Work on the section between No. 10 Bridge and Aberdeen Docks was also commenced and by the end of the year many of the dangerous bends were improved, and the bridges widened.

1920 Estimates, $40,000.00

1920 Supplementary Vote, $15,277.46

1920 Expenditure, $55,277.46

$54,795.52

(j.) Raising Praya Wall and Roadway (Connaught Road West) West of Morrison Street.—The Tramway track, referred to in paragraph 98 (o) of last year's Report, having been relaid to an improved level, the carriageway abutting it was similarly dealt with, the surface being finished with granite setts on the sea side and treated with asphaltum on the other.

1920 Estimates, $3,000.00

1920 Expenditure, $1,581.21

(k.) Shaukiwan,— Widening existing road between North Point and Quarry Point.—The carriageway between these points was widened to a minimum width of 35 ft., the sea-wall being erected or re-erected throughout the entire length to retain and protect such widening. A minimum width of 10′ 6′′ is provided between the nearest Tram-rail and the sea-wall.

Culverts were extended and Tramway standards and poles were moved to new positions to conform with the improved alignment.

The surfacing, which is of macadam, is coated with asphaltum.

1920 Estimates, $60,000.00

1920 Supplementary Vote, $20,000.00

1920 Expenditure, $80,000.00

$79,880.51

(l.) Shaukiwan Road,— Improvements to Shaukiwan Village.—To give greater effective width to the carriageway passing through Quarry Bay, flat concrete channelling was substituted for the existing circular channelling, and, in order to admit of traffic passing between the Tramway track and a portion of the Northern side of Quarry Bay Inland Lot No. 8, the approach path to the houses erected on this lot was set back an average depth of 8 feet.

The carriageway on the North side of the Tramway track between Sai Wan Ho Market and a point where the Tramway track takes a sharp turn to Shaukiwan Village East (about 430 yards to the Eastward of Sai Wan Ho Market) was widened to its proper alignment, kerbed, channelled and surfaced with macadam treated with asphaltum.

Edit History

2026-05-06 22:40:33 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Hongkong. Q 44 Work on the section between No. 10 Bridge and Aberdeen Docks was also commenced and by the end of the year many of the dangerous bends were improved, and the bridges widened. 1920 Estimates, $40,000.00 1920 Supplementary Vote, $15,277.46 1920 Expenditure, $55,277.46 $54,795.52 (j.) Raising Praya Wall and Roadway (Connaught Road West) West of Morrison Street.—The Tramway track, referred to in paragraph 98 (o) of last year's Report, having been relaid to an improved level, the carriageway abutting it was similarly dealt with, the surface being finished with granite setts on the sea side and treated with asphaltum on the other. 1920 Estimates, $3,000.00 1920 Expenditure, $1,581.21 (k.) Shaukiwan,— Widening existing road between North Point and Quarry Point.—The carriageway between these points was widened to a minimum width of 35 ft., the sea-wall being erected or re-erected throughout the entire length to retain and protect such widening. A minimum width of 10′ 6′′ is provided between the nearest Tram-rail and the sea-wall. Culverts were extended and Tramway standards and poles were moved to new positions to conform with the improved alignment. The surfacing, which is of macadam, is coated with asphaltum. 1920 Estimates, $60,000.00 1920 Supplementary Vote, $20,000.00 1920 Expenditure, $80,000.00 $79,880.51 (l.) Shaukiwan Road,— Improvements to Shaukiwan Village.—To give greater effective width to the carriageway passing through Quarry Bay, flat concrete channelling was substituted for the existing circular channelling, and, in order to admit of traffic passing between the Tramway track and a portion of the Northern side of Quarry Bay Inland Lot No. 8, the approach path to the houses erected on this lot was set back an average depth of 8 feet. The carriageway on the North side of the Tramway track between Sai Wan Ho Market and a point where the Tramway track takes a sharp turn to Shaukiwan Village East (about 430 yards to the Eastward of Sai Wan Ho Market) was widened to its proper alignment, kerbed, channelled and surfaced with macadam treated with asphaltum.
Baseline (Original)
P.W.E. Hongkong. Q 44 Work on the section between No. 10 Bridge and Aberdeen Docks was also commenced and by the end of the year many of the dangerous bends were improved, and the bridges widened. 1920 Estimates, $40,000.00 1920 Supplementary Vote,...... 15,277.46 1920 Expenditure, $55,277.46 54,795.52/ (j.) Raising Praya Wall and Roadway (Connaught Road West) West of Morrison Street.—The Tramway track, referred to in paragraph 98 (0) of last year's Report, having been relaid to an improved level, the carriageway abutting it was similarly dealt with, the surface being finished with granite setts on the sea side and treated with asphaltum on the other. 1920 Estimates, 1920 Expenditure, $3,000.00 $1,581.21 (k.) Shaukiwan,-- Widening existing road between North Point and Quarry Point.—The carriageway between these points was widened to a minimum width of 35 ft., the sea-wall being erected or re-erected throughout the entire length to retain and protect such widening. A minimum width of 10′ 6′′ is provided between the nearest Tram-rail and the sea-wall. Culverts were extended and Tramway standards and poles were moved to new positions to conform with the improved alignment. The surfacing, which is of macadam, is coated with asphaltum. .$60,000.00 1920 Estimates, 1920 Supplementary Vote,...... 20,000.00 1920 Expenditure, $80,000.00 79,880.51 1 (1.) Shaukiwan Road,— Improvements to Shaukiwan Village.- To give greater effective width to the carriageway passing through Quarry Bay, flat concrete channelling was substituted for the existing circular channelling, and, in order to admit of traffic passing between the Tramway track and a portion of the Northern side of Quarry Bay Inland Lot No. 8, the approach path to the houses erected on this lot was set back an average depth of 8 feet. The carriageway on the North side of the Tramway track between Sai Wan Ho Market and a point where the Tramway track takes a sharp turn to Shaukiwan Village East (about 430 yards to the Eastward of Sai Wan Ho Market) was widened to its proper alignment, kerbed, channelled and surfaced with macadam treated with asphaltum.
2026-05-06 22:40:33 · Baseline
View content

