could be arrived at, all the claims, with the exception of one, were so referred. One claim was under consideration with a view to an amicable settlement.
1911 Estimates, $12,500.00 | Total Estimates, ...$87,000.00
427.00 Expenditure to 31/12/11, ...1,666.00
1911 Estimates $12,500.00 Total Estimates $87,000.00 Expenditure to 31/12/11 427.00 1,666.00111. Reclamation between Kowloon Marine Lot 83 and Hunghom Marine Lot 1, Hunghom.-This work was completed in November. A description of it was contained in last year's Report.
1911 Estimates $7,000.00 1911 Sup. Vote $5,620.00 Total $12,620.00 1911 Expenditure $12,580.36* Total Estimates $17,000.00 Expenditure to 31/12/11 $16,848.36*112. Improvement of Ap Liu Village.-Substantial progress was made with the filling-in of the area to form a new site for the village, 65,000 cubic yards of material being deposited and 800 cubic yards of rubble pitching set. The expenditure under the Contract amounted to $9,426.50 whilst sums amounting to $16,325.25 were drawn for disbursement in the shape of compensation for land and buildings.
1911 Estimates $13,000.00 1911 Sup. Vote $14,000.00 Total $27,000.00 1911 Expenditure $25,751.75 Total Estimates $28,800.00 Expenditure to 31/12/11 $25,751.75113. Improvement of Tai Hang Village.-The works described in last year's Report were continued, 16 houses and 24 pigsties being demolished and reconstructed on new and improved sites during the year.
1911 Estimates $6,000.00 Total Estimates $15,500.00 1911 Expenditure $5,865.00 Expenditure to 31/12/11 $10,349.81114. Public Health and Buildings Ordinance, 1903-Compensation. This vote provides for the resumption of areas to form scavenging lanes and for the payment of compensation in connection with the removal of houses over the ends of private streets or lanes or for the loss of storeys resulting from the operation of section 188 sub-section (3) of the Public Health and Buildings Ordinance. In some cases, where houses were of moderate depth, a modification of the open space requirements has been granted, the owners agreeing to provide a lane without compensation in consideration of being permitted to count it as part of their open space.
1911 Estimates $12,000.00 1911 Supplementary Vote $564.00 Total $12,564.00 1911 Expenditure $12,563.09* Includes a sum of $2,095.50, being retention money under the Contract, transferred to "Deposits not available".
Page 54
- P 54
could be arrived at, all the claims, with the exception of one, were so referred. One claim was under consideration with a view to an
amicable settlement.
1911 Estimates,
1911 Expenditure,
$12,500.00 | Total Estimates, ...$87,000.00
427.00 Expenditure to
31/12/11, ...1,666.00
+
111. Reclamation between Kowloon Marine Lot 83 and Hung- hom Marine Lot 1, Hunghom.-This work was completed in Novem- ber. A description of it was contained in last year's Report.
1911 Estimates, ...$ 7,000.00 1911 Sup. Vote, 5,620.00
12,620.00
1911 Expenditure, 12,580.36*
Total Estimates, $17,000.00 Expenditure to
31/12/11,
16,848.36*
112. Improvement of Ap Liu Village.-Substantial progress was made with the filling-in of the area to form a new site for the village, 65,000 cubic yards of material being deposited and 800 cubic yards of rubble pitching set. The expenditure under the Con- tract amounted to $9,426.50 whilst sums amounting to $16,325.25 were drawn for disbursement in the shape of compensation for land and buildings.
1911 Estimates, - $13,000.00 1911 Sup. Vote, 14,000.00
$27,000.00
1911 Expenditure, 25,751.75
-
Total Estimates, - - $28,800.00 Expenditure to
31/12/11,
-
25,751.75
113. Improvement of Tai Hang Village.-The works described in last year's Report were continued, 16 houses and 24 pigsties being demolished and reconstructed on new and improved sites during the year.
1911 Estimates,
$6,000.00 Total Estimates, - - $15,500.00 1911 Expenditure, 5,865.00 Expenditure to
31/12/11, 10,349.81
114. Public Health and Buildings Ordinance, 1903-Com- pensation. This vote provides for the resumption of areas to form scavenging lanes and for the payment of compensation in connection with the removal of houses over the ends of private streets or lanes or for the loss of storeys resulting from the operation of section 188 sub-section (3) of the Public Health and Buildings Ordinance. In
• some cases, where houses were of moderate depth, a modification of the open space requirements has been granted, the owners agreeing to provide a lane without compensation in consideration of being permitted to count it as part of their open space.
1911 Estimates,
1911 Supplementary Vote, ·
$12,000.00 564.00
1911 Expenditure,
$12,564 00
12,563.09
* Includes a sum of $2,095,50, being retention money under the Contract, transferred to " Deposits not available”,