P.W.E. New Territories.
-Q 78
All liabilities were discharged before the close of the year.
1916 Estimates,..... $3,000.00
Amount erroneously
debited to Vote in
Total Estimates,... $14,500.00
1915 and subsequent-
ly credited to Vote
in 1916,
6,703.34*
Total,... $9,703.34
Expenditure to
1916 Expenditure, 6,160.81
31/12/16,
13,699.29
(c.) Kam Tin to Fanling viâ Ha Tsia Gap.--A survey of the centre line for a distance of 14 miles was made and levels were taken, but it was decided to postpone the work for the time being. No expenditure was incurred.
1916 Estimates $33,000.00 Total Estimates, $33,000.00 1916 Expenditure, Nil. Expenditure to 31/12/16, Nil.(d) Sha Kong Mui to Ping Shan.-It was decided not to proceed with this work.
1916 Estimates, $4,200.00 1916 Expenditure, Nil.(e.) Branch Road from Shanghai Street to Shamshuipo. This work was undertaken to link up the village of Shamshuipo, where extensive developments are taking place, with the Kowloon road system. A Contract for it was let in May, the road being completed and opened for traffic before the close of the year.
The road, which is 20 feet wide and 2,400 feet in length, is constructed along the line of a future main road, which has been laid out with a width of 100 feet. It is partly on embankment, about 11 feet high, where it crosses a tidal flat, and partly in cutting, the quantity of material used in its formation amounting to 15,000 cubic yards. A masonry culvert, 8 feet × 5 feet, provides for the escape of stormwater from the low-lying area, the drainage of which has been intercepted by the embankment.
A number of resumptions were necessary to enable the work to be carried out and, in several cases, new lots were granted in exchange for the old, compensation being paid for the removal and re-erection of the buildings. The total amount expended in connection with such resumptions and exchanges amounted to $4,494.58. One lot, the owner of which could not be found, still remains to be dealt with. The new lots granted were levelled off in connection with the formation of the road.
Certain liabilities remained outstanding at the close of the year.
1916 Estimates, $12,500.00 Total Estimates, $12,500.00 1916 Expenditure, 11,933.47 Expenditure to 31/12/16, 11,933.47* In Annexe B, this amount is credited by deducting the whole of the sum expended and showing only the balance ($542.53), the sum of $3,000 provided in the Estimates remaining intact.
P.W.E. New Territories.
-Q 78
All liabilities were discharged before the close of the year.
1916 Estimates,..... $3,000.00
Amount erroneously
debited to Vote in
Total Estimates,... $14,500.00
1915 and subsequent-
ly credited to Vote
in 1916,
6,703.34*
Total,... $9,703.34
Expenditure to
1916 Expenditure, 6,160.81 31/12/16,
13,699.29
(c.) Kam Tin to Fanling viâ Ha Tsia Gap.--A survey of the centre line for a distance of 14 miles was made and levels were taken, but it was decided to postpone the work for the time being. No expenditure was incurred.
1916 Estimates..... $33,000.00 | Total Estimates, ...$33,000.00
1916 Expenditure,
|
Nil.
Expenditure to
31/12/16,
Nil.
(d) Sha Kong Mui to Ping Shan.-It was decided not to proceed with this work.
1916 Estimates,.
1916 Expenditure,
$4,200.00
Nil.
(e.) Branch Road from Shanghai Street to Shamshuipo. This work was undertaken to link up the village of Shamshuipo, where extensive developments are taking place, with the Kowloon road system. A Contract for it was let in May, the road being completed and opened for traffic before the close of the year.
The road, which is 20 feet wide and 2,400 feet in length, is constructed along the line of a future main road, which has been laid out with a width of 100 feet. It is partly on embankment, about 11 feet high, where it crosses a tidal flat, and partly in cutting, the quantity of material used in its formation amounting to 15,000 cubic yards. A masonry culvert, 8 feet × 5 feet, provides for the escape of stormwater from the low-lying area, the drainage of which has been intercepted by the embankment.
A number of resumptions were necessary to enable the work to be carried out and, in several cases, new lots were granted in exchange for the old, compensation being paid for the removal and re-erection of the buildings. The total amount expended in con- nection with such resumptions and exchanges amounted to $4,494.58. One lot, the owner of which could not be found, still remains to be dealt with. The new lots granted were levelled off in connection with the formation of the road.
year.
Certain liabilities remained outstanding at the close of the
1916 Estimates, $12,500.00
1916 Expenditure,
11,933.47
Total Estimates, Expenditure to 31/12/16,
$12,500.00
.11,933.47
* In Annexe B, this amount is credited by deducting the whole of the sum expended and showing only the balance ($542.53), the sum of $3,000 provided in the Estimates remaining intact.