FINAL STAGE ON LEI MUK SHUE ESTATE

Work To Begin Next Month

Construction of the final stage of the $76 million Lei Muk Shue

Government Low Cost Housing Estate in Kwai Chung will start next month to provide homes for some 18,800 people.

Seven multi-storey blocks of the estate were completed more than a

year ago and have been taken up by about 36,000 residents.

The final stage includes two 22-storey, one 15-storey and three

seven-storey domestic blocks.

Work is expected to be completed in two and a half years.

Included in this stage will be a commercial centre with a department

The building will be so constructed as to allow shopkeepers

to instal their own air-conditioners. The roof will be used for social activities.

store and a restaurant.

A modular market with more than 60 stalls will be provided. The rooftop

of the market will be turned into a sitting-out area.

Social facilities will include a day nursery and a multi-purpose welfare

hall. A site within the estate has been reserved for a cinema.

In addition, more than four acres of land has been set aside for

recreation grounds. Eight basketball courts and a soccer pitch will be provided.

Three primary schools will be built and three adjacent sites have been

set aside for secondary schools.

Two bus termini have been planned and there will be about 300 parking

spaces for private cars, of which 170 will be covered.