# CONSTRUCTION ACCOUNT-FANLING BRANCH
Expenditure to 31st December, 1917. Expenditure during 1918. Expenditure to end of 1918.
$ C. $ C. $ C.
II.—Land, Land,. 2,389.45 2,389.45
(a) Ballast, 11.05 11.05
VII.-Track, (6) Permanent Way, 46,651.14 46,651.14
VIII. Station and Buildings,........ (a) Station Buildings, 3,447.08 3,447.08
(e) Locomotive, 15,237.89 15,237.89
IX.-Plant,.. (f) Carriages, 21,762.36 21,762.36
X.-General Charges, (a) 1. Salaries, 309.60 309.60
Total of Fanling Branch Line Construction, $89,808.57 $89,808.57
I.
Main-Head.
CONSTRUCTION ACCOUNT-FANLING BRANCH.
II.
Sub-Head.
III.
IV.
V.
Expenditure to Expenditure Expenditure to 31st December, during 1918. end of 1918.
1917.
$
..
$
C.
$
C.
II.—Land,
Land,.
2,389.45
2,389.45
(a) Ballast,
11.05
11.05
VII.-Track,
(6) Permanent Way,
46,651.14
46,651,14
VIII. Station and Buildings,........
(a) Station Buildings,
3,447,08
3,447.08
(e) Locomotive,
15,237.89
15,237.89
IX.-Plant,..
(f) Carriages,
21,762.36
21,762.36
X.-General Charges,
(a) 1. Salaries,
309.60
309.60
Total of Fanling Branch Line
Construction,
$89,808,57
$89,808.57
No comments yet.
Private notes are available after approval.