P 59
(ii.) Reconstructing invert of Mount Parker Catchwater, (completed), - $7,560
(iii) Substituting 3" main for old 2" main round Mount Kellett, (not completed), - 2,784
(iv.) Renewing portion of 5" main from No. 4 Motor, Bowen Road, to 650 service reservoir, (completed), - 1,186
(v.) Connecting up ends of existing mains near Wongneichong Village, (completed), - 1,267
(vi.) Connecting up ends of existing mains near Tai Hang Village, (completed), 999
(vii.) Providing floor plates and additional stays to valve spindles in valve well of Tytam Intermediate Reservoir, (completed), 762
(viii) Altering the position of No. 4 Tank, Peak, consequent on the sale of R.B.L. 133, (completed), 721
(ix) Extending water main at To Kwa Wan as far as K.M.L. 90, and erecting fountain for the supply of the Basel Mission School, (completed), 1,261
Item (i.) The reasons for this work were stated in last year's Report.
Item (ii.) This was necessary owing to the invert of the catchwater channel having been worn away by sand, &c., conveyed by the water during rainstorms. In reconstructing the invert, glazed half-pipes were inserted to take the dry-weather flow and the shape of the invert was improved.
Item (iii) The new main was laid, but the old main was not removed nor the road surface made good by the end of the year.
Item (iv.) This was necessary owing to the corrosion of the old pipes which had been laid in 1900.
Items (v.) & (vi.) These connections were made for the purpose of improving the circulation of water in the mains and affording better pressure.
Item (vii.) The provision of floor plates was found to be necessary in connection with the execution of ordinary maintenance work and repairs, and some additional support was also required for the valve spindles.
Item (viii.) Under the Conditions of Sale for R.B.L. 133, a sum of $500 was paid into the Treasury for the removal of the tank in question. As mentioned in last year's Report, this sum was credited to the Vote in 1910.
P 59
(ii.) Reconstructing invert of Mount Parker Catchwater,
(completed), -
(iii) Substituting 3" main for old 2" main round Mount
Kellett, (not completed),
-
(iv.) Renewing portion of 5" main from No. 4 Motor, Bowen Road, to 650 service reservoir, (com- pleted),
(v.) Connecting up ends of existing mains near
Wongneichong Village, (completed),
- $7,560
2,784
-
1,186
1,267
(vi.) Connecting up ends of existing mains near Tai
Hang Village, (completed),
999
(vii.) Providing floor plates and additional stays to valve spindles in valve well of Tytam Intermediate Reservoir, (completed),
762
(viii) Altering the position of No. 4 Tank, Peak, con- sequent on the sale of R.B.L. 133, (completed),
721
(ix) Extending water main at To Kwa Wan as far as K.M.L. 90, and erecting fountain for the supply of the Basel Mission School, (completed),
1,261
Item (i.) The reasons for this work were stated in last year's Report.
Item (i.) This was necessary owing to the invert of the catch- water channel having been worn away by sand, &c., conveyed by the water during rainstorms. In reconstructing the invert, glazed half- pipes were inserted to take the dry-weather flow and the shape of the invert was improved.
Item (iii) The new main was laid, but the old main was not removed nor the road surface made good by the end of the year.
Item (iv.) This was necessary owing to the corrosion of the old pipes which had been laid in 1900.
Items (v.) & (vi.) These connections were made for the pur- pose of improving the circulation of water in the mains and affording better pressure.
Item (vii.) The provision of floor plates was found to be neces- sary in connection with the execution of ordinary maintenance work and repairs, and some additional support was also required for the valve spindles.
Item (viii.) Under the Conditions of Sale for R.B.L. 133, a sum of $500 was paid into the Treasury for the removal of the tank in question. As mentioned in last year's Report, this sum was credited to the Vote in 1910.