116. Government Civil Hospital—Structural Alterations to “C” Block.—Nothing remained to be done during the year beyond the completion of the ward kitchen, referred to in last year's Report, which was completed early in the year.

1924 Estimates, $10,000.00 Total Estimates, ...$
1924 Expenditure, $5,696.66
Expenditure to 31.12.24, $9,891.96

117. Government Civil Hospital—Extension Quarters.—This work consists of a three-storey brick building adjoining the present quarters, Shanghai Plaster being used externally, and contains 14 bedrooms, a sitting room for the Matron, and the usual bathrooms, box rooms, etc.

The contract was let to Messrs. Trollope and Colls (Far East), Ltd., in May, and satisfactory progress made with the work, the building at the end of the year being up to the first floor level.

1924 Estimates, $50,000.00
1924 Expenditure, $28,785.11
Total Estimates, ...$
Expenditure to 31.12.24, $28,785.11

118. Chair Coolie Shelters. This work was referred to in paragraph 234 of last year's Report.

The three shelters at:
(a) Garden Road, at its junction with Bowen Road,
(b) Macdonnell Road, to the West of Calder Path, and
(c) Glenealy, at its junction with Albert Road,
were satisfactorily completed towards the end of the year.

1924 Estimates, $3,200.00
1924 Expenditure, $2,693.11
Total Estimates, ...$
Expenditure to 31.12.24, $2,693.11

119. Motor Garage near P.W.D. Offices.—This building, to accommodate 6 cars with a workshop attached, was constructed in brick with Asbestos sheet roofing carried on reinforced concrete purlins.

A contract for the work was let to Messrs. Yee Lee & Co. in June, and by the end of the year it was satisfactorily completed.

1924 Estimates, $5,000.00
1924 Sup: Vote, $10,000.00
Total Estimates, $15,000.00
1924 Expenditure, $13,769.72
Expenditure to 31.12.24, $13,769.72

Edit History

2026-05-07 08:03:41 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Hong Kong. Q 88 116. Government Civil Hospital—Structural Alterations to “C” Block.—Nothing remained to be done during the year beyond the completion of the ward kitchen, referred to in last year's Report, which was completed early in the year. 1924 Estimates, $10,000.00 Total Estimates, ...$ 1924 Expenditure, $5,696.66 Expenditure to 31.12.24, $9,891.96 117. Government Civil Hospital—Extension Quarters.—This work consists of a three-storey brick building adjoining the present quarters, Shanghai Plaster being used externally, and contains 14 bedrooms, a sitting room for the Matron, and the usual bathrooms, box rooms, etc. The contract was let to Messrs. Trollope and Colls (Far East), Ltd., in May, and satisfactory progress made with the work, the building at the end of the year being up to the first floor level. 1924 Estimates, $50,000.00 1924 Expenditure, $28,785.11 Total Estimates, ...$ Expenditure to 31.12.24, $28,785.11 118. Chair Coolie Shelters. This work was referred to in paragraph 234 of last year's Report. The three shelters at: (a) Garden Road, at its junction with Bowen Road, (b) Macdonnell Road, to the West of Calder Path, and (c) Glenealy, at its junction with Albert Road, were satisfactorily completed towards the end of the year. 1924 Estimates, $3,200.00 1924 Expenditure, $2,693.11 Total Estimates, ...$ Expenditure to 31.12.24, $2,693.11 119. Motor Garage near P.W.D. Offices.—This building, to accommodate 6 cars with a workshop attached, was constructed in brick with Asbestos sheet roofing carried on reinforced concrete purlins. A contract for the work was let to Messrs. Yee Lee & Co. in June, and by the end of the year it was satisfactorily completed. 1924 Estimates, $5,000.00 1924 Sup: Vote, $10,000.00 Total Estimates, $15,000.00 1924 Expenditure, $13,769.72 Expenditure to 31.12.24, $13,769.72
Baseline (Original)
P.W.E. Ho gkong. Q 88 ―.com 116. Government Ciril Hospital-Structural Alterations to “C” Block,—Nothing remained to be done during the year beyond the completion of the ward kitchen, referred to in last year's Report, which was completed early in the year. 1924 Estimates,.. .$10,000.00 Total Estimates, ...$ 1924 Expenditure, $5,696.66 | Expenditure to 31.12.24...... $9,891.96 to Sisters" 117. Gorerument Civil Hospital— Extension Quarters :-This work consists of a three-storey brick building adjoining the present quarters, Shanghai Plaster being used externally, and contains 14 bedrooms, a sitting room for the Matron, and the usual bathrooms, box rooms, etc. The contract was let to Messrs. Trollope and Colls (Far East), Ltd., in May, and satisfactory progress made with the work, the building at the end of the year being up to the first floor level. 1924 Estimates, .$50,000.00 1924 Expenditure, $28,785.11 118. Chair Coolie Shelters. paragraph 234 of last year's Report. Total Estimates, ...$ Expenditure to 31.12.24 ...... $28,785.11 This work was referred to in The three shelters at :- (a.) Garden Road, at its junction with Bowen Road, (b.) Macdonnell Road, to the West of Calder Path, and (r.) Glenealy, at its junction with Albert Road, were satisfactorily completed towards the end of the year. 1924 Estimates.......$ 3,200.00 1924 Expenditure... $ 2,693.11 | Total Estimates, ...$ Expenditure to 31.12.24,.... $ 2,693 11 119. Motor Garage near P.W.D. Offices.-This building, to accommodate 6 cars with a workshop attached, was constructed in brick with Asbestos sheet roofing carried on reinforced con- crete purlins. A contract for the work was let to Messrs. Yee Lee & Co. in June, and by the end of the year it was satisfactorily completed. 1924 Estimates, 1924 Sup: Vote, $ 5,000.00 10,000.00 Total Estimates, ...$ ****** $15,000.00 Expenditure to 1924 Expenditure, $13,769.72 31.12.24, ...$13,769.72
2026-05-07 08:03:41 · Baseline
View content

