P.W.E. Hongkong.

representing in some cases only a portion of the cost owing to the work extending into more than one year :-

(i.) Construction of 6" and 4" sewer from Shauki-wan Road to I. L's 1917, 2027 and Tsat Tsz Mui Police Station (completed),

Cost of Work, ... $1,872.76

Less contributions by Lessees, 330.00

$1,542.76

(ii.) Extension of 6" sewer and 9" and 6" storm-water drains in High Street and Lane east of I. L. 689, Bonham Road, (completed),

Cost of work, $978.04

Less contribution by Lessee,... 916.40

$61.64

(iii.) Extension of 6" sewer in Lane east of I.L. 309, Blacksmith's Lane, (completed),

Cost of work, $206.72

Less contribution by Lessee,... 216.55

Cr.,... $9.83

(iv.) Extension of 9" sewer in Shing On Street to I.L. 2165, Wongneichong, (completed),

(v.) Extension of 9" sewer in Main Street, Aberdeen, (completed),...

(vi.) Extension of 6" sewer in Bowen Road from near I.L. 1570 to opposite I.L.'s 2237 and 2238 (completed),

Cost of work, ... $3,950.52

Less contributions by Lessees, 1,921.34

$1,451.65

469.69

(vii.) Extension of 6" sewer to I.L. 2071, Mount Parish, (completed),

Cost of work, $473.74

Less contribution by Lessee, 100.00

$373.74

(viii.) Extension of 9" storm-water drain in Queen's Road Central between Wing Kut Street and Wing Wo Street, (completed),

$246.05

+

(ix.) Extension of 6" sewer to S.I.L's 440-441, Sai Wan Ho, (completed),...

... $125.53

(x.) Extension of 6" and 9" sewer and 9" storm-water drain in Sands Street and new road north of J.L. 2091 (completed),

$1,725.90

$1,563.66

(xi.) Extension of 9" sewer in Wongneichong Road from Sing Woo Road to I.L. 2065 (completed),

(xii.) Extension of 6" sewer to IL. 2205, Conduit Road, (2nd extension), (completed), ...

(xiii.) Extension of storm-water drain along new main road to north-west angle of Dock Company's premises, Aberdeen, (completed),

$133.02

$2,719.08

Edit History

2026-05-06 19:13:18 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 63 P.W.E. Hongkong. representing in some cases only a portion of the cost owing to the work extending into more than one year :- (i.) Construction of 6" and 4" sewer from Shauki-wan Road to I. L's 1917, 2027 and Tsat Tsz Mui Police Station (completed), Cost of Work, ... $1,872.76 Less contributions by Lessees, 330.00 $1,542.76 (ii.) Extension of 6" sewer and 9" and 6" storm-water drains in High Street and Lane east of I. L. 689, Bonham Road, (completed), Cost of work, $978.04 Less contribution by Lessee,... 916.40 $61.64 (iii.) Extension of 6" sewer in Lane east of I.L. 309, Blacksmith's Lane, (completed), Cost of work, $206.72 Less contribution by Lessee,... 216.55 Cr.,... $9.83 (iv.) Extension of 9" sewer in Shing On Street to I.L. 2165, Wongneichong, (completed), (v.) Extension of 9" sewer in Main Street, Aberdeen, (completed),... (vi.) Extension of 6" sewer in Bowen Road from near I.L. 1570 to opposite I.L.'s 2237 and 2238 (completed), Cost of work, ... $3,950.52 Less contributions by Lessees, 1,921.34 $1,451.65 469.69 (vii.) Extension of 6" sewer to I.L. 2071, Mount Parish, (completed), Cost of work, $473.74 Less contribution by Lessee, 100.00 $373.74 (viii.) Extension of 9" storm-water drain in Queen's Road Central between Wing Kut Street and Wing Wo Street, (completed), $246.05 + (ix.) Extension of 6" sewer to S.I.L's 440-441, Sai Wan Ho, (completed),... ... $125.53 (x.) Extension of 6" and 9" sewer and 9" storm-water drain in Sands Street and new road north of J.L. 2091 (completed), $1,725.90 $1,563.66 (xi.) Extension of 9" sewer in Wongneichong Road from Sing Woo Road to I.L. 2065 (completed), (xii.) Extension of 6" sewer to IL. 2205, Conduit Road, (2nd extension), (completed), ... (xiii.) Extension of storm-water drain along new main road to north-west angle of Dock Company's premises, Aberdeen, (completed), $133.02 $2,719.08
Baseline (Original)
Q 63 P.W.E. Hongkong. representing in some cases only a portion of the cost owing to the work extending into more than one year :- (i.) Construction of 6" and 4" sewer from Shauki- wan Road to I. L's 1917, 2027 and Tsat Tsz Mui Police Station (completed), Cost of Work, ... Less contributions by Lessees, $1,872.76 330.00 $1,542.76 (ii.) Extension of 6" sewer and 9" and 6" storm- water drains in High Street and Lane east of I. L. 689, Bonham Road, (completed), Cost of work, Less contribution by Lessee,... $978.04 916.40 61.64 (iii.) Extension of 6" sewer in Lane east of I.L. 309, Blacksmith's Lane, (completed), Cost of work, Less contribution by Lessee,... Cr.,... $206.72 216.55 $ 9.83 (iv.) Extension of 9" sewer in Shing On Street to I.L. 2165, Wongneichong, (completed), (v.) Extension of 9" sewer in Main Street, Aberdeen, (completed),... (vi.) Extension of 6" sewer in Bowen Road from near I.L. 1570 to opposite I.L.'s 2237 and 2238 (completed), Cost of work, ... Less contributions by Lessees, 397.83 3,950.52 $1,921.34 1,451.65 469.69 (vii.) Extension of 6" sewer to I.L. 2071, Mount Parish, (completed), Cost of work, Less contribution by Lessee, $473.74 100.00 373.74 (viii.) Extension of 9" storm-water drain in Queen's Road Central between Wing Kut Street and Wing Wo Street, (completed), 246,05 + (ix.) Extension of 6" sewer to S.I.L's 440-441, Sai Wan Ho, (completed),... ... 125.53 (x.) Extension of 6" and 9" sewer and 9" storm-water drain in Sands Street and new road north of J.L. 2091 (completed), 1,725.90 1,563.66 (xi.) Extension of 9" sewer in Wongneichong Road from Sing Woo Road to I.L. 2065 (completed), (xii.) Extension of 6" sewer to IL. 2205, Conduit Road, (2nd extension), (completed), ... (xiii.) Extension of storm-water drain along new main road to north-west angle of Dock Company's premises, Aberdeen, (completed), 133.02 2,719.08
2026-05-06 19:13:18 · Baseline
View content

