Q 25
P.W.R. Hongkong,
The following buildings, &c., mentioned in last year's Report were not completed by the 31st December, 1915:-
*7 Chinese houses, N.K.I.L. 41, Shamshuipo.
+7 European houses, I.L. 1926, Wongneichong.
Schoolhouse, I.L. 1937, Macdonnell Road.
Workshops and packing sheds. N.K.I.L. 53, Tai Wan.
School in connection with Rosary Church, K.I.L. 617, Chatham Road.
Forming sites for building operations, I.L.'s 1931, 1938 and 1948, Kennedy Road; I.L.'s 690 and 691, Bonham Road; I.L. 953, Belchers Street; K.I.L.'s 1283 and 1284, Ho Mun Tin; and K.I.L.'s 640 and 1267, Ma Tau Kok.
PUBLIC WORKS RECURRENT.
Hongkong.
47. Maintenance of Buildings.-The buildings upon which any considerable sum was expended were the following:-
Government Civil Hospital:-
Staff Quarters-General repairs and painting throughout, $3,982.91 Repairs to drains, etc., 335.85 $4,318.76 "A" Block-Sundry repairs, 416.07 Relaying tiles,... 288.73 704.80 "B" Block--General repairs and painting throughout, 2,985.77 Sundry repairs, 61.57 3,047.34 "C" Block-General repairs and painting throughout, 2,000.64 Maternity Block-General repairs and painting throughout, 1,008.77 Sundry repairs. 67.22 1,075.99 Operating Theatre -Minor repairs, 114.70 Chinese Staff Quarters--General repairs and painting throughout, 619.99 European Lunatic Asylum- General repairs and painting throughout, 1,369.05 Sundry repairs, 438.11 1,807.16 and painting throughout, Chinese Lunatic Asylum-General repairs 925.87 Carried forward,..... $14,615.25* These were grouped in last year's Report with 8 houses on N.K.I.L. 46 which have been completed.
+ Of the 10 houses mentioned in last year's Report, 3 were completed. This work was commenced in 1913 but progress on it has been suspended.
Q 25
P.W.R. Hongkong,
The following buildings, &c., mentioned in last year's Report were not completed by the 31st December, 1915:-
*7 Chinese houses, N.K.I.L. 41, Shamshuipo.
+7 European houses, I.L. 1926, Wongneichong.
Schoolhouse, I.L. 1937, Macdonnell Road.
Workshops and packing sheds. N.K.I.L. 53, Tai Wan.
School in connection with Rosary Church, K.I.L. 617, Chatham
Road.
Forming sites for building operations, I.L.'s 1931, 1938 and 1948, Kennedy Road; I.L.'s 690 and 691, Bonham Road; I.L. 953, Belchers Street; K.I.L.'s 1283 and 1284, Ho Mun Tin; and K.I.L.'s 640 and 1267, Ma Tau Kok.
PUBLIC WORKS RECURRENT.
Hongkong.
47. Maintenance of Buildings.-The buildings upon which any considerable sum was expended were the following:-
Government Civil Hospital:-
Staff Quarters-General repairs
and painting throughout,
$3,982.91
Repairs to drains, etc.,
335.85
$4,318.76
>>
"A Block-Sundry repairs,
416.07
Relaying tiles,...
288.73
704.80
"B" Block--General repairs
and painting throughout,
2,985.77
Sundry repairs,
61.57
3,047.34
"C" Block-General repairs and painting
throughout,
2,000.64
Maternity Block-General re-
pairs and painting through-
out,
1,008.77
Sundry repairs.
67.22
1,075.99
Operating Theatre -Minor repairs,
114.70
Chinese Staff Quarters--General repairs
and painting throughout,
619.99
European Lunatic Asylum-
General repairs and painting
throughout,
1,369.05
Sundry repairs,
438.11
1,807.16
and painting throughout,
Chinese Lunatic Asylum-General repairs
Carried forward,.....
* These were grouped in last year's Report with 8 houses on N.K,IL 46 which have been completed.
of the 10 houses mentioned in last year's Report, 3 were completed. This work was commenced in 1913 but progress on it has been suspended.
925.87
$14,615.25