ANNEXE B.-Continued.

PROVISION- ESTIMATED. ACTUAL. INCREASE. DECREASE. ALLY, BALANCE. EXCESS.

VOTED.

C. 2. C. C. c.

Brought forward. 3,152,200 1,822,262.97 181,821.72 1,511,768.75 220,464.05 1,551,708.66 1,297.58

Kowloon,- Continued.

Miscellaneous,—Continued.

58. Enlarging Playground at Kowloon British School... 4,000 3,997.59 2.41 2.41

59. King's Park Quarters,-Installing water-closets 2,000 893.12 1,106.88 1,106.88

60. Chinese Cemeteries,-Laying out new areas 1,000 991.13 8.87 8.87

61. Miscellaneous Works 7,000 5,853.21 1,146.79 1,146.79

Public Health and Buildings Ordinance, 1903.

62. Compensation and Resumptions Water Works,

63. Substituting 18″ main for existing 12″ from Kowloon Filter Beds to Yau-mati.............. 50,000 23,706.22 26,293.78 26,293.78

64. Enlarging mains to improve the distribution system in Kowloon.......... 150,000 115,479.51 34,520.49 34,520.49

65. Miscellaneous Water Works ... 50,000 44,647.13 5,352.87 5,352.87

8,000 6,926.03 1,073.97 1,073.97

New Territories.

Buildings.

66. Block House, Shatin Gap 3,000 2,470.18 529.82 529.82

67. Public Latrines and Urinals 15,000 5,093.34 9,906.66 9,906.66

Communications.

68. Roads :-

(a) Taipo Road, Widening and improving road between Shatin and Taipo 29,000.00 10,122.22 18,877.78

(b) Metalling and tarring road from Fanling to Castle Peak 49,053.00 18,736.80 30,316.20

(c) Fencing alongside new roads 10,000 9,928.52 71.48 71.48

(d) Road to Kowloon Walled City 5,000 5,000.00

(e) Path (3 feet wide) along Frontier to Lin Tong for Police Patrol 14,000 14,000.00

Drainage.

69. Training Nullahs-

(a) Storm-water culverts in connection with Sham Shui Po Reclamation 30,000 20,550.66 9,449.34 9,449.34

(b) Training main stream at Lai Chi Kok 20,000 20,000.00

(c) General Works 25,000 24,623.42 376.58 376.58

70. Miscellaneous Drainage Works:-

(a) Kowloon City Reclamation Sewerage Scheme 10,000 10,000.00

(b) General Works 12,269.88 2,269.88 10,000.00 7,400.00 5,130.12

Carried forward........ ..$ 3,636,200 2,218,676.89 233,285.58 1,650,808.69 305,917.05 1,724,737.74 1,297.58

Edit History

2026-05-06 22:48:46 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 82 ANNEXE B.-Continued. PROVISION- ESTIMATED. ACTUAL. INCREASE. DECREASE. ALLY, BALANCE. EXCESS. VOTED. C. 2. C. C. c. Brought forward. 3,152,200 1,822,262.97 181,821.72 1,511,768.75 220,464.05 1,551,708.66 1,297.58 Kowloon,- Continued. Miscellaneous,—Continued. 58. Enlarging Playground at Kowloon British School... 4,000 3,997.59 2.41 2.41 59. King's Park Quarters,-Installing water-closets 2,000 893.12 1,106.88 1,106.88 60. Chinese Cemeteries,-Laying out new areas 1,000 991.13 8.87 8.87 61. Miscellaneous Works 7,000 5,853.21 1,146.79 1,146.79 Public Health and Buildings Ordinance, 1903. 62. Compensation and Resumptions Water Works, 63. Substituting 18″ main for existing 12″ from Kowloon Filter Beds to Yau-mati.............. 50,000 23,706.22 26,293.78 26,293.78 64. Enlarging mains to improve the distribution system in Kowloon.......... 150,000 115,479.51 34,520.49 34,520.49 65. Miscellaneous Water Works ... 50,000 44,647.13 5,352.87 5,352.87 8,000 6,926.03 1,073.97 1,073.97 New Territories. Buildings. 66. Block House, Shatin Gap 3,000 2,470.18 529.82 529.82 67. Public Latrines and Urinals 15,000 5,093.34 9,906.66 9,906.66 Communications. 68. Roads :- (a) Taipo Road, Widening and improving road between Shatin and Taipo 29,000.00 10,122.22 18,877.78 (b) Metalling and tarring road from Fanling to Castle Peak 49,053.00 18,736.80 30,316.20 (c) Fencing alongside new roads 10,000 9,928.52 71.48 71.48 (d) Road to Kowloon Walled City 5,000 5,000.00 (e) Path (3 feet wide) along Frontier to Lin Tong for Police Patrol 14,000 14,000.00 Drainage. 69. Training Nullahs- (a) Storm-water culverts in connection with Sham Shui Po Reclamation 30,000 20,550.66 9,449.34 9,449.34 (b) Training main stream at Lai Chi Kok 20,000 20,000.00 (c) General Works 25,000 24,623.42 376.58 376.58 70. Miscellaneous Drainage Works:- (a) Kowloon City Reclamation Sewerage Scheme 10,000 10,000.00 (b) General Works 12,269.88 2,269.88 10,000.00 7,400.00 5,130.12 Carried forward........ ..$ 3,636,200 2,218,676.89 233,285.58 1,650,808.69 305,917.05 1,724,737.74 1,297.58
Baseline (Original)
HEADS AND SUB-HEADS. Q 82 ANNEXE B.-Continued. PROVISION- ESTIMATED. ACTUAL. INCREASE. DECREASE. ALLY, BALANCE. EXCESS. VOTED. C. 2. C. C. c. Brought forheard. 3,152,200 1,822,262.97 181,821.721,511,768.75 220,464.05 1,551,708.66 1.297.58 Kowloon,- Continued, Miscellaneous,—Continued. 58. Enlarging Playground at Kowloon British School... 4,000 3,997.59 2.11 2.41 59. King's Park Quarters,-lustalling water-closets 2,000 893.12 1,106.88 1,106.88 60. Chinese Cemeteries,-Laying out new areas 1,000 991,13 8.87 61. Miscellaneous Works 7,000 5,853.21 1,146,79 8.87 1,146.79 Public Health and Buildings Ordinance, 1903. 62. Compensation and Resumptions Water Works, 63. Substituting 18' main for existing 12′′ from Kowloon Filter Beds to Yau- mati.............. 50,000 23,706.22 26,298.78 26,293.78 150,000 115,479.51 34,520,49 34,520.49 64. Enlarging mains to improve the distri- bntion system in Kowloon.......... ! 50,000 44,647.13 5,352.87 5,352,87 65. Miscellaneous Water Works ... 8,000 6,926.03 1,073.97 1,073.97 New Territories. Buildings. 66. Block House, Shatin Gap 67. Public Latrines and Urinals 3,000 15,000 2,470.18 5,093.34 529.82 9,906,66 529.82 9,906.66 Communications. 68. Roads :- (a) Taipo Road, Widening and improving road between Shatin and Taipo 10,000 28,877.78 19,877.78 29,000.00 10,122.22 () Metalling and tarring road from Fauling to Castle Penk 60,000 90,316,20 30,316.20 i 49,053.00 * 18,736,80 (c) Fencing alongside new roads (d) Road to Kowloon Walled City (e) Path (3 feet wide) along Fron- 10,000 9,928.52 5,000 71.48 5,000.00 71.48 5,000,00 ter to Lin Tong for Police Patrol 14,000 14,000.00 14,000.00 Drainage. 69. Training Nullahs- (a) Storm-water culverts in con- nection with Sham Shui Po Reclamation 30,000 20,550.66 9,649.34 9,619,34 () Training main stream at Lai Chi Kok 20,000 (c) General Works 25,000 24,623.42 20,000.00 376.58 20,000.00 376.58 70. Miscellaneous Drainage Works:- (a) Kowloon City Reclamation Sewerage Scheme (b) General Works 10,000 10,000 10,000.00 12,269.88 2,269.88 10,000.00 7,400.00 5,130.12 Carried forward........ ..$ 3,636,200 2,218,676.89 233,285.58 1,650,808.69 305,917,05 1,724.737.74 1,297.58
2026-05-06 22:48:46 · Baseline
View content

