Page 60
Item (ix.) his calls for no explanation.
With regard to Item (viii) in last year's Report, which was reported as 'not completed", no further work had to be carried out during 1911.
1911 Estimates, $25,000.00 1911 Expenditure, $17,828.86 Works not appearing in Estimates.119. Pier at Castle Peak Bay. This pier is 190 feet long and is, for the most part, constructed of rubble with a top width of 65 feet, the surface being finished with cement concrete. The outer end is constructed of timber with 12′′ x 12′′ hardwood piles and a platform 15′ × 15' to enable launches to get alongside. The approach road is carried on an embankment about 200 feet long, the slopes being protected by rubble pitching. The surfacing is of decomposed granite.
1911 Estimates, Total Estimates,...$3,000.00 1911 Expenditure,... $2,599.19 Expenditure to 31/12/11......... 2,937.19120. Compensation to Squatters in Hok Un Village.-- This item was described in last year's Report, compensation being paid for some additional houses.
1911 Estimates, Total Estimates,...$3,459.00 1911 Expenditure,... $405.00 Expenditure to 31/12/11......... 2,570.00121. New Quarters at Tai Po for Public Works Department Officers. The expenditure under this heading consisted principally of a transfer to Railway funds for the value of the bungalow taken over from the Railway as referred to in last year's Report.
1911 Estimates,... Total Estimates,...$5,752.00 1911 Expenditure,... $5,582.09 Expenditure to 31/12/11......... 5,582.09122. Fan Ling Branch, Kowloon-Canton Railway.—The expenditure under this heading consisted merely of a transfer to Railway funds on account of earthworks executed by that Department in connection with the light railway to Sha Tau Kok. As explained in paragraph 99 of this Report, the construction of the road to Sha Tau Kok by the Public Works Department terminated at Au Ha Gap, all work to the eastward of that point being executed by the Railway Department.
1911 Estimates, Total Estimates,..... 1911 Expenditure,... $17,277.02 Expenditure to 31/12/11......... $17,277.02123. Resumption of Land in connection with the laying out of Survey District No. 1.-This consisted merely of the resumption of 3
Page 450
Page 451
P 60
Item (ix.) his calls for no explanation.
With regard to Item (viii) in last year's Report, which was reported as 'not completed", no further work had to be carried out during 1911.
1911 Estimates,
1911 Expenditure,
Works not appearing in Estimates.
$25,000.00 17,828.86
119. Pier at Castle Peak Bay. This pier is 190 feet long and is, for the most part, constructed of rubble with a top width of 65 feet, the surface being finished with cement concrete. The outer end is constructed of timber with 12′′ x 12′′ hardwood piles and a platform 15′ × 15' to enable launches to get alongside. The approach road is carried on an embankment about 200 feet long, the slopes being protected by rubble pitching. The surfacing is of decomposed granite.
1911 Estimates,
Total Estimates,...$3,000.00
1911 Expenditure,... $2,599.19 Expenditure to
31/12/11......... 2,937.19
120. Compensation to Squatters in Hok Un Village.-- This item was described in last year's Report, compensation beingpaid for some additional houses.
1911 Estimates,
Total Estimates,...$3,459.00
31/12/11. 2,570.00
1911 Expenditure,... $405.00 Expenditure to
—
121. New Quarters at Tai Po for Public Works Department Officers. The expenditure under this heading consisted principally of a transfer to Railway funds for the value of the bungalow taken over from the Railway as referred to in last year's Report.
1911 Estimates,...
Total Estimates,...$5,752.00 1911 Expenditure,... $5,582.09 | Expenditure to
... 5,582.09
31/12, 11.........
122. Fan Ling Branch, Kowloon-Canton Railway.—The ex- penditure under this heading consisted merely of a transfer to Railway funds on account of earthworks executed by that Depart- ment in connection with the light railway to Sha Tau Kok. As explained in paragraph 99 of this Report, the construction of the road to Sha Tau Kok by the Public Works Department terminated at Au Ha Gap. all work to the castward of that point being executed by the Railway Department.
1911 Estimates,
Total Estimates,.....
1911 Expenditure,...$17,277.02 Expenditure to
31/12/11, $17,277.02
123. Resumption of Land in connection with the laying out of Survey District No. 1.-This consisted merely of the resumption of 3
Page 450Page 451
No comments yet.
Private notes are available after approval.