P.W.E. Kowloon.
90
160. Training Nullahs
(a) Mongkoktsui Nullah East, Extension through Railway Bridge.—A Contract for this work was let in June to Messrs. Li Hing Bros. and by the end of the year excavation for the Foundations was well in hand.
1922 Estimates, $116,000.00
1922 Expenditure, $750.00
(b) Waterloo Road Nullah, Extension to Temple.—A Contract for this work was let in June to Messrs. Li Hing Bros.
The construction is of rubble face work with lime and cement concrete backing and cement concrete invert and foundations, the latter being carried on China Fir piles.
By the end of the year satisfactory progress had been made.
1922 Estimates, $21,000.00
1922 Expenditure, $5,000.00
(c) Extending Mongkoktsui Nullah to Boundary of Old Kowloon.—This nullah was completed in July and was referred to in paragraph 141 (6) of last year's Report.
By the end of the year all liabilities had been discharged against the work.
1922 Estimates, ...
1922 Sup. Vote, $10,000.00 | Total Estimates, $34,675.50
Expenditure to 31/12/22, $34,675.50
1922 Expenditure, $50,969.33
(d) General Works. No work was carried out during the year under this Vote.
1922 Estimates, $10,000.00
1922 Expenditure, ...
VII.
P.W.E. Kowloon.
90
160. Training Nullahs
(u) Mongkokisui Nullah East, Extension through Railway Bridge-A Contract for this work was let in June to Messrs. Li Hing Bros. and by the end of the year excavation for the Foundations was well in hand.
1922 Estimates,
1922 Expenditure,...
$ 116,000.00 750.00
(b) Waterloo Road Nullah, Extension to Temple.—A Con- tract for this work was let in June to Messrs. Li Hing Bros,
The construction is of rubble face work with lime and cement concrete backing and cement concrete invert and foundations, the latter being carried on China Fir piles.
By the end of the year satisfactory progress had been made.
1922 Estimates.
1922 Expenditure,
$21,000.00
5.000.00
(c.) Extending Mongkoktsui Nullah to Boundary of Old Kowloon.—This nullah was completed in July and was referred to in paragraph 141 (6) of last year's Report.
By the end of the year all liabilities had been discharged against the work,
1922 Estimates,
...
1922 Sup. Vote,
$10,000.00 | Total Estimates,
24,675.50
$34,675.50 Expenditure to
1922 Expenditure.... 34,675.50 | 31/12/22..
$50.96933
(1.) General Works. No work was carried out during the
year under this Vote.
1922 Estimates, 1922 Expenditure,
$10,000,00
Vil.
No comments yet.
Private notes are available after approval.