P.W.E. Hongkong.
106. Government Stores Extension.—This work consists of :-
(a) Covering the existing Store at the South end of the yard with a reinforced concrete roof carried on concrete piers,
(b) The erection of a brick store for oil and cement adjacent to the Main Store Building,
For these two items of work, a contract was let to Messrs. Yee Lee & Co. in September, and by the end of the year the work was almost completed.
1924 Estimates, $15,000.00 Total Estimates, 1924 Expenditure, $7,739.58 Expenditure to 31.12.24 $7,750.31107. Coal Storage and Motor Garage, Wanchai Depôt.--This work, referred to in paragraph 114 of last year's Report, was practically completed during the year.
1924 Estimates, $10,000.00 1924 Sup. Vote, $8,000.00 $18,000.00 1924 Expenditure, $17,482.39108. Garage – Stubbs Road. This work was referred to in paragraph 115 of last year's Report.
Satisfactory progress was made during the year, the building being completed in July. A certain amount of work was subsequently required to be done owing to trouble with the bank at the rear of the site. This work, which consisted of facing the bank with granite, was nearing completion at the end of the year.
1924 Estimates.. $10,000.00 Total Estimates, 1924 Sup. Vote..... $11,000.00 $21,000.00 Expenditure to 31.12.24, $26,957.24 1924 Expenditure, $20,659.01109. New Infectious Diseases Hospital.-It was not found possible to proceed with this work during the year.
1924 Estimates, $30,000.00 Total Estimates, 1924 Expenditure,... $ Expenditure to 31.12.24, $110. New Government Offices - Alterations to the General Post Office. This work was referred to in paragraph 117 of last year's report.
85
P.W.E. Hongkong.
106. Government Stores Extension.—This work consists of :-
(a.) Covering the existing Store at the South end of the yard with a reinforced concrete roof carried on concrete piers,
(b.) The erection of a brick store for oil and cement
adjacent to the Main Store Building,
For these two items of work, a contract was let to Messrs. Yee Lee & Co. in September, and by the end of the year the work was almost completed.
1924 Estimates, ............. .$ 15,000.00 | Total Estimates,
$
1924 Expenditure,...$ 7,739.58
Expenditure to
31.12.24..
$ 7,750.31
107. Coal Storage and Motor Garage, Wanchai Depôt.--This work, referred to in paragraph 114 of last year's Report, was practically completed during the year.
1924 Estimates, 1924 Sup. Vote,
1924 Expenditure,..
$ 10,000.00 8,000,00
$ 18,000.00
$ 17,482.39
108. Garage – Stubbs Road. This work was referred to in paragraph 115 of last year's Report.
Satisfactory progress was made during the year, the building being completed in July. A certain amount of work was subse- quently required to be done owing to trouble with the bank at the rear of the site. This work, which consisted of facing the bank with granite, was nearing completion at the end of the year.
1924 Estimates.. ..$ 10,000.00 | Total Estimates,......$ 1924 Sup. Vote.....
11,000.00
$21,000.00
Expenditure to
31.12.24, ......... $ 26,957.24
1924 Expenditure,..... $ 20,659.01
109, New Infectious Diseases Hospital.-It was not found possible to proceed with this work during the year.
$ 30,000.00 | Total Estimates,
1924 Estimates,
1924 Expenditure, ...$
| Expenditure to
31.12.24,
$
110. New Government Offices - Alterations to the General Post Office. This work was referred to in paragraph 117 of last.
year's report.