P.W.E. Hongkong.

Q 58

There is an Admissions and Casualties Room near the entrance, and a Dispensary and small Venereal Clinic are also embodied in the Building. The work was continued during the year with but little delay, and the building was completed during December.

1922 Estimates. 1922 Sup. Vote...
35,000.00 | Total Estimates. 15,449.91
$ 50,449.91 | Expenditure to 1922 Expenditure...... 50,319.81 31/12/22.
...$ 57,541.71

Page 363

93. Quarters for Scavenging Coolies, Belchers Street. ---This work was referred to in paragraph 89 of last year's Report. With the exception of a short delay during the general strike, the work proceeded satisfactorily during the early part of the year, and the building was completed and occupied at the end of June.

1922 Estimates..
1922 Sup. Vote....
30,000.00 | Total Estimates................ $135,000.00
20,500.00
$ 50,500.00 Expenditure to
1922 Expenditure... 48,360.07 | 31/12/22.
109,975.36

94. Temporary School for Chinese Boys;—Morrison Gap Road. — This work was referred to in paragraph 178 of last year's Report, and is fully described therein. At the commencement of the year the site preparation had already begun and the erection of the building, which was shortly afterwards commenced, proceeded without interruption, and was completed together with the supply of furniture ready for occupation on the opening of the Autumn term in September.

1922 Estimates
1922 Expenditure.
$ 28,000.00 31,385.67

95. Suiyingpun School.-This work was briefly referred to in paragraph 98 of last year's Report.

The building is designed to accommodate 1,000 pupils, the main block occupying three sides of the site, with the latrines detached, on the fourth side. A swimming pool is provided on the lower ground to the N.W. and a fairly large Playground remains in the centre of the quadrangle thus formed.

The main block-three storeys-will comprise the following accommodation :--Assembly Hall, 29 Class Rooms, Laboratories, Library and Museum, Art Room, Handicraft Rooms, Gymnasium and Changing Rooms, Recreation Room, Head Master's Office and General Office, Masters and Mistresses Common Rooms, Cloak Room accommodation, and Coolie Quarters. A covered Playground is provided beneath the Assembly Hall and on the same level as the central quadrangle.

Sketch plans, and subsequently working drawings were in course of preparation during the year, and during November

