 Estimates,..... $8,000.00 Total Estimates,

|

1924 Expenditure,... $ 1,459.35 | Total Expenditure,....$ 1,692.14

142. Mount Cameron Development,--Temporary arrangements for water supply (not including distribution service) —This work was referred to in paragraph 15z of last year's Report.

During the year a line of 3" W. I. pipe, 4,200 feet in length, was laid from the Peak system along the new path from Wanchai Gap leading to R. B. L. 237, but so far little development has taken place.

1924 Estimates, $ 4,000.00 | Total Estimates, 1924 Expenditure,...$ 2.694.75 | Total Expenditure,.. $ 4,563.90-

143. Bankers, Taitam Tuk Pumping Station.—This work was referred to in paragraph 153 of last year's Report.

No work has been carried out in connection with coal bunkers. as work on the Extensions to the Pumping Station was in progress..

No expenditure was incurred during the year.

1924 Estimates,

1924 Expenditure,

$15,000.00 Nil

144. New Rising Main to 750 foot Tank (9′′).—This work was referred to in paragraph 155 of last year's Report.

The laying of the new 8" wrought iron pipes with screwed on flanges was comnienced, completed, and in use in July. About 2,300 lin. feet of 8" W.I. piping was laid.

1924 Estimates.......$10,000.00 | Total Estimates,......$30,000.00 1924 Sup. Vote,

...

6,000

$16,000.00

1924 Expenditure,...$ 4,722.08 Total Expenditure,..$16,015.21

145. Conduit and Hatton Roads Development Scheme:-

(a). Diverting Peak Pumping Main.

(b). Diverting Distribution Main.

This work was referred to in paragraph 156 of last year's. Report.