P.W.E. Hongkong.

Q 44

Work on the section between No. 10 Bridge and Aberdeen Docks was also commenced and by the end of the year many of the dangerous bends were improved, and the bridges widened.

1920 Estimates,

$40,000.00

1920 Supplementary Vote,...... 15,277.46

1920 Expenditure,

$55,277.46

54,795.52/

(j.) Raising Praya Wall and Roadway (Connaught Road West) West of Morrison Street.—The Tramway track, referred to in paragraph 98 (0) of last year's Report, having been relaid to an improved level, the carriageway abutting it was similarly dealt with, the surface being finished with granite setts on the sea side and treated with asphaltum on the other.

1920 Estimates,

1920 Expenditure,

$3,000.00 $1,581.21

(k.) Shaukiwan,-- Widening existing road between North Point and Quarry Point.—The carriageway between these points was widened to a minimum width of 35 ft., the sea-wall being erected or re-erected throughout the entire length to retain and protect such widening. A minimum width of 10′ 6′′ is provided between the nearest Tram-rail and the sea-wall.

Culverts were extended and Tramway standards and poles were moved to new positions to conform with the improved alignment.

The surfacing, which is of macadam, is coated with asphaltum.

.$60,000.00

1920 Estimates,

1920 Supplementary Vote,...... 20,000.00

1920 Expenditure,

$80,000.00 79,880.51

1

(1.) Shaukiwan Road,— Improvements to Shaukiwan Village.- To give greater effective width to the carriageway passing through Quarry Bay, flat concrete channelling was substituted for the existing circular channelling, and, in order to admit of traffic passing between the Tramway track and a portion of the Northern side of Quarry Bay Inland Lot No. 8, the approach path to the houses erected on this lot was set back an average depth of 8 feet.

The carriageway on the North side of the Tramway track between Sai Wan Ho Market and a point where the Tramway track takes a sharp turn to Shaukiwan Village East (about 430 yards to the Eastward of Sai Wan Ho Market) was widened to its proper alignment, kerbed, channelled and surfaced with macadam treated with asphaltum.