P.W.E. Hongkong.

124, Roads:--

(a.) Improving and widening road through Quarry Bay Village.--This work was referred to in paragraph 120 (a.) of last year's Report.

The progress made was very unsatisfactory, due to the dilatory manner in which the Contractor carried out his work. The Contract was closed in July.

The excavation within the area of the Quarry was completed and the material deposited in the Reclamation; but this was not the case below Taikoo Terrace. The main culverts were extended as far as possible to carry the road on its new alignment.

1924 Estimates, $ 50,000.00 Total Estimates. $360,000.00 1924 Sup. Vote, 50,000.00 $100,000.00 Expenditure to 1924 Expenditure, $ 31,903.44 31.12.24, $186,578.11

(b.) Road from Taitam Gap to Shek-O.--This work was referred to in paragraph 120 (b) of last year's Report.

The section let under contract to Mr. Ng Wah was duly completed by July.

1924 Estimates, $ 17,000.00 Total Estimates, $492,000.00 1924 Sup. Vote, 40,000.00 $ 57,000.00 Expenditure to 31.12.24, 1924 Expenditure, $ 50,679.30 $379,749.85

(c.) Extending 20-foot Road from Magazine Gap to Victoria Gap, Stubbs Road.—This work was referred to in paragraph 120 (c.) of last year's Report.

The progress made during the year was not satisfactory, typhoon and rainstorm damages, as well as a shortage of filling material, greatly retarded the work. The Mt. Kellett Road Bridge was completed, and the banks above Pokfulam Reservoir were made good.

At the close of the year, this work was nearly completed. There remained only the retention money to be paid to the Contractor on the final making up of the bank of the motor road to the South of the proposed garage site, below Plunkett's Road.

1924 Estimates, $20,000.00 Total Estimates, $200,000.00 1924 Sup. Vote, 15,000.00 $35,000.00 Expenditure to 31.12.24, 1924 Expenditure, $19,726.18 $226,616.40

Edit History

2026-05-07 08:04:06 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 91 P.W.E. Hongkong. 124, Roads:-- (a.) Improving and widening road through Quarry Bay Village.--This work was referred to in paragraph 120 (a.) of last year's Report. The progress made was very unsatisfactory, due to the dilatory manner in which the Contractor carried out his work. The Contract was closed in July. The excavation within the area of the Quarry was completed and the material deposited in the Reclamation; but this was not the case below Taikoo Terrace. The main culverts were extended as far as possible to carry the road on its new alignment. 1924 Estimates, $ 50,000.00 Total Estimates. $360,000.00 1924 Sup. Vote, 50,000.00 $100,000.00 Expenditure to 1924 Expenditure, $ 31,903.44 31.12.24, $186,578.11 (b.) Road from Taitam Gap to Shek-O.--This work was referred to in paragraph 120 (b) of last year's Report. The section let under contract to Mr. Ng Wah was duly completed by July. 1924 Estimates, $ 17,000.00 Total Estimates, $492,000.00 1924 Sup. Vote, 40,000.00 $ 57,000.00 Expenditure to 31.12.24, 1924 Expenditure, $ 50,679.30 $379,749.85 (c.) Extending 20-foot Road from Magazine Gap to Victoria Gap, Stubbs Road.—This work was referred to in paragraph 120 (c.) of last year's Report. The progress made during the year was not satisfactory, typhoon and rainstorm damages, as well as a shortage of filling material, greatly retarded the work. The Mt. Kellett Road Bridge was completed, and the banks above Pokfulam Reservoir were made good. At the close of the year, this work was nearly completed. There remained only the retention money to be paid to the Contractor on the final making up of the bank of the motor road to the South of the proposed garage site, below Plunkett's Road. 1924 Estimates, $20,000.00 Total Estimates, $200,000.00 1924 Sup. Vote, 15,000.00 $35,000.00 Expenditure to 31.12.24, 1924 Expenditure, $19,726.18 $226,616.40
Baseline (Original)
Q 91 P.W.E. Hongkong. 124, Roads:-- (a.) Improving and widening road through Quarry Bay Village.--This work was referred to in paragraph 120 (a.) of last year's Report. The progress made was very unsatisfactory, due to the dilatory manner in which the Contractor carried out his work. The Contract was closed in July. The excavation within the area of the Quarry was completed and the material deposited in the Reclamation; but this was not the case below Taikoo Terrace. The main culverts were extended as far as possible to carry the road on its new alignment. 1924 Estimates, 1924 Sup. Vote, $ 50,000.00 Total Estimates. ...$360,000,00 50,000.00 $100,000.00 Expenditure to 1924 Expenditure, ...$ 31,903.44 31.12.24, $186,578.11 .. (b.) Road from Taitam Gap to Shek-0.-This work was referred to in paragrph 120 (6) of last year's Report. The section let under contract to Mr. Ng Wah was duly completed by July. 1924 Estimates, ...$ 17,000.00 | Total Estimates,... $492,000.00 1924 Sup. Vote, 40,000.00 $ 57,000.00 Expenditure to 31.12.24, 1924 Expenditure, $ 50,679.30 .$379,749.85 (c.) Extending 20-foot Road from Magazine Gap to Victoria Gap, Stubbs Road.—This work was referred to in paragraph 120 (c.) of last year's Report. The progress made during the year was not satisfactory, typhoon and rainstorm damages, as well as a shortage of filling material, greatly retarded the work. The Mt. Kellett Road Bridge was completed, and the banks above Pokfulam Reservoir were made good. At the close of the year, this work was nearly completed. There remained only the retention money to be paid to the Contractor on the final making up of the bank of the motor road to the South of the proposed garage site, below Plunkett's Road. 1924 Estimates, $20,000.00 Total Estimates, ... $200,000.00 1924 Sup. Vote, 15,000.00 *** | $35,000,00 Expenditure to 1924 Expenditure, $19,726.18 31.12.24, $226,616.40
2026-05-07 08:04:06 · Baseline
View content

