AnnualReport-1914 — Page 478

Administrative Reports 行政報告書 All AI Reviewed

P.W.E. Kowloon.

Page 82

The construction of the slipway was carried out as an extra work under the contract for the reclamation of the area opposite K.M.L.s 29-31 and was completed. An indent for the steelwork for the pier was despatched in May but, owing to the outbreak of war, no advice of the materials had been received up to the end of the year.

A contract for the erection of the whole of the buildings was let to Messrs. Wing Lee & Co. on the 27th July and by the end of the year substantial progress had been made with all of them.

1914 Estimates, ......$33,000.00 .$33,000.00

Total Estimates, (exclusive of slipway),... $39,000.00 1914 Expenditure....... 9,380.63 31 12/14............. 9,380.63

132. Chinese Cemeteries,-Laying out new areas.—A statement of the works carried out under this heading will be found in paragraph 43 of this Report.

1914 Estimates, $3,000.00 1914 Expenditure, $1,174.70

133. Miscellaneous Works.-The following are the principal items of expenditure under this heading, representing in some cases only a part of the cost of the works in consequence of their execution extending over more than one year:-

Yaumati Vegetable Market :-

Kerbing, channelling and laying granolithic paving on west side of market, $1,424 Erecting kitchen and store, $606 $2,030.00

Yaumati Police Station :--

Constructing an additional room over the main gateway and installing electric light, $1,059 Constructing a reinforced concrete staircase to Sergeants' mess room and altering windows of European Detective's quarters, $503 $1,562.00

Kowloon Reservoir :-Constructing permanent quarters for Police Guard,

Mataukok Cattle Depôt — Inspector's Quarters-Substituting hardwood flooring laid on cement concrete for floors laid on wooden joists,

Slaughter House-Providing extra scalding pans, $1,016.56 Shroff's Quarters-Providing extra window and iron grilles to windows, $137 $30 $585.00

Page 82

...

(No further text is given to continue the proofreading)

Edit History

2026-05-06 09:07:26 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Kowloon. Page 82 The construction of the slipway was carried out as an extra work under the contract for the reclamation of the area opposite K.M.L.s 29-31 and was completed. An indent for the steelwork for the pier was despatched in May but, owing to the outbreak of war, no advice of the materials had been received up to the end of the year. A contract for the erection of the whole of the buildings was let to Messrs. Wing Lee & Co. on the 27th July and by the end of the year substantial progress had been made with all of them. 1914 Estimates, ......$33,000.00 .$33,000.00 Total Estimates, (exclusive of slipway),... $39,000.00 1914 Expenditure....... 9,380.63 31 12/14............. 9,380.63 132. Chinese Cemeteries,-Laying out new areas.—A statement of the works carried out under this heading will be found in paragraph 43 of this Report. 1914 Estimates, $3,000.00 1914 Expenditure, $1,174.70 133. Miscellaneous Works.-The following are the principal items of expenditure under this heading, representing in some cases only a part of the cost of the works in consequence of their execution extending over more than one year:- Yaumati Vegetable Market :- Kerbing, channelling and laying granolithic paving on west side of market, $1,424 Erecting kitchen and store, $606 $2,030.00 Yaumati Police Station :-- Constructing an additional room over the main gateway and installing electric light, $1,059 Constructing a reinforced concrete staircase to Sergeants' mess room and altering windows of European Detective's quarters, $503 $1,562.00 Kowloon Reservoir :-Constructing permanent quarters for Police Guard, Mataukok Cattle Depôt Inspector's Quarters-Substituting hardwood flooring laid on cement concrete for floors laid on wooden joists, Slaughter House-Providing extra scalding pans, $1,016.56 Shroff's Quarters-Providing extra window and iron grilles to windows, $137 $30 $585.00 Page 82 ... (No further text is given to continue the proofreading)
Baseline (Original)
P.W.E. Kowloon. P 82 The construction of the slipway was carried out as an extra work under the contract for the reclamation of the area opposite K.M.L.s 29-31 and was completed. An indent for the steelwork for the pier was despatched in May but, owing to the outbreak of war, no advice of the materials had been received up to the end of the year. A contract for the erection of the whole of the buildings was let to Messrs. Wing Lee & Co. on the 27th July and by the end of the year substantial progress had been made with all of them. 1914 Estimates, ......$33,000.00 .$33,000.00 | Total Estimates, (excln- sive of slipway),...$39,000.00 Expenditure to 1914 Expenditure....... 9,380.63 31 12/14............. 9.380,63 132. Chinese Cemeteries,-Laying out new areas.—A statement of the works carried out under this heading will be found in para- graph 43 of this Report. 1914 Estimates, 1914 Expenditure, $3,000.00 1,174.70 133. Miscellaneous Works.-The following are the principal items of expenditure under this heading, representing in some cases only a part of the cost of the works in consequence of their execution extending over more than one year:- Yaumati Vegetable Market :- Kerbing, channelling and laying grano- lithic paving on west side of market, $1,424 Erecting kitchen and store, 606 $2.030.00 Yaumati Police Station :-- Constructing an additional room over the 1,059 main gateway and installing electric light, Constructing a reinforced concrete stair- case to Sergeants' mess room and altering windows of European De- tective's quarters, Kowloon Reservoir :-Constructing permanent quarters for Police Guard, Mataukok Cattle Depôt Inspector's Quarters-Substituting hard- wood flooring laid on cement con- crete for floors laid on wooden joists, Slaughter House-Providing extra scald- 503 1.562 00 1,016.56 אן4 ing pans, 137 Shroff's Quarters-Providing extra win- dow and iron grilles to windows, 30 585.00
2026-05-06 09:07:26 · Baseline
View content

P.W.E. Kowloon.

P 82

The construction of the slipway was carried out as an extra work under the contract for the reclamation of the area opposite K.M.L.s 29-31 and was completed. An indent for the steelwork for the pier was despatched in May but, owing to the outbreak of war, no advice of the materials had been received up to the end of the year.

A contract for the erection of the whole of the buildings was let to Messrs. Wing Lee & Co. on the 27th July and by the end of the year substantial progress had been made with all of them.

1914 Estimates, ......$33,000.00 .$33,000.00

| Total Estimates, (excln-

sive of slipway),...$39,000.00 Expenditure to

1914 Expenditure....... 9,380.63

31 12/14.............

9.380,63

132. Chinese Cemeteries,-Laying out new areas.—A statement of the works carried out under this heading will be found in para- graph 43 of this Report.

1914 Estimates,

1914 Expenditure,

$3,000.00

1,174.70

133. Miscellaneous Works.-The following are the principal items of expenditure under this heading, representing in some cases only a part of the cost of the works in consequence of their execution extending over more than one year:-

Yaumati Vegetable Market :-

Kerbing, channelling and laying grano-

lithic paving on west side of market, $1,424 Erecting kitchen and store,

606

$2.030.00

Yaumati Police Station :--

Constructing an additional room over the

1,059

main gateway and installing electric light,

Constructing a reinforced concrete stair-

case to Sergeants' mess room and altering windows of European De- tective's quarters,

Kowloon Reservoir :-Constructing permanent

quarters for Police Guard,

Mataukok Cattle Depôt

Inspector's Quarters-Substituting hard- wood flooring laid on cement con- crete for floors laid on wooden joists, Slaughter House-Providing extra scald-

503

1.562 00

1,016.56

אן4

ing pans,

137

Shroff's Quarters-Providing extra win-

dow and iron grilles to windows,

30

585.00

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.