P.W.E. Ho gkong.

Q 88

―.com

116. Government Ciril Hospital-Structural Alterations to “C” Block,—Nothing remained to be done during the year beyond the completion of the ward kitchen, referred to in last year's Report, which was completed early in the year.

1924 Estimates,..

.$10,000.00 Total Estimates, ...$

1924 Expenditure, $5,696.66 |

Expenditure to

31.12.24......

$9,891.96

to Sisters"

117. Gorerument Civil Hospital— Extension Quarters :-This work consists of a three-storey brick building adjoining the present quarters, Shanghai Plaster being used externally, and contains 14 bedrooms, a sitting room for the Matron, and the usual bathrooms, box rooms, etc.

The contract was let to Messrs. Trollope and Colls (Far East), Ltd., in May, and satisfactory progress made with the work, the building at the end of the year being up to the first floor level.

1924 Estimates,

.$50,000.00

1924 Expenditure, $28,785.11

118. Chair Coolie Shelters. paragraph 234 of last year's Report.

Total Estimates, ...$ Expenditure to

31.12.24 ......

$28,785.11

This work was referred to in

The three shelters at :-

(a.) Garden Road, at its junction with Bowen Road, (b.) Macdonnell Road, to the West of Calder Path, and (r.) Glenealy, at its junction with Albert Road, were satisfactorily completed towards the end of the

year.

1924 Estimates.......$ 3,200.00

1924 Expenditure... $ 2,693.11 |

Total Estimates, ...$ Expenditure to

31.12.24,.... $ 2,693 11

119. Motor Garage near P.W.D. Offices.-This building, to accommodate 6 cars with a workshop attached, was constructed in brick with Asbestos sheet roofing carried on reinforced con- crete purlins.

A contract for the work was let to Messrs. Yee Lee & Co. in June, and by the end of the year it was satisfactorily completed.

1924 Estimates,

1924 Sup: Vote,

$ 5,000.00 10,000.00

Total Estimates, ...$

******

$15,000.00

Expenditure to

1924 Expenditure, $13,769.72

31.12.24,

...$13,769.72