P.W.E. New Territories.
Q F +
157. Market, Tai O.-It was decided to postpone the execution of this work and no expenditure was incurred.
158. Tai Po Land Office,-Additions to provide quarters for Bailiff.-As it was found impossible to obtain what was regarded as a satisfactory tender for this work from local Contractors, it was decided to carry out the work departmentally, all plant, labour, materials, etc., being provided directly by the Government. Work was begun in July and was practically completed by the end of the year.
The work consists of the erection of a second storey over a portion of the Tai Po Land Office, the building having been originally designed to take a second storey. The accommodation provided includes a living room, 19′ 4″ x 16′ 4″, two bedrooms, 16′ 4″ x 16′ 0″ and 17′ 4″ × 17′ 0″ respectively, a verandah, 19′ 0″ × 8′ 0″, a hall, 17′ 0″ x 8′ 0″, two bathrooms, a European kitchen, a store, a coal cellar and 3 servants' rooms. An internal concrete stair gives access to the quarters and an external concrete stair to the servants' quarters. Externally the extension is in conformity with the original building, the walls being of brickwork in cement, with granite dressings, the whole being roofed with double pan and roll tiling.
1915 Estimates, $7,500.00 Total Estimates, $13,980.00 1915 Sup. Vote, 6,480.00 1915 Expenditure, 13,954.89 Expenditure to 31/12/15, 13,954.89159. Police Station, — Tai Ku Ling.-It was decided to postpone the execution of this work and no expenditure was incurred.
160. Roads:-
(a.) Extension at Castle Peak Bay, including construction of Pier.-This work was fully described in last year's Report (p. 85). The road and pier were completed by the end of March.
1915 Estimates, $1,000.00 Total Estimates, $11,600.00 1915 Expenditure, 716.58 Expenditure to 31/12/15, 11,240.00(b.) Tai Po to Fan Ling, including bridge over river.—This road was fully described in last year's Report (p. 8.).
The whole of the work was finally completed in June and all liabilities were discharged before the close of the year.
1915 Estimates, $6,000.00 Total Estimates, $46,000.00 1915 Sup. Vote, 10,810.09 $16,810.09 1915 Expenditure, 16,810.09 Expenditure to 31/12/15, 53,592.34P.W.E. New Territories.
Q F +
157. Market, Tai 0.-It was decided to postpone the execution of this work and no expenditure was incurred.
158. Tai Po Land Office,-Additions to provide quarters for Bailiff.-As it was found impossible to obtain what was regarded as a satisfactory tender for this work from local Contractors, it was decided to carry out the work departmentally, all plant, labour, materials, etc., being provided directly by the Government. Work was begun in July and was practically completed by the end of the
year.
The work consists of the erection of second storey over a portion of the Tai Po Land Office, the building having been origin- ally designed to take a second storey. The ecommodation provided includes a living room, 19′ 4′′x 16′ 4′′, two bedrooms, 16′ 4′′x 16′ 0′′ and 17′ 4′′ × 17′ 0′′ respectively, a verandah, 19′ 0′′×8′ ()", a hall, 17' 0"x8' 0", two bathrooms, a European kitchen, a store, a coal cellar and 3 servants' rooms. Au internal concrete stair gives access to the quarters and an external concrete stair to the servants' quar- ters. Externally the extension is in conformity with the original building, the walls being of brickwork in cement, with granite dressings, the whole being roofed with double pan and roll tiling.
1915 Estimates, 1915 Sup. Vote,
$7,500.00 Total Estimates,
6,480,00
$7,500.00
$13,980.00
Expenditure to
1915 Expenditure, 13,954.89
31/12/15,
13,954.89
159. Police Station, —Ta Ku Linj.-It was decided to postpone the execution of this work and no expenditure was incurred.
160. Rouds:-
(a.) Extension at Castle Peak Bay, including construction of Pier. -This work was fully described in last year's Report (p. 85). The road and pier were completed by the end of March,
1915 Estimates,
1915 Expenditure,
$1,000.00 Total Estimates,
716.58
$11,600.00
Expenditure to
31,1215,
11,240.00
(b.) Tai Po to Fan Ling, including bridg_j_river.—This road
was fully described in last year's Report (p. §.).,
The whole of the work was finally competed in June and all liabilities were discharged before the close of the year.
1915 Estimates, 1915 Sup. Vote,
|
$ 6,000.00 Total Estates, ...$46,000.00
10,810.09
$16,810 09 Expenditure to
1915 Expenditure, 16,810.09 |
31/12/15,
53,592.34
No comments yet.
Private notes are available after approval.