AnnualReport-1915 — Page 438

Administrative Reports 行政報告書 All AI Reviewed

P.W.E. Hongkong.

61

1915 Estimates, $7,000.00 Total Estimates,

1915 Expenditure, 3,643.99*

Total Estimates, $7,000.00 Expenditure to 31/12/15,

3,643.99*

(e.) Wongneichong Village - Extension of two nullahs east and west of I.L. 1926.—This work forms a continuation of that undertaken in 1913, another Farm Lot (F.L. 45) having been converted into Inland Lots. The work was begun in the latter part of the year and had not reached completion at its close.

A length of the main nullah, that on the east of I.L. 1926, measuring 207 feet, was undertaken, besides 138 feet of the branch nullah to the west of I.L. 1926. The inverts are of cement concrete, 4" thick, laid on a foundation of lime and cement concrete, and the side walls are of rubble masonry, built in lime mortar and finished with a coping of cement concrete. The main nullah averages 7' 0" wide by 10' 0" deep and the branch nullah 5′ 3′′ wide by 10′ 6′′ deep.

A portion of the branch nullah, 93 feet in length, has been arched over with cement concrete to provide for its being crossed by a future public road.

1915 Estimates,.....$9,700.00

1915 Expenditure,.. 5,231.46

Total Estimates,. Expenditure to 31/12/15,..

$9,700.00

5,231.46

(f.) General Works.-The following is a statement of the works carried out under this heading:-

(i.) Magazine Gap-District south of Gap ---Completion of item (iv) of last year's Report, (completed), (ii) Training nullah west of I.L. 1942, Conduit Road. including small branches, (completed) :- Length trained. Lin. Ft. Expenditure. Main stream, 220 $847.20 Branches, 291 385.68 (iii) Training stream-course west of old Pumping Station, Bonham Road, (completed), 287 $1,077.59 (iv.) Training stream-courses between Ship Street and Kennedy Road, (completed). 280 Cost of work.... $1,232.88 Less contribution by lessees, 350.00 $727.59

* A sum of $64.25 was erroneously debited to this sub-head instead of to sub-head (e). The expenditure therefore appears as $3,708.24 in Annexe B.