Q 63

P.W.E. Hongkong.

representing in some cases only a portion of the cost owing to the work extending into more than one year :-

(i.) Construction of 6" and 4" sewer from Shauki- wan Road to I. L's 1917, 2027 and Tsat Tsz Mui Police Station (completed),

Cost of Work, ...

Less contributions by Lessees,

$1,872.76 330.00

$1,542.76

(ii.) Extension of 6" sewer and 9" and 6" storm- water drains in High Street and Lane east of I. L. 689, Bonham Road, (completed), Cost of work,

Less contribution by Lessee,...

$978.04

916.40

61.64

(iii.) Extension of 6" sewer in Lane east of I.L. 309,

Blacksmith's Lane, (completed),

Cost of work,

Less contribution by Lessee,...

Cr.,...

$206.72 216.55

$ 9.83

(iv.) Extension of 9" sewer in Shing On Street to

I.L. 2165, Wongneichong, (completed),

(v.) Extension of 9" sewer in Main Street, Aberdeen,

(completed),...

(vi.) Extension of 6" sewer in Bowen Road from near I.L. 1570 to opposite I.L.'s 2237 and 2238

(completed),

Cost of work,

...

Less contributions by Lessees,

397.83

3,950.52

$1,921.34

1,451.65

469.69

(vii.) Extension of 6" sewer to I.L. 2071, Mount

Parish, (completed),

Cost of work,

Less contribution by Lessee,

$473.74 100.00

373.74

(viii.) Extension of 9" storm-water drain in Queen's Road Central between Wing Kut Street and Wing Wo Street, (completed),

246,05

+

(ix.) Extension of 6" sewer to S.I.L's 440-441, Sai

Wan Ho, (completed),...

...

125.53

(x.) Extension of 6" and 9" sewer and 9" storm-water drain in Sands Street and new road north of J.L. 2091 (completed),

1,725.90

1,563.66

(xi.) Extension of 9" sewer in Wongneichong Road from Sing Woo Road to I.L. 2065 (completed), (xii.) Extension of 6" sewer to IL. 2205, Conduit

Road, (2nd extension), (completed), ...

(xiii.) Extension of storm-water drain along new main road to north-west angle of Dock Company's premises, Aberdeen, (completed),

133.02

2,719.08