Q 91

P.W.E. Hongkong.

124, Roads:--

(a.) Improving and widening road through Quarry Bay Village.--This work was referred to in paragraph 120 (a.) of last year's Report.

The progress made was very unsatisfactory, due to the dilatory manner in which the Contractor carried out his work. The Contract was closed in July.

The excavation within the area of the Quarry was completed and the material deposited in the Reclamation; but this was not the case below Taikoo Terrace. The main culverts were extended as far as possible to carry the road on its new alignment.

1924 Estimates,

1924 Sup. Vote,

$ 50,000.00 Total Estimates. ...$360,000,00

50,000.00

$100,000.00 Expenditure to

1924 Expenditure, ...$ 31,903.44

31.12.24, $186,578.11

..

(b.) Road from Taitam Gap to Shek-0.-This work was referred to in paragrph 120 (6) of last year's Report.

The section let under contract to Mr. Ng Wah was duly completed by July.

1924 Estimates, ...$ 17,000.00 | Total Estimates,... $492,000.00 1924 Sup. Vote,

40,000.00

$ 57,000.00

Expenditure to

31.12.24,

1924 Expenditure, $ 50,679.30

.$379,749.85

(c.) Extending 20-foot Road from Magazine Gap to Victoria Gap, Stubbs Road.—This work was referred to in paragraph 120 (c.) of last year's Report.

The progress made during the year was not satisfactory, typhoon and rainstorm damages, as

well as a shortage of filling material, greatly retarded the work. The Mt. Kellett Road Bridge was completed, and the banks above Pokfulam Reservoir were made good.

At the close of the year, this work was nearly completed. There remained only the retention money to be paid to the Contractor on the final making up of the bank of the motor road to the South of the proposed garage site, below Plunkett's Road.

1924 Estimates, $20,000.00 Total Estimates, ... $200,000.00 1924 Sup. Vote, 15,000.00

***

|

$35,000,00 Expenditure to 1924 Expenditure, $19,726.18 31.12.24,

$226,616.40