P.W.E. Hongkong.
Q 62
(xii) Extension of 6" sewer and (5″ storm-water drain in Mallory Street from Praya East (completed), (xiii) Extension of 6" sewer in Sharp Street East for I.L. 729, R.P., (completed),
Cost of work, $737.13
Less contribution by lessees, $376.73 200.00 176.73
(xiv.) Extension of 9" storm-water drain in Catchick Street from Davis Street eastwards (completed), 609.65
(xv.) Extension of 9" storm-water drain in Kennedy Road opposite I.L. 1945 (completed), 249.93
(xvi.) Extension of 6" sewer to I.L. 2205, Conduit Road, (completed),
Cost of work, $418.05
Less contribution by lessees, $250.00 168.05
(xvii.) Construction of 9" storm-water overflow from sewer to storm-water drain at the junction of Garden Road and Queen's Road Central (completed),... 134.51
(xviii.) Extension of 6" sewer to I.L. 2169, Lard Factory above Smithfield, Kennedy Town, (completed), 165.72
(xix.) Extension of 6" sewer to S.I.L. 433, Shaukiwan East, (completed), 411.49
(xx.) Extension of 9" and 6" sewers and 12" and 9" storm-water drains in Landale Street on M.L. 23, Praya East (completed), 1,795.08
(xxi.) Extension of 12″ storm-water drain in Queen's Road East, east of Fletcher Street, (completed), 913.28
(xxii.) Extension of 6" sewer and 9" storm-water drain to lane on I.L. 734 in Sharp Street East from Matheson Street (completed), 383.46
(xxiii.) Construction of additional gullies and connections and altering existing ones in Matheson Street and Sharp Street East (completed), 349.42
(xxiv.) Construction of additional gullies and connections near I.L. 2089, Ship Street, (completed), 31.91
(xxv.) Relaying 12" storm-water drain with 18" earthenware pipes in Rutter Street between Po Yan Street and Pound Lane (completed), 786.86
(xxvi.) Extension of storm-water drain in Holland Street to M.L. 268, R.P., (completed),
Cost of work, $197.58
Less contribution by lessee, $164.16 33.42 752.32
(xxvii.) Extension of 4" sewer to urinal in May Road, east of Peak Tramway, (completed),...
P.W.E. Hongkong.
Q 62
(xii) Extension of 6" sewer and (5′′ storm-water drain in Mallory Street from Praya East (completed), (xiii) Extension of 6" sewer in Sharp Street East for
I.L. 729, R.P., (completed),
Cost of work,
$737,13
Less contribution by lessees,
$376.73 200.00
176.73
(xiv.) Extension of 9" storm-water drain in Catchick Street from Davis Street eastwards (completed),
609.65
(xv.) Extension of 9" storm-water drain in Kennedy
Road opposite I.L. 1945 (completed),
249.93
(xvi.) Extension of 6" sewer to I.L. 2205, Conduit
Road, (completed),
Cost of work,
Less contribution by lessees,
$418.05 250.00
168.05
(xvii.) Construction of 9" storm-water overflow from sewer to storm-water drain at the junction of Garden Road and Queen's Road Central (com- pleted),...
134.51
(xviii.) Extension of 6" sewer to I.L. 2169, Lard Factory
above Smithfield, Kennedy Town, (completed),
165.72
(xix.) Extension of 6" sewer to S.I.L. 433, Shaukiwan
East, (completed),
411.49
(xx.) Extension of 9" and 6" sewers and 12" and 9" storm-water drains in Landale Street on M.L. 23, Praya East (completed),
(xxi.) Extension of 12′′ storm-water drain in Queen's Road East, east of Fletcher Street, (completed), (xxii.) Extension of fi" sewer and 9" storu-water drain to lane on I.L. 734 in Sharp Street East from Matheson Street (completed),
(xxiii.) Construction of additional gullies and
1,795.08
913.28
383.46
con-
349.42
31.91
nections and altering existing ones in Matheson Street and Sharp Street East (completed),
(xxiv.) Construction of additional gullies and con- nections near L.L. 2089, Ship Street, (completed), (xxv.) Relaying 12" storm-water drain with 18" ear- thenware pipes in Rutter Street between Po Yan Street and Pound Lane (completed),
(xxvi.) Extension of storm-water drain in Holland
Street to M.L. 268, R.P., (completed),
786.86
Cost of work,
Less contribution by lessee,
$197.58
164.16
33.42
752.32
(xxvii.) Extension of 4" sewer to urinal in May Road,
east of Peak Tramway, (completed),...
No comments yet.
Private notes are available after approval.