2C
PUBLIC RECORD OFFICE
Reference :-
TUTTIC.O.885
ון
7
PUBLIC RECORD OFFICE, LONDON
ALLY WITHOUT PERMISSION OF THE BE REPRODUCED PHOTOGRAPHIC:
COPYRIGHT PHOTOGRAPH—NOT TO
38
purpose of this Article, forthwith re-transfer and deliver to the Contractors the policies in respect of which such money shall be payable, and do all acts necessary to enable the Contractors to obtain the full benefit thereof. The Contractors shall have full authority to collect and recover the moneys payable under such policies, and to make such settlements or agreements as to the amounts to be paid thereon as they think fit; and subject us hereinafter provided, the moneys received under the said policies, after deduction of the expenses of recovery thereof, shall, unless otherwise agreed, be deposited at interest with Messrs. Barclay, Bevan & Co., Bafikers, in the joint names of the Company and the Contractors, or their respective nominees.
Article 16. The Contractors shall, upon receipt of the said policies, with all practi- cable despatch, replace the Cable so lost, destroyed or damaged, with similar type or types of Cable or other Cable certified by the Engineer to be suitable for the purposes of this Contract, and the Contractors shall use and apply the substituted Cable (when certified by the Engineer as satisfactory) for the purposes of this Contract accordingly.
Article 17. The moneys referred to in Article 15, and all interest thereon, shall be paid to the Contractors upon the Certificate of the Engineer of the shipment of the whole of the substituted Cable, and that the condition thereof when shipped was satisfactory, and the Contractors shall have no further claitu upon the Company in respect of the substituted Cable.
(Signed) W. SHUTER,
FORM OF TENDER No. 1. (SIEMENS BROS.)
To Messrs CLARK, FORDE & TAYLOR,
Managing Director.
1, Great Winchester Street, E.C.
14th August, 1900, Referring to the proposed "Pacific Cable" and to the printed “Forms of Contract, Specification and Tender "received from you :—
WE, the undersigned, hereby agree to manufacture and lay the Types and Lengths of Cable described in the Contracts and Specifications Nos, 1, 2 and 3, contained in the said print, and to carry out the manufacture and laying of such Cable in accordance with the terins of the said Contracts and Specifications, and to complete the manufacture and laying of the same by the undermentioned dates, for the undermentioned suns, viz. :—
Probable late of completion of Laying.
Contract tur! Specification,
Price.
Date of completion of Manufacture.
No. 1.
Vancouver-Fanning Island .......
1,235,000
Eight months
Twelve months.
S.No. 2.
Fanning Island—Fiji
No. 3
Fiji-Norfolk Island... .......
Norfolk Island—Queensland.....
Norfolk Island—New Zealand
512,200
Five months
Ten months.
461,500
Five-and-half months Ten months.
The above sums are based on cash payments in instalments as described in the Contracts.
This Tender may be accepted as a whole, or as to any one or two of its parts, aud we agree to hold it open for acceptance until 14th October, 1900,
12, Quern Anne's Gate,
Westminster, S.W.
(Signed)
SIEMENS BROS, & Co., Ltd., G. VON CHAUVIN,
Managing Director.
DEAR SIRS,
39
Letter from Messrs. SIEMENS Bros.
12, Queen Anne's Gate, Westminster,
London, S.W., 14th August, 1900.
HEREWITH We beg leave to hand you our Tenders for the three sections of the Pacific Cable and for the Sounding and Surveying Operations.
Our price for any two or all of the sections would be the sum of the prices quoted for each single section, but the time of completion of manufacture and laying would be considerably less than the sum of the times needed for each section in question.
We would submit the core to a hydraulic pressure equal at least to the one to which the cable will be subject after having been submerged, so as to ensure the removal of air-bubbles, in addition to the test by an E.M.F. of 5,000 volts us provided for in the Specification.
As fully explained in the answer to Question No. 646 of the Pacific Cable Committe (1896), the two chief causes of trouble in submarine cables are air-bubbles and small particles of foreign matter. By the high voltage test the latter can be discovered, but the air-lubbles will not be detected unless hydraulic pressure is applied.
The efficiency of these tests has been demonstrated by the success of the Atlantic Cable which we have laid in 1894 for the Commercial Cable Company, and which has proved itself to be entirely free from faults during the laying and has remained so since.
We would also employ, in laying any of the cables, our method for insuring the proper percentage of slack by paying-out au auxiliary wire. We have found this system to prove of great value if ever repairing operations have to be conducted, especially in great depths such as occur in the Pacific.
In submitting our Tender herewith, we would suggest that the Deep-Sea Cables should be of the close-armoured type, which we have found very satisfactory.
For the Deep-Sea Cable in Contract No. 1 we woukl thus, for instance, propose a Specification as follows :—
CONTRACT No. 1.
"(D) Type D. (Main Cable). The served core to be covered with 22 gal-,
vanized steel wires, cach wire being well covered with a bituminous compound."
...
The galvanized steel wires to be No. 14 BW.G,, equal to 083 of an inch, etc,'
The rest of Clause (1) and the following clauses to remain unaltered, except that the sheathing wire for Type D. is to be treated the same as prescribed in Clause (L) for . the sheathing wires of Types A.A., E., and B.
This adoption of close-sheathing will increase the breaking strain of the D. Type by more than 20% (twenty per cent.).
Contract No. 2%
*(-1) Type D (Light-Deep-Sea). The served core to be covered with 17 gal vanized steel wires, each wire being well-covered with a preservative compound.”
The galvanized steel wires to be No. 14 BW.G., equal to 083 of an inch, ete." The rest of Clause (J) and the following clauses to remain unaltered, except that the sheathing wire for D Type is to be treated the same as prescribed in Clause (M) for the sheathing wires of Types A.A., E., B. and D3.
The adoption of close sheathing would increase the breaking strain of the D Type by a little over 5% (five per cent.).
The advantages which we have found practice to result from this alteration are that the breaking strain is increased, and that the danger of galvanic corrosion is avoided.
We have in our possession a specimen of picked-up cable, constructed with separately covered sheathing wire, in which such corrosion had extended for miles, and in places some of the sheathing wires had been completely caten away. The possibility of such action taking place can easily be proved by placing two taped wires into salt water and connecting their ends protruding from the liquid through a galvanometer, when a current will be observed.
No comments yet.
Private notes are available after approval.