4.
-
Route 3
The Kwai Chung and Tsing Yi sections of Route 3 are part of the ACP. They comprise the Cheung Ching Tunnel, the Rambler Channel Bridge and the Kwai Chung Viaduct, and are about 75 per cent complete.
On Tsing Yi Island, tunnelling and carriageway works inside the 1.6-kilometre tunnel have been completed.
The 500-kilometre bridge structure across the Rambler Channel between Tsing Yi Island and Kwai Chung has been completed and linked to the Cheung Ching Tunnel.
Construction of the superstructure for the Kwai Chung Viaduct is continuing with good progress along the busy Kwai Chung Road.
West Kowloon Expressway
The 4.2-kilometre West Kowloon Expressway is about 67 per cent complete.
Work on the expressway's elevated northern section on the West Kowloon Reclamation is substantially complete. For the southern section, works continue to progress on piling for bridges and footbridges, culverts and retaining walls.
Lantau Fixed Crossing
Linking Lantau Island to Tsing Yi and Route 3 will be the Lantau Fixed Crossing, which comprises the 820-metre Kap Shui Mun cable-stayed bridge, the Ma Wan Viaduct and the 2.2-kilometre Tsing Ma suspension bridge. Overall, this project is about 77 per cent complete.
Work on the main decks of the Kap Shui Mun Bridge and the Tsing Ma Bridge is nearing completion.
So far, 29 of 39 deck units have been lifted into place on the Kap Shui Mun Bridge and 42 of 51 on the Tsing Ma Bridge,
Completion of the lifting work early this year will be followed by construction of the railway track form, electrical and mechanical works, and work on public lighting and road surfacing.
A