Edit History

2026-05-06 10:50:18 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Hongkong. 61 1915 Estimates, $7,000.00 Total Estimates, 1915 Expenditure, 3,643.99* Total Estimates, $7,000.00 Expenditure to 31/12/15, 3,643.99* (e.) Wongneichong Village - Extension of two nullahs east and west of I.L. 1926.—This work forms a continuation of that undertaken in 1913, another Farm Lot (F.L. 45) having been converted into Inland Lots. The work was begun in the latter part of the year and had not reached completion at its close. A length of the main nullah, that on the east of I.L. 1926, measuring 207 feet, was undertaken, besides 138 feet of the branch nullah to the west of I.L. 1926. The inverts are of cement concrete, 4" thick, laid on a foundation of lime and cement concrete, and the side walls are of rubble masonry, built in lime mortar and finished with a coping of cement concrete. The main nullah averages 7' 0" wide by 10' 0" deep and the branch nullah 5′ 3′′ wide by 10′ 6′′ deep. A portion of the branch nullah, 93 feet in length, has been arched over with cement concrete to provide for its being crossed by a future public road. 1915 Estimates,.....$9,700.00 1915 Expenditure,.. 5,231.46 Total Estimates,. Expenditure to 31/12/15,.. $9,700.00 5,231.46 (f.) General Works.-The following is a statement of the works carried out under this heading:- (i.) Magazine Gap-District south of Gap ---Completion of item (iv) of last year's Report, (completed), (ii) Training nullah west of I.L. 1942, Conduit Road. including small branches, (completed) :- Length trained. Lin. Ft. Expenditure. Main stream, 220 $847.20 Branches, 291 385.68 (iii) Training stream-course west of old Pumping Station, Bonham Road, (completed), 287 $1,077.59 (iv.) Training stream-courses between Ship Street and Kennedy Road, (completed). 280 Cost of work.... $1,232.88 Less contribution by lessees, 350.00 $727.59 * A sum of $64.25 was erroneously debited to this sub-head instead of to sub-head (e). The expenditure therefore appears as $3,708.24 in Annexe B.
Baseline (Original)
P.W.E. Hongkong. 61 1915 Estimates, $7,000.00 Total Estimates, 1915 Expenditure, 3,643.99* Total Estimates, $7,000.00 Expenditure to 31/12/15, 3,643.99* (e.) Wongneichong Village-Extension of two nullahs cast and west of I.L. 1926.—This work forms a continuation of that under- taken in 1913, another Farm Lot (F.L. 45) having been converted into Inland Lots. The work was begun in the latter part of the year and had not reached completion at its close. A length of the main nullah,-that on the east of I.L. 1926,- ineasuring 207 feet, was undertaken, besides 138 feet of the branch nullah to the west of I.L. 1926. The inverts are of cement concrete, 4" thick, laid on a foundation of lime and cement concrete, and the side walls are of rubble masonry, built in lime mortar and finished with a coping of cement concrete. The main nullah averages 7' 0" wide by 100" deep and the branch nullah 5′ 3′′ wide by 10′ 6′′ deep. A portion of the branch nullah, 93 feet in length, has been arched over with cement concrete to provide for its being crossed by a future public road. 1915 Estimates,.....$9,700.00 1915 Expenditure,.. 5,231.46 Total Estimates,. Expenditure to 31/12/15,.. $9,700.00 5,231.46 (f.) General Works.-The following is a statement of the works carried out under this heading:- (1.) Magazine Gap-District south of Gap ---Completion of item (iv) of last year's Report, (complcted), (ii) Training nullah west of I.L. 1942, Con- duit Road. including small branches, (completed) :- Main stream, Branches,... (iii) Training stream-course west of old Pumping Station, Bonhamı Road, (completed), (iv.) Training stream-courses between Ship Street and Kennedy Road, (completed). Cost of work.... Length trained. Expendi- ture. Lin. Ft. FC 64.25 220 291} 847.20 287 385.68 $1,077.59 Less contribution by lessees, 350.00 280 727.59 * A sum of $64.25 was erroneously debited to this sub-head instead of to sub-head (e). The expenditure therefore appears as $3.708.24 in Annexe B.
2026-05-06 10:50:18 · Baseline
View content

P.W.E. Hongkong.

61

1915 Estimates, $7,000.00 Total Estimates,

1915 Expenditure, 3,643.99*

Total Estimates, $7,000.00 Expenditure to

31/12/15,

3,643.99*

(e.) Wongneichong Village-Extension of two nullahs cast and west of I.L. 1926.—This work forms a continuation of that under- taken in 1913, another Farm Lot (F.L. 45) having been converted into Inland Lots. The work was begun in the latter part of the year and had not reached completion at its close.

A length of the main nullah,-that on the east of I.L. 1926,- ineasuring 207 feet, was undertaken, besides 138 feet of the branch nullah to the west of I.L. 1926. The inverts are of cement concrete, 4" thick, laid on a foundation of lime and cement concrete, and the side walls are of rubble masonry, built in lime mortar and finished with a coping of cement concrete. The main nullah averages 7' 0" wide by 100" deep and the branch nullah 5′ 3′′ wide by 10′ 6′′ deep.

A portion of the branch nullah, 93 feet in length, has been arched over with cement concrete to provide for its being crossed by a future public road.

1915 Estimates,.....$9,700.00

1915 Expenditure,.. 5,231.46

Total Estimates,. Expenditure to 31/12/15,..

$9,700.00

5,231.46

(f.) General Works.-The following is a statement of the works

carried out under this heading:-

(1.) Magazine Gap-District south of Gap ---Completion of item (iv) of last year's Report, (complcted),

(ii) Training nullah west of I.L. 1942, Con- duit Road. including small branches, (completed) :-

Main stream,

Branches,...

(iii) Training stream-course west of old Pumping Station, Bonhamı Road, (completed),

(iv.) Training stream-courses between Ship Street and Kennedy Road, (completed).

Cost of work....

Length trained.

Expendi-

ture.

Lin. Ft.

FC

64.25

220

291}

847.20

287

385.68

$1,077.59

Less contribution by

lessees,

350.00

280

727.59

* A sum of $64.25 was erroneously debited to this sub-head instead of to sub-head (e). The expenditure therefore appears as $3.708.24 in Annexe B.