Page 363

Edit History

2026-05-07 03:14:38 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Hongkong. Q 58 There is an Admissions and Casualties Room near the entrance, and a Dispensary and small Venereal Clinic are also embodied in the Building. The work was continued during the year with but little delay, and the building was completed during December. 1922 Estimates. 1922 Sup. Vote... 35,000.00 | Total Estimates. 15,449.91 $ 50,449.91 | Expenditure to 1922 Expenditure...... 50,319.81 31/12/22. ...$ 57,541.71 Page 363 93. Quarters for Scavenging Coolies, Belchers Street. ---This work was referred to in paragraph 89 of last year's Report. With the exception of a short delay during the general strike, the work proceeded satisfactorily during the early part of the year, and the building was completed and occupied at the end of June. 1922 Estimates.. 1922 Sup. Vote.... 30,000.00 | Total Estimates................ $135,000.00 20,500.00 $ 50,500.00 Expenditure to 1922 Expenditure... 48,360.07 | 31/12/22. 109,975.36 94. Temporary School for Chinese Boys;—Morrison Gap Road. This work was referred to in paragraph 178 of last year's Report, and is fully described therein. At the commencement of the year the site preparation had already begun and the erection of the building, which was shortly afterwards commenced, proceeded without interruption, and was completed together with the supply of furniture ready for occupation on the opening of the Autumn term in September. 1922 Estimates 1922 Expenditure. $ 28,000.00 31,385.67 95. Suiyingpun School.-This work was briefly referred to in paragraph 98 of last year's Report. The building is designed to accommodate 1,000 pupils, the main block occupying three sides of the site, with the latrines detached, on the fourth side. A swimming pool is provided on the lower ground to the N.W. and a fairly large Playground remains in the centre of the quadrangle thus formed. The main block-three storeys-will comprise the following accommodation :--Assembly Hall, 29 Class Rooms, Laboratories, Library and Museum, Art Room, Handicraft Rooms, Gymnasium and Changing Rooms, Recreation Room, Head Master's Office and General Office, Masters and Mistresses Common Rooms, Cloak Room accommodation, and Coolie Quarters. A covered Playground is provided beneath the Assembly Hall and on the same level as the central quadrangle. Sketch plans, and subsequently working drawings were in course of preparation during the year, and during November Page 363
Baseline (Original)
P.W.E. Hongkong. Q 58 There is an Admissions and Casualties Room near the entrauce, and a Dispensary and small Venereal Clinic are also embodied in the Building. The work was continued during the year with but little delay, and the building was completed during December. 1922 Estimates. 1922 Sup. Vote... 35,000.00 | Total Estimates. 15,449.91 $ 50,149.91 | Expenditure to 1922 Expenditure...... 50,319.81 31/12/22. ...$ 57,541.71 93. Quarters for Scavenging Coolies, Belchers Street. ---This work was referred to in paragraph 89 of last year's Report. With - the exception of a short delay during the general strike, the work proceeded satisfactorily during the early part of the year, and the building was completed and occupied at the end of June. 1922 Estimates.. 1922 Sup. Vote.... 30,000.00 | Total Estimates................ $135,000,00 20,500.00 $ 50,500.00 Expenditure to 1922 Expenditure... 48,360.07 | 31/12/22. 109,975.36 94. Temporary School for Chinese Boys;—Morrison Gap Rend. This work was referred to in paragraph 178 of last year's Report, and is fully described therein. At the commencement of the year the site preparation had already begun and the erection of the building, which was shortly afterwards commenced, proceeded without interruption, and was completed together with the supply of furniture ready for occupation on the opening of the Autumn term in September. 1922 Estimates 1922 Expenditure. $ 28,000.00 31,385.67 95. Suiyingpun School.-This work was briefly referred to in paragraph 98 of last year's Report. The building is designed to accommodate 1,000 pupils, the main block occupying three sides of the site, with the latrines. detached, on the fourth side. A swimming pool is provided on the lower ground to the N.W. and a fairly large Playground remains in the centre of the quadrangle thus formed. The main block-three storeys-will comprise the following accommodation :--Assembly Hall, 29 Class Rooms, Laboratories, Library and Museum, Art Room, Handicraft Rooms, Gymnasium and Changing Rooms, Recreation Room, Head Master's Office and General Office, Masters and Mistresses Common Rooms, Cloak Room accommodation, and Coolie Quarters. A covered Playground is provided beneath the Assembly Hall and on the same level as the central quadrangle. Sketch plans, and subsequently working drawings were in course of preparation during the year, and during November
2026-05-07 03:14:38 · Baseline
View content

P.W.E. Hongkong.

Q 58

There is an Admissions and Casualties Room near the entrauce, and a Dispensary and small Venereal Clinic are also embodied in the Building. The work was continued during the year with but little delay, and the building was completed during December.

1922 Estimates. 1922 Sup. Vote...

35,000.00 | Total Estimates. 15,449.91

$ 50,149.91 | Expenditure to 1922 Expenditure...... 50,319.81 31/12/22.

...$ 57,541.71

93. Quarters for Scavenging Coolies, Belchers Street. ---This work was referred to in paragraph 89 of last year's Report. With - the exception of a short delay during the general strike, the work proceeded satisfactorily during the early part of the year, and the building was completed and occupied at the end of June.

1922 Estimates..

1922 Sup. Vote....

30,000.00 | Total Estimates................ $135,000,00 20,500.00

$ 50,500.00 Expenditure to

1922 Expenditure... 48,360.07 | 31/12/22.

109,975.36

94. Temporary School for Chinese Boys;—Morrison Gap Rend. — This work was referred to in paragraph 178 of last year's Report, and is fully described therein. At the commencement of the year the site preparation had already begun and the erection of the building, which was shortly afterwards commenced, proceeded without interruption, and was completed together with the supply of furniture ready for occupation on the opening of the Autumn term in September.

1922 Estimates

1922 Expenditure.

$ 28,000.00 31,385.67

95. Suiyingpun School.-This work was briefly referred to in paragraph 98 of last year's Report.

The building is designed to accommodate 1,000 pupils, the main block occupying three sides of the site, with the latrines. detached, on the fourth side. A swimming pool is provided on the lower ground to the N.W. and a fairly large Playground remains in the centre of the quadrangle thus formed.

The main block-three storeys-will comprise the following accommodation :--Assembly Hall, 29 Class Rooms, Laboratories, Library and Museum, Art Room, Handicraft Rooms, Gymnasium and Changing Rooms, Recreation Room, Head Master's Office and General Office, Masters and Mistresses Common Rooms, Cloak Room accommodation, and Coolie Quarters. A covered Playground is provided beneath the Assembly Hall and on the same level as the central quadrangle.

Sketch plans, and subsequently working drawings were in course of preparation during the year, and during November