HEADS AND SUB-HEADS.

Q 82

ANNEXE B.-Continued.

PROVISION-

ESTIMATED. ACTUAL. INCREASE. DECREASE. ALLY, BALANCE. EXCESS.

VOTED.

C.

2.

C.

C.

c.

Brought forheard.

3,152,200 1,822,262.97

181,821.721,511,768.75 220,464.05 1,551,708.66

1.297.58

Kowloon,- Continued,

Miscellaneous,—Continued.

58. Enlarging Playground at Kowloon

British School...

4,000

3,997.59

2.11

2.41

59. King's Park Quarters,-lustalling

water-closets

2,000

893.12

1,106.88

1,106.88

60. Chinese Cemeteries,-Laying out new

areas

1,000

991,13

8.87

61. Miscellaneous Works

7,000

5,853.21

1,146,79

8.87 1,146.79

Public Health and Buildings Ordinance, 1903.

62. Compensation and Resumptions

Water Works,

63. Substituting 18' main for existing 12′′ from Kowloon Filter Beds to Yau- mati..............

50,000

23,706.22

26,298.78

26,293.78

150,000

115,479.51

34,520,49

34,520.49

64. Enlarging mains to improve the distri- bntion system in Kowloon..........

!

50,000

44,647.13

5,352.87

5,352,87

65. Miscellaneous Water Works ...

8,000

6,926.03

1,073.97

1,073.97

New Territories.

Buildings.

66. Block House, Shatin Gap 67. Public Latrines and Urinals

3,000

15,000

2,470.18 5,093.34

529.82 9,906,66

529.82 9,906.66

Communications.

68. Roads :-

(a) Taipo Road, Widening and improving road between Shatin

and Taipo

10,000

28,877.78 19,877.78

29,000.00 10,122.22

() Metalling and tarring road from

Fauling to Castle Penk

60,000

90,316,20

30,316.20

i

49,053.00 * 18,736,80

(c) Fencing alongside new roads (d) Road to Kowloon Walled City (e) Path (3 feet wide) along Fron-

10,000

9,928.52

5,000

71.48 5,000.00

71.48 5,000,00

ter to Lin Tong for Police Patrol

14,000

14,000.00

14,000.00

Drainage.

69. Training Nullahs-

(a) Storm-water culverts in con- nection with Sham Shui Po Reclamation

30,000

20,550.66

9,649.34

9,619,34

() Training main stream at Lai

Chi Kok

20,000

(c) General Works

25,000 24,623.42

20,000.00 376.58

20,000.00 376.58

70. Miscellaneous Drainage Works:-

(a) Kowloon City Reclamation

Sewerage Scheme

(b) General Works

10,000 10,000

10,000.00

12,269.88

2,269.88

10,000.00 7,400.00 5,130.12

Carried forward........ ..$ 3,636,200 2,218,676.89 233,285.58

1,650,808.69 305,917,05

1,724.737.74